| 1 | Excavation in trenches n.exc 1.5 mtr wide and n.exc 1.5 mtr deep in loose / soft soil and getting out for under ground cable/Pipe lines / erection of poles, stays etc complete all as specified and as directed. |
| 2 | Returning, filling in including spreading, leveling, watering and well ramming in layers n.exc 25 cm thick complete all as specified and directed. |
| 3 | Removing of excavated material n, exc 50 mtr away and depositing where directed at a level n, exc 1.5 mtr above the starting point complete all as specified. |
| 4 | Taking out old unserviceable DI/CI pipe with all fittings (including all fittings), with spigot and socket ends and lead joints including burning out joints and recovering lead from trenches of 300 mm dia boreall as directed :-(Note : Excavation & earth work will be measured & paid seperately under respective item ) |
| 5 | Description all as per ser item No 4 here-in-before but for 200 mm bore |
| 6 | Description all as per ser item No 4 here-in-before but for 150 mm bore |
| 7 | Description all as per ser item No 4 here-in-before but for 100 mm bore |
| 8 | Description all as per ser item No 4 here-in-before but for 80 mm bore |
| 9 | Supply and layingDI pipe of 300 mm boreISI marked, spigot and socketed type, Class K-7 centrifugally cast suitable for rubber tyton joints laid in trenches complete all as specified and as directed by Engineer-in-charge (Earth work for excess width of taking down, route change of pipe & joints shall be measured and paid separately)Make:Electro Steel/Tata/NECO/Kesoram/Rashmi Metaliks |
| 10 | Description all as per ser item No 9 here-in-before but for 200 mm bore |
| 11 | Description all as per ser item No 9 here-in-before but for 150 mm bore |
| 12 | Description all as per ser item No 9 here-in-before but for 100 mm bore |
| 13 | Description all as per ser item No 9 here-in-before but for 80 mm bore |
| 14 | Laying only DI/CI pipe new or old position in trenches where directed and testing complete all as specified :-(Note : Excavation & earth work will be measured & paid seperately under respective item ) for 300 mm dia bore |
| 15 | Description all as per ser item No 14 here-in-before but for 200 mm dia bore |
| 16 | Description all as per ser item No 14 here-in-before but for 150 mm dia bore |
| 17 | Description all as per ser item No 14 here-in-before but for 100 mm dia bore |
| 18 | Description all as per ser item No 14 here-in-before but for 80 mm dia bore |
| 19 | Cutting to existing cast iron pipes of 80mm bore before laying in position or in position for insertion of new tees, branches, bend and new fitting etc complete all as specified and as directed by Engineer-in-charge. |
| 20 | All as per above item No 19 here-in-before but 100mm bore |
| 21 | All as per above item No 19here-in-before but 150mm bore |
| 22 | All as per above item No 19 here-in-before but 200mm bore |
| 23 | All as per above item No 19 here-in-before but 300mm bore |
| 24 | M & L in replacement of cast iron pipe fittings such as bend upto 150mm bore (any type radious and angle) tapers any type (straight, bend, increasing, descreasing or double socket etc), Tee piece single branch, \"Y\" junction, double branch cross (all sockets or socket and spigot) collors, caps and plugs, D joint, mechanical joint as in repairs, excavation earth work and run lead jointsshall be measured and paid seperately upto 150mm borefor spigot socketed pipes. |
| 25 | All as per above item No 9 here-in-before but 200 to 300mm bore |
| 26 | M & L Bends. Tapers. Tee pieces (single & double branch) any type and angle/radius and straight connecting pieces but all ends flanged upto 150mm bore for flanged pipes. |
| 27 | Taking out old unserviceable GI tubing with all fittings from trenches, walls, floors etc of 150 mm dia bore size and all as directed (Note : Excavation & earth work will be measured & paid seperately under respective item ) |
| 28 | Description all as per ser item No 27 here-in-before but for 100 mm dia bore |
| 29 | Description all as per ser item No 27 here-in-before but for 80 mm dia bore |
| 30 | Description all as per ser item No 27 here-in-before but for 50 mm dia bore |
