| 1 | Excavation in foundation in ordinary soil (loam, clay or sand) including lift upto 1.50 M lead upto 30 M and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by Engineer-in-charge upto a distance of 30 M from the foundation trenches. (S.I. No. 251a) /2022 |
| 2 | Earthwork in cutting or in embankment in ordinary soil excavation to be in the form of regular pits not exceeding 0.50 M. in depth and earth work in embankment to be in 20 cm. layers including remming and dressing the surface to required levels and slopes and also including 1.50 M. lift and 30 M. lead. the earth from cutting to be used in making embankment or to be deposited as spoil banks with in 30 M. distance as directed by the Engineer-in charge. (Royalty removed by Govt.) for small works/Abadi area (where machine can not moveI S.I. No. 253(a)/2022 |
| 3 | Cement Concrete with 4cm. gauge approved stone ballast, coarse sand and cement in the proportion of 8:4:1 including supply of all materials, labour, T&P etc. required for proper completion of the work. (S.I. No. 281/2022) |
| 4 | Construction of granular sub-base by providing coarse graded material, sperading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401 (Grade-I) (Ref. to Mort&H Specification No. 401) |
| 5 | RCC work with cement, approved Coarse sand and 40mm stone grit in proportion of 1:1.5:3 in raft and foundation excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc. and supply of all materials, labour, T&P etc. required for proper completion of the work, including cost of binding wire. (S.I. No. 287a/2022) |
| 6 | R.C.C. work with cement approved corsand & 2 cm gauge stone grit in proportion of 1:1.5:3 in slab Excluding supply of reinforcement and its bending, but including its fixing and binding the same waith 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc. and supply of all materials, labour, Tools & plants etc. required for proper completion of the work including cost of binding wire. The rate excludes making of drip course which shall be paid extra. (S.I. No. 284(a)/2022) |
| 7 | M.S (Tor steel or plain) work in plain work such as RCC or RB work including bending for proper shape and including supply of steel and its wastage, bend, hooks and authorized over lapping shall be measured and including cost of binding wire (S.I. No. 504/2022) A.R. |
| 8 | Providing & laying of interlocking concrete Block Pavement having thickness 80mm as per drawings and technical specification Clause 1504 (Exclusive G.S.B.) (S.I. No New Item 14) |
| 9 | Disposal of dismentaled materials and earth upto 2.0 km distance. (S.I. No 261b+231a/2022) |
| 10 | Cement concrete with 2cm gauge approved stone grit, coarse sand & cement in proportion of 1:1.5:3 in cc pavment (thickness as per design) cement coarse & fine aggregate confirming to IS standred mixed inconcrete mixer/plant of not less than 0.2 cum capacity and appropriate weight batcher using approved mix design, laid in approved fixed from work(steel channel) laying & fixing of 125 micron thick polythene film, wedges, steel plates including levelling the form work spreding the concrete with shovles. rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including hassion cloth for curring of concrete pavments for not less then 14 days, curing compound (Where specified) and water finishing to lines and gradeincludings supply of all materials, labour Tools &plants etc. required for proper completion of work andalso includin complete shifting ofRecron38 fibre reinforcement materials etcl & concrete etc S.I. No. New Item 9/2022 |
| 11 | S/F of sign Marble board (Pre Approved Rate) |