| 1 | RELAYING WITH ADVANCE PATCHES OF THE ROADMILAGANOOR - KATTANOOR ROAD TO KUVALAIVELIROAD0/0 -3/05 (R-29) |
| 2 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road landincluding uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut |
| 3 | Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, including compacti |
| 4 | Advance patch work for making up the undulation in the existing B.Tsurface to an average thickness ofof 50mm using 45mm IRC size HBG metal |
| 5 | 0/0-1/0 |
| 6 | 1/0-2/0 |
| 7 | 2/0-3/0 |
| 8 | MAINTENANCE OF THE ROAD FROMMILAGANOOR KATTANUR ROAD TO KEELAMELKUDI ROADKM 0/0 -/900 (R-31) |
| 9 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road landincluding uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut |
| 10 | Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, including compacti |
| 11 | Advance patch work for making up the undulation in the existing B.Tsurface to an average thickness ofof 50mm using 45mm IRC size HBG metal |
| 12 | 0/0-1/0 |
| 13 | Providing and laying Tack coat over BT surface using 2Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat |
| 14 | Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00-9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP si |
| 15 | MAINTENANCE OF THE ROAD FROM MELAMELKUDI TO SEENIMADAI ROAD 0/0-2/425(R32) |
| 16 | Advance patch work for making up the undulation in the existing B.Tsurface to an average thickness ofof 50mm using 45mm IRC size HBG metal |
| 17 | 0/0-1/0 |
| 18 | 1/0-2/0 |
| 19 | MAINTENANCE OF THE ROAD FROM 1/6 OF ANNAVASAL ROAD TO KILANKATTUR ROAD0/0 -1/650 (R-33) |
| 20 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road landincluding uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut |
| 21 | Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, including compacti |
| 22 | Advance patch work for making up the undulation in the existing B.Tsurface to an average thickness ofof 50mm using 45mm IRC size HBG metal |
| 23 | 0/0-1/0 |
| 24 | 1/0-2/0 |
| 25 | Providing and laying Tack coat over BT surface using 2Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat |
| 26 | Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00-9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP si |
| 27 | MAINTENANCE OF THE ROAD FROM MILAGANOOR KATTANOOR ROAD TO KARUVAKKUDIROAD Km 0/0-0/800(R-55) |
| 28 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road landincluding uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut |
| 29 | Advance patch work for making up the undulation in the existing B.Tsurface to an average thickness ofof 50mm using 45mm IRC size HBG metal |
| 30 | 0/0-1/0 |
| 31 | MAINTENANCE OF THE ROAD FROM MILAGANOOR KATTANOOR ROAD TO KANJIMADAI ROAD Km 0/0-0/600(R-66) |
| 32 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road landincluding uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut |
| 33 | Advance patch work for making up the undulation in the existing B.Tsurface to an average thickness ofof 50mm using 45mm IRC size HBG metal |
| 34 | 0/0-1/0 |
| 35 | MAINTENANCE OF THE ROAD FROM NH -49 TO KEELAMELKUDI ROADKM 0/0 -2/00 (R-68) |
| 36 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road landincluding uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut |
| 37 | Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, including compacti |
| 38 | Advance patch work for making up the undulation in the existing B.Tsurface to an average thickness ofof 50mm using 45mm IRC size HBG metal |
| 39 | 0/0-1/0 |
| 40 | 1/0-2/0 |
| 41 | Providing and laying Tack coat over BT surface using 2Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat |
| 42 | Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00-9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP si |
| 43 | MAINTENANCE OF THE ROAD FROMRAJAGAMBEERAM TO KALPIRAVU LINK ROAD0/0 -1/60(R-93) |
| 44 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road landincluding uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut |
| 45 | Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, including compacti |
| 46 | Advance patch work for making up the undulation in the existing B.Tsurface to an average thickness ofof 50mm using 45mm IRC size HBG metal |
| 47 | 0/0-1/0 |
| 48 | 1/0-2/0 |
| 49 | Providing and laying Tack coat over BT surface using 2Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat |
| 50 | Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00-9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP si |
| 51 | MAINTENANCE OF THE ROAD FROMTHUTHIKULAM ROAD0/0 -0/200(R-97) |
| 52 | Advance patch work for making up the undulation in the existing B.Tsurface to an average thickness ofof 50mm using 45mm IRC size HBG metal |
| 53 | MAINTENANCE OF THE ROAD FROM CHINNAKANNANOOR ROAD TO RAJAKKALKUDIERUPPU ROAD0/0 -3/60 (R-115) |
| 54 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road landincluding uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut |
| 55 | Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, including compacti |
| 56 | Advance patch work for making up the undulation in the existing B.Tsurface to an average thickness ofof 50mm using 45mm IRC size HBG metal |
| 57 | 0/0-1/0 |
| 58 | 1/0-2/0 |
| 59 | 2/0-3/0 |
| 60 | 3/0-4/0 |
| 61 | Providing and laying Tack coat over BT surface using 2Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat |
| 62 | Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00-9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP si |
| 63 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column \"BB\" for all works in this package}(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) |