| 31 | Description all as per ser item No 27 here-in-before but for 25 mm dia bore |
| 32 | Description all as per ser item No 27 here-in-before but for 20 mm dia bore |
| 33 | M & L for GI pipe medium grade with all fittings laid in trenches 150 mm bore medium grade ISI Markedof following sizes with all fittings complete all as specified and as directed by Engineer-in-Charge. |
| 34 | Description all as per ser item No 33 here-in-before but of size 100 mm Dia |
| 35 | Description all as per ser item No 33 here-in-before but of size 80 mm Dia |
| 36 | Description all as per ser item No 33 here-in-before but of size 50 mm Dia |
| 37 | Description all as per ser item No 33 here-in-before but of size 25 mm Dia |
| 38 | Description all as per ser item No 33 here-in-before but of size 20 mm Dia |
| 39 | S & F Gun metal gate valve 50 mmISI marked with iron wheel screwed down high pressure screwed both ends for iron pipe incl taking down old unserviceablecomplete all as specified and directed by Engineer-in-Charge. |
| 40 | Description all as per ser item No 40 here-in-before but of 40 mm bore |
| 41 | Description all as per ser item No 40 here-in-before but of 25 mm bore |
| 42 | Description all as per ser item No 40 here-in-before but of 20 mm bore |
| 43 | Material and labour forburning out lead in position and jointing to cast iron pipe of size 300mm bore spigot and socket by run lead joints including spun yarn and caulking of lead joints complete all as specified and as directed by Engineer-in-charge |
| 44 | All as per above item No 44 here-in-before but 200mm bore |
| 45 | All as per above item No 44 here-in-before but 150mm bore |
| 46 | All as per above item No 44 here-in-before but 100mm bore |
| 47 | All as per above item No 44 here-in-before but 80mm bore |
| 48 | Material & Labour for brick masonry valve pit internal size 1200mm x 1200mm x 1200mm with one brick thick wall using sub class ‘B’ brick in cement mortar 1:6 over 20cm thick PCC plate form with 15cm off sets on every side of 1:3:6 type C-1 including plastering of internal surfacesand exposed surfaces with 15mm thick plastering in cement mortar 1:4 and 50mm thick RCC cover (in two equal parts 1:2:4 type B-1 with 10mm dia deformed bars at 10cm interval on both side including necessary form work with 150mm dia hole in the center complete all as specified and as directed by Engineer-in-Charge |
| 49 | Description all as per ser item No 49 here-in-before but of size 1000mm x 1000mm x 1000 -ditto- |
| 50 | Description all as per ser item No 49 here-in-before but of size 600mm x 600mm x 600m -ditto- |
| 51 | S & F in replacement of unsv/damaged 15mm bib tap cast copper alloy with crutch or butterflyhandle screwed down, screwed for iron pipe or for brass ferrule complete all as specified and as directed. |
| 52 | Supply & Fixing in replacement of old unsv CI Foot valve of size 150 mm dia completeincluding rubber / fiber board ,gasket,nuts, washer etc including taking down old/ unserviceable Foot valve complete all as specified and as directed by Engineer-in Charge Make Rmco/ Kirloskar/Kartar |
| 53 | Supply & Fixing in replacement of old unsv CI NRV valve of size 150 mm dia with fly nut flanged both ends and drilled for jointing wheel head type conforming to IS 14846 including two flanged joints with nuts bolts and washers rubber insertion packing etc complete with gun metal or stainless steel spindle and cast iron hand wheel including rubber / fiber board gasket,nuts,bolts, washer etc required at site for proper installation,including taking down old/ unservicable NRV valve and complete all as specified and as directed by Engineer-in Charge Make BVI/ Kirloskar/ Kishor/Kartar |
| 54 | Supply & Fixing in replacement of old unsv CI Sluice valve PN-1.6of size 200 mm dia with fly nut flanged both ends and drilled for jointing wheel head type conforming to IS 14846 including two flanged joints with nuts bolts and washers rubber insertion packing etc complete with gun metal or stainless steel spindle and cast iron hand wheel including rubber / fiber board gasket,nuts,bolts, washer etcincluding taking down old/ unservicable Sluice valve complete all as specified and as directed by Engineer-in Charge Make BVI/ Kirloskar/ Kishor/Kartar |
| 55 | Description all as per item Ser No 55 but for 150mm dia |
| 56 | Description all as per item Ser No 55 but for 100mm dia |
| 57 | Description all as per item Ser No 55 but for 80mm dia |
| 58 | Material and Labour for taking out and dismantlingthe 150mm dia bore sluice valves in various locations and reconditioning,refacing and regrindindthe sluice valve by replacing SS spindle, spindle nuts with brass ring, gland bush , nuts,gasket,bonnet and disc or as requires at site complete all as specified and as directed. |
| 59 | Material and Labour for taking out and dismantlingthe 300 mm dia bore sluice valves in various locations and reconditioning,refacing and regrindindthe sluice valve by replacing SS spindle, spindle nuts with brass ring, gland bush , nuts,gasket,bonnet and disc or as requires at site complete all as specified and as directed. |
| 60 | Material and Labour for taking out and dismantlingthe 200 mm dia bore sluice valves in various locations and reconditioning,refacing and regrindindthe sluice valve by replacing SS spindle, spindle nuts with brass ring, gland bush , nuts,gasket,bonnet and disc or as requires at site complete all as specified and as directed. |
| 61 | Material and Labour for taking out and dismantlingthe 100 mm dia bore sluice valves in various locations and reconditioning,refacing and regrindindthe sluice valve by replacing SS spindle, spindle nuts with brass ring, gland bush , nuts,gasket,bonnet and disc or as requires at site complete all as specified and as directed. |
| 62 | Material and Labour for taking out and dismantlingthe 80 mm dia bore sluice valves in various locations and reconditioning,refacing and regrindindthe sluice valve by replacing SS spindle, spindle nuts with brass ring, gland bush , nuts,gasket,bonnet and disc or as requires at site complete all as specified and as directed. |
| 63 | Material and Labour for gland packing repacking stuffing box of sluice valve spindle including taking apart and reassembling in leaking Sluice Valves of 80mm dia size Complete including replacing / tightening the existing bolts and nuts etc. complete all as directed by Engr-in-Charge. |
| 64 | Material and Labour for gland packing repacking stuffing box of sluice valve spindle including taking apart and reassembling in leaking Sluice Valves of 100 mm dia size Complete including replacing / tightening the existing bolts and nuts etc. complete all as directed by Engr-in-Charge. |
| 65 | Material and Labour for gland packing repacking stuffing box of sluice valve spindle including taking apart and reassembling in leaking Sluice Valves of 150mm dia size Complete including replacing / tightening the existing bolts and nuts etc. complete all as directed by Engr-in-Charge. |
| 66 | Material and Labour for gland packing repacking stuffing box of sluice valve spindle including taking apart and reassembling in leaking Sluice Valves of 200mm dia size Complete including replacing / tightening the existing bolts and nuts etc. complete all as directed by Engr-in-Charge. |
| 67 | Material and Labour for gland packing repacking stuffing box of sluice valve spindle including taking apart and reassembling in leaking Sluice Valves of 300mm dia size Complete including replacing / tightening the existing bolts and nuts etc. complete all as directed by Engr-in-Charge. |
| 68 | M&L for collection of water samples from bore wells located at Lower Pump House of Raiwala Military Station in white colour PVC containers of capacity not less than 5.0 Ltr, hygenically dry, neat & clean duly sealed and transporting the same to laboratory for followings tests of drinking water for portability charaterstics/parameter as per IS 10500-2012 from Government approved/certified laboratory seperately for each borewell and submit the test results/reports of water samples (bore well wise) to Engineer in chargefor maintain the record at bore wells/sub divn level and Engineer in charge will submit the same as and when asked by higher HQ and complete all as specified and directed. (a) Colour,(b) Odour (c) Turbidity(d) Temperature(e) Taste (f) TDS(