| 1 | Hospital road - Andiappan koil road ( from Ondikadai ) (KM 0/0 - 1/34) |
| 2 | Clearing the Scrub jungle by uprooting including all cutting charges and disposing of the products and clearing as directed by the departmental officers including all incidental charges etc., complete. |
| 3 | Km 0/0-2/6 |
| 4 | Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 25mm using 13.20mm IRC size HBG metal |
| 5 | Km 0/0-1/0 |
| 6 | Km 1/0-2/0 |
| 7 | Provision for Hecta Metre Stone - Nos |
| 8 | Ladies seat road - TV station road (KM 0/0 - 0/6) |
| 9 | Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 25mm using 13.20mm IRC size HBG metal |
| 10 | KM 0/0-0/6 |
| 11 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 12 | KM 0/0-0/6 |
| 13 | Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. |
| 14 | KM 0/0-0/6 |
| 15 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., |
| 16 | KM 0/0-0/6 |
| 17 | BITUMINOUS CONCRETE 25/30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete asper specification using CMP as per clause 507 of MORTH Rev-5 |
| 18 | KM 0/0-0/6 |
| 19 | Nagalur Puthur road - Muluvi road (KM 0/0 - 1/57) |
| 20 | Clearing the Scrub jungle by uprooting including all cutting charges and disposing of the products and clearing as directed by the departmental officers including all incidental charges etc., complete. |
| 21 | KM 0/0 - 1/57 |
| 22 | Providing and laying including cost and conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by power roller to achieve the required Proctor density at 100% compaction at Optimum moisture content and hire fuel charges for powerroller, watersprinkler and all other incidental charges such as traffic barricading and providing dangerlights etc. comp for base-course and side berms. |
| 23 | KM 0/0 - 1/57 |
| 24 | Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m |
| 25 | KM 0/0 - 1/57 |
| 26 | Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 25mm using 13.20mm IRC size HBG metal |
| 27 | KM 0/0 - 1/57 |
| 28 | Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50mm using 45mm IRC size HBG metal |
| 29 | KM 0/0 - 1/57 |
| 30 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) 250 mm thick, including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory Soil Compactor to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as pwe clause 406 of MORTH Rev-5 |
| 31 | KM 0/0 - 1/57 |
| 32 | Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. |
| 33 | KM 0/0 - 1/57 |
| 34 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., |
| 35 | KM 0/0 - 1/57 |
| 36 | BITUMINOUS CONCRETE 25 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5 |
| 37 | KM 0/0 - 1/57 |
| 38 | Provision for Hecta Metre Stone - Nos |
| 39 | Provision for KM Stone Repainting |
| 40 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} Please Enable Macros to View BoQ information |