| 1 | Carriage of following material from store center Meerut to site of work including loading & unloading at both ends maximum distance up to 100 Km. :- |
| 2 | PCC/STP Pole 11 Mtr. Long. |
| 3 | PCC Pole 8.5 Mtr Long. |
| 4 | Line material such as HT/LT Cross arms, HT/LT pin, HT/LT pin insulator, HT/LT Disc insulator with fitting, Stay rod, Stay wire, LT AB cable of various size, ACSR conductor, GI Wire, MS angle iron & MS Channel, TPMO, Fuse set etc. |
| 5 | 25 KVA to 100 KVA T/F including complete related material required for transformer. |
| 6 | 250/400 KVA T/F including complete related material required for transformer. |
| 7 | XLPE Cable of size 3x70/3x120 sq.mm |
| 8 | Erection of PCC pole 8.5 Mtr long/STP Pole 11 mtr long with grouting after digging a pit of size 1.6 mtr deep in all type of Soil including back filling of the pole with proper ramming after completion of work.(as per UPPCL Respo). |
| 9 | Fabrication and fixing of all 11 KV HT/LT line accessories.(as per UPPCL Respo). |
| 10 | Erection of Double pole on PCC pole 8.5 mtr/STP Pole 11 mtr long with grouting after digging a pit of size 1.6 mtr deep in all type of Soil for each pole including back filling of the pole with proper ramming after completion of work. (as per UPPCL Respo). |
| 11 | Fabrication and fixing of MS angle and MS channel, fixing all 11 KV accessories TPMO, Fuse set 11 KV pin insulators on D/P Pole.(as per UPPCL Respo). |
| 12 | Mounting of 25 to 100 KVA T/F with proper jumpering of HT side and fixing of cable on LT side of T/F.(as per UPPCL Respo). |
| 13 | Making of New 250/400 KVA T/F Plinth of size 6\"x6\"x3\" (feet) (as per UPPCL Respo). |
| 14 | Fencing of 250/400 KVA T/F (as per UPPCL Respo). |
| 15 | Mounting/Installation of 250/400 KVA T/F with proper jumpering of HT side and fixing of cable on LT side of T/F. (as per UPPCL Respo). |
| 16 | Making a section pole to exist pole after fabrication & fixing of T channel fixing of all HT/LT accessories. (as per UPPCL Respo). |
| 17 | Erection of stay rod complete after digging a pit of size 1.6 mtr deep and grouting the same in block of size 0.60 x 0.60 x 0.30 mtr and nuzzling at the both ends and filling the pit with excavated earth soil with proper ramming.(as per UPPCL Respo). |
| 18 | Gaurding of HT/LT Line. (as per UPPCL Respo). |
| 19 | Laying lifting stringing & proper sagging of ACSR conductor for HT/LT line including binding & jumpering properly. (as per UPPCL Respo). |
| 20 | Laying of LT ABC Cable of various size including fixing of all LT ABC accessories on support (as per UPPCL Respo). |
| 21 | Laying of XLPE Cable of size 3x70/3x120/3x185 sq.mm pit of the size 1.5 in the trench and road crossing in the air (as per UPPCL Respo). |
| 22 | Trenchless boring(as per UPPCL Respo). |
| 23 | Fixing of Distribution box including fixing the cable from transformar and consumer service cable (as per UPPCL Respo). |
| 24 | Earthing of each HT/LT line pole & T/F properly after drive of electrodes if size 20mm x 250 mm and connection the earthing point with GL wire. (as per UPPCL Respo). |
| 25 | Chemical earthing of T/F (Neutral and body) with GI Pipe 32mm Dia. (as per UPPCL Respo). |
| 26 | Guarding of line with G.I. wire having 2 no. horizontal wire & 3 Mtr distance of SWG G.I. wire after fabrication of guard cross arms of & fixing the same in supports. (as per UPPCL Respo). |
| 27 | Filling of 33KV/11 KV Jointing Kit Indoor/Outdoor of size 3x70/3x120/3x185 sq.mm (as per UPPCL standard). |
| 28 | Providing and fixing of Holding Clamp (As Per Direction of Supervising Engineer). |
| 29 | Providing and fixing of HT/LT Clamp (As Per Direction of Supervising Engineer). |
| 30 | Providing and fixing of J Hook (As Per Direction of Supervising Engineer). |
| 31 | Providing and fixing of Piercing Clamp (As Per Direction of Supervising Engineer). |
| 32 | Providing and fixing of Dead and Clamp(As Per Direction of Supervising Engineer). |
| 33 | Providing and fixing of MS Nut and Bolts(As Per Direction of Supervising Engineer). |
| 34 | Providing and fixing of HT/LT Insulator (As Per Direction of Supervising Engineer). |
| 35 | Cutting & chopping tree branches near side of line for making the clearance between line and tree. |