| 1 | All wall panelling & cupboard work (including removing & refixing of AC units, Server boxes, Switch boards/ TV Units etc. and cutouts wherver necessary) should be in Plywood confirming to IS: 710-2010, BWP MARINE GRADE, Premium quality from LIST OF MAKES FOR GUIDANCE TO BIDDERS for plywood/WPC/Laminates/1st Class TW Veneer: Greenply, Century, Kitply, Austin plywood, Everest ply, Indian Plywood Mfg. Ltd. (Anchor) or equivalent. All hardware items like drawer channels, handles, SS hinges, SS Beading etc shall be from LIST OF MAKES FOR GUIDANCE TO BIDDERS like Godrej, Olive, Hitachi, Kich, Hilti or as Approved by EIC. Drawer locks shall be from LIST OF MAKES FOR GUIDANCE TO BIDDERS like Godrej, Dorset, Hilti, Hardwyn. SS Handles, SS Legs shall be fromLIST OF MAKES FOR GUIDANCE TO BIDDERS of Annexure B of Section-VII. Adhesive shall be fromLIST OF MAKES FOR GUIDANCE TO BIDDERS like Fevicol, Jivanjor, Vamicol, Dunlop, Araldite of marine quality. Appropriate other adhesives for WPC & Ply bonding, TW beading with ply wood shall be adopted. All work to complete as per instructions by Engineer-In Charge. All visible surfaces shall be finished with 1.0 mm thick laminates or 4 mm thick TW Veneers wherever specified as per the item description/approved drawings and inside surfaces shall be using 1.0 mm or 0.80 mm thick (wherever specified) laminates of approved texture, shade & finish.MTC shall be submitted for all materials like plywood, veneer, aluminium, laminates & WPC sheets etc. All items including hardware items shall be got approved by the Architect/Engineer-in-charge before purchasing and using the same. Furniture/ wall and column panelling/ all items Drawings shall be prepred by contractor and submit to BARC for approval before making the furniture/ wall panelling . |
| 2 | Contractor shall submit relevant product catalogues and data sheets for BARC prior approval.Final colour scheme will be approved by BARC at the time of procurement. Contractor to furnish various colour schemes available with them.The laminates / veneers having single piece areas larger than 8 S.ft shall preferably be machine pressed |
| 3 | PANELLING: |
| 4 | (a) Wall & Column panelling shall be provided for the existing surface in the rooms to be made of 16 gauge aluminium framework (2\"X1\") at 2 feet c/c to be covered with 12mm thick WPC board and finished with 4.0mm thick veneer and melamine polish. |
| 5 | (b)Teakwood mould beading at top of the wallas per approved drawing |
| 6 | (c) Window inside finish with 0.5\" thick teakwood plank in melamine polish |
| 7 | Supply, Fabrication and fixing of cupboards made out of 18mm thick WPC boards finished in 1mm thick laminate on the surfaces and match PVC edge bending from bottom step (10\") |
| 8 | i.) Project Manager\"s Room (12.5\"x8\"x1.6\") |
| 9 | ii.) Conference Rooms 1 & 2 (9\"x2.5\"x2\") |
| 10 | iii.) System Unit boxes with 1/2\" thk.- 4 toughned glass partitions |
| 11 | iv.)UPS storage boxes (5\"x4\"x1.6\")-Fire resistant type as approved by EIC |
| 12 | v) Open Office -1 (15\"x5\"X1.6\") |
| 13 | vi) Open Office - 2 (8\"x5\"X1.6\") |
| 14 | Shifting and Fixing of UPS units to outside corridor with proper concealed wiring and shifting of all switch boards to a designated location and all work as directed by EIC.The below item includes(for all 3 Nos)a) Supply & laying of 3 Core FRLSH copper PVC flexible cable along with cable trunking including hardware for installation. i) 06 sqmm - 80 Meters approx. ii)04 sqmm - 80 Meters approx.b) Supply and installation of C type double pole MCB along with double door enclosure. i) 63 amps- 2 Nos. ii)32 amps- 6 Nos. Contactor is required to submit name of makes for all items for BARC approval before procurement |