| 1 | Providing Keymen to watch out Daily routine maintenance work of railway track from Plant railway gate to take-off point at Panki Dham stn.( work include Patroling of track,checking of Fishplate joints, Fish bolts, Alignment of track, regular cleaning of check rails at both L-Xings and other Deficiency if any)0128 (DSR2023) |
| 2 | Through packing of track, as per procedure prescribed in latest edition of Indian Railways Permanent Way Manual.For PSC sleeper Track with Sleeper Density of 1540 Sleepers/Km or more( 800X3=2400) IRUSSOR Code131031 |
| 3 | Quick cutting with abrasive rail cutter of all types of rail sections including wear resistant, head hardened rails up to 110 UTS, with contractors tools & plants, equipment, consumable with all lead & lift etc. complete as directed by Engineer in-charge. Abrasive Rail Cutter will be as per RDSO Specification No. TM/SM/1 (Rev. 01 of 2012) with latest status of RDSO; Rail Cutting Wheel Abrasive Disc will be as per RDSO Specification No.TM/SM/2 (Rev. 01 of 2020) ( 60Kg- 110/90 UTS on running line )IRUSSOR Code 161014 |
| 4 | Hiring of machinery for minor miscellaneous works for short duration including operator/driver, fuel, lubricants and consumable. The contractor shall arrange all statutory permits as required by rules and regulations prevailing in the area of work. Payment shall be made for actual working hours at site. JCB Backhoe Loaders 3DX Plus or similar with minimum 1.10 cum bucket capacity IRUSSOR Code 211200 |
| 5 | Pulling & positioning of rails accurately on cess including supporting rails, providing required gap and squaring at ends for renewal preparation, as directed by Engineer in-charge.061011 Up to 40 m long rail panel RM 8.49 IRUSSOR Code61010 |
| 6 | Replacement of any type of sleepers in track with PSC sleepers lying on cess or at Bridge Approaches for casual renewal at isolated locations with all fittings complete to specified gauge & cross level with contractor’s tools including packing and dressing of ballast, as directed by Engineer in-charge. Released materials shall be neatly stacked and handed over at specified location within an average lead of 250 m or near either side of Bridge approaches as directed. 062031 Locations other than Ballasted Deck Bridge IRUSSOR Code 62030 |
| 7 | Fixing of fish plates with fish bolts on a joint of all rail sections duly lubricating fish plates/bolts with contractor\"s grease graphite in runningtrack condition including transportation of fish plates and fish bolts fromnearest station / store / level crossing. Note: Rail cutting & drilling to be paid separately .063011 Fish plates with 4 fish bolts. Joint 179.45 IRUSSOR Code 63010 |
| 8 | Through replacement of Grooved Rubber Sole pads(GRSP) on PSC sleepers duly removing the ERCs and liners and replacing the GRSP by just lifting the rail after cleaning the rail seat, refixing the liner and ERC after greasing of ERCs, liners and Liner contact area including sealing with Contractor\"s Grease Graphite Grade \"O\" (IS:408) duly cleaning of rust/scale of ERC, Metal /GFN liners & SGCI insert by using wire brush, scrapper/sand emery paper etc., with all contractor’s labour, tools, plants including collection and stacking of released materials at nominated locations within SSE Jurisdiction and as directed byEngineer-in-Charge.Note: GRSP will be supplied at SSE/stores/depIRUSSOR Code 63040 |
| 9 | Lubrication of fish plated rail joints under traffic, by using Grease Graphite Grade \"O\" (IS:408) and Black oil supplied by contractor, for all types of rail sections as per procedure laid down in latest version of IRPWM and as directed by Engineer In charge. Note: Release U/S bolt & nuts is to be deposited back. If any fish bolts is jammed it should be cut with chisel and hammer and replaced with fresh fish bolt supplied.IRUSSOR Code 63050 |
| 10 | Removing seized ERC from SGCI inserts of existing track by using suitable approved chemicals and re-fixing after greasing of insert eye and ERC with Contractor\"s grease of specified quality as per provisions of IRPWM, as directed by Engineer in-charge.Note: 1.List of Seized ERC along with location shall be prepared after inspection of SSE/P.Way and marked prior to execution of this item. 2. Due care shall be taken to avoid any damage to the sleeper 3.A penalty of 50% of the basic cost of new sleeper in nearest sleeper factory shall be levied on each, if SGCI insert is broken or sleeper gets cracked in the process. IRUSSOR Code 63100 |
| 11 | Lubrication of gauge face of rail on curves, cross overs, points & crossings, turn-in curves and at locations as required with contractor\"s grease graphite grade \"O\" IS 408 and as directed. IRUSSOR Code 63110 |
| 12 | Supplying and spraying in specified proportion Weedicide Chemical, capable to kill entire weed on track / cess / embankment with all labour, material, tools & plants etc. complete job in all respect. Scientific name of the chemical is Isopropylamine Salt of Glyphosate, in which active ingredient is Glyphosate (41%), colour is light amber to brownish, very low in toxicity and has favourable environmental characteristics. It will be ensured that no weed growth occurs up to six months period, otherwise re-spraying shall be done by the contractor free of cost. IRUSSOR Code 211140 |
| 13 | Slewing and realigning of curves under traffic line block condition, as directed by Engineer in-charge with contractor\"s labour, tools & plants, as required with general lift up to 25mm including one round of through packing, ballast profiling, loosening/tightening of P.Way fittings, if required and other incidental works. Note: Payment will be made based on average slew calculated in each 50m length of track by averaging absolute values of positive and negative value of slews .134011 Other than PSC Sleeper track - Maximum slew up to 50mm TRM 98.31 IRUSSOR Code 134010 |
| 14 | Scattered renewal or replacement of missing / worn-out fittings with Railway\"s fittings for track/Points & Crossings sleepers including leading to required location for the work and the released fittings shall be collected and neatly stacked, as directed by the Engineer In charge. Note: New fittings shall be supplied from and released material shall be deposited at, nearest Plant Stores. ERCs Each ,GFN Liners Each. IRUSSOR Code 63130 |
| 15 | Removing weeds & bushes in ballast section and cess up to 3.95m from centre line of track in mid section & station yard, as specified by Engineer in-charge including disposal of branches, bushes outside cess/yard.( 1000X6=6000mtr) IRUSSOR Code 136100 |
| 16 | Suplying,Laying and compacting Stone aggregate(machine crushed track ballast) conforming to latest RDSO Specification of Ballast. Stacking of Ballast to be done at site as per direction of Engineer in Charge including all types types of transportation up to the site.DSR2023 |