| 1 | Dismantling of existing B.T. Surface (flexible Pavement) to a depth of 50 mm. manually including loading of dismantled material to transport vehicle at site excluding lead charges |
| 2 | Excavation for catch / side water gutter in Hard murum strata to the specified section including stacking the excavated stuff in a regular bund and disposing of unsuitable or excess stuff as directed. |
| 3 | Excavation for roadway in earth, soil of all sorts, sand, gravel or soft murum including dressing section to the requiredgrade,camberandside slopesandconveying the excavatedmaterialswithallliftsuptoaleadof 50m. and spreading for embankment or stacking as directed. |
| 4 | Supplying trap/granite/quartzite /gneiss stone metal of required size by bringing the boulders / Rubble at the road side breaking them to required gradation including conveying the boulders /Rubble and stacking the broken metal etc. complete . (Prior approval of sample stack of broken metal by the Ex. Engineer is necessary the date of approval will form part of the measurements)a)80 mm Metal, By breaking Boulders (Hand broken). |
| 5 | Supplying trap/granite/quartzite /gneiss stone metal of required size by bringing the boulders / Rubble at the road side breaking them to required gradation including conveying the boulders /Rubble and stacking the broken metal etc. complete . (Prior approval of sample stack of broken metal by the Ex. Engineer is necessary the date of approval will form part of the measurements)(a)40 mm Metal, By breaking Boulders (Hand broken). |
| 6 | Supplying hard murum/ kankar at the road site, including conveying and stacking complete. |
| 7 | Supplying soft murum at the road site, including conveying and stacking complete. |
| 8 | Spreading 80/40 mm metal for road work including sectionong etc complete as directed by Engineer in charge . |
| 9 | Spreading hard murum/ soft murrum/ gravel or kankar for side width complete |
| 10 | Compacting the sub grade/gravel/oversize metal (200 mm loose) layers for all width with Power roller having weight 8 to 10 MT. including necessary, labour, materials and artificial watering complete |
| 11 | Compacting the sub grade / gravel / size metal (100 mm loose) layers for all widths with Power roller having weight 8 to 10 MT. including necessary, labour, materials and artificial watering complete. |
| 12 | Compacting the hard murum side widths including laying in layers on each side with power roller including artificial watering etc. complete. |
| 13 | Providing and laying in situ / ready mix / ready mix M10cement concrete of trap/ granite/ quartzite/gneissmetalinfoundationincludingnecessarycentering,formwork,bailingout water, compacting and curing etc. complete. (with fully automatic micro processor based PLC with SCADA enabled with reversible drum type mixer/ concrete batch mix plant (pan mixer) with natural /artifical sand) |
| 14 | Providing and laying in situ cement concrete M -30 with tremix treatment for 200 mm thickness for Concrete Road is including laying plastic sheet for 125 micron thickness with groove cutting of 4 mm wide and 20 mm deep with necessary refilling with bitumen ( excluding reinforcement) with coarse and fine aggregate ( natural sand/ VSI grade finely washed crushed sand) etc. complete |
| 15 | Providing and fixing board displaying information, such as \"Name of work, Tender cost, Name of Contractor, Work completion and liability period etc\", having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm)thickmildsteelsheetpaintedwithonecoatofZincchromatestovingprimerandtwocoatsof enamelpaintonfrontside andgreystove enamelon |
| 16 | ROYALTY FOR OTHER MINERALS |
| 17 | Laboratory test charges for concrete |
| 18 | ADD 18 % GST |
| 19 | ADD 1% LABOUR INSURANCE |