| 1 | Item No 1-\"Excavationforroadwayinearth,soilofallsorts,sand,gravelorsoftmurumincluding dressing section to the required grade, camber and side slopes and conveying the excavated materialswithallliftsuptoaleadof50m.andspreadingforembankmentorstackingasdirected.2.10 |
| 2 | Item No 1 B ) Excavation for roadway in hard rock by wedging and chiselling or line drilling includingdressing section to the required grade, camber and side slopes and conveying theexcavated materials with all lifts upto a lead of 50m. and spreading for embankment orstacking as directed. |
| 3 | Item No 2-Supplying 60 mm Laterite Stone Metal At The Road Side For Metal including Conveying &Stocking etc.R A2 |
| 4 | Item No 3-Supplying soft murum at the road site, including conveying and stacking complete. |
| 5 | Item No 4-Spreading80/60 mm metal for road work including sectionong etc complete as directed by Engineer in charge . 50.58 |
| 6 | Item No 5-Spreading hard murum/ soft murrum/ gravel or kankar for side width complete2.30 |
| 7 | Item No 6-Compacting For 60mm Lat.Stone Metel Layers With Power Roller including Necessary Labour Materials And Artificial Watering Etc. |
| 8 | Item No 7-Providingandconstructing50mm.thickModified PenetrationMacadam(MPM) road surface including all mataerials, preparing the existing road surface, spreading 40mm. stone metal layers 100% crusher broken metal with conical crusher plant heating and spraying the [email protected]/SquareMetre,spreading12mm.sizechips compactingwith staticrollerhavingweight8to10MT.toachivethedesireddegreeof compactionas per Technical SpecificationClause 506 etc. complete.Including picking of existing WBM surface.(VG-30 bulk bitumen rates are considered to arrive at rates) R A 2 |
| 9 | Item No 8-Providing 20mm Thick Premix bituminous Carpet including Supplying All Materials Preparing And Cleaning The Bese Heating Bitumen Applying Tack Coat At Specified Rate Mixing Hot Bitumen And Chips Laying The Carpet Layer And Compacting R A3 |
| 10 | Item No 9 -Providing bituminous Type A liquid seal coat on bituminous surface including supplying all materialsandbitumenofspecifiedgrade preparingexistingroadsurface,heatingand applying bitumen @ 0.98 KilogramSquare Metre. by mechanical means, spreading chips and rolling, by static roller having weight 8 to 10 MT. etc. complete. (VG-30 bulk bitumen rates are considered to arrive at rates) R A4 |
| 11 | Item No 10-\"Providing and laying cement concrete pipe of IS 458:2003 NP-2 class of 600mm diameter in proper line, level and slope including providing and fixing collars in cement mortar 1:2 andcuring etc. complete.\"11.09 |
| 12 | 450mm |
| 13 | Item No 11 - Providing laterite stone masonry in C. M. 1:6 in foundation & plinth including striking joints on the unexposed faces & watering complete.As per New Supplimentry |
| 14 | Item No 11-Providing And Fixing Board Displaying information Such As Name of Work Tender Cost Name of Contractor Works Complation etc. |
| 15 | Quallity Control Material Testing Charges |
| 16 | A)Extraction Test (OGC) |
| 17 | B)Water Absorption,Specific Gravity ,Impact Value,Crushing Value |
| 18 | C)Penetration Softening Point, Flash &Fire Point,Specific Gravity |
| 19 | Item No 12Royalty Charges 80mm Lat/Trap Metal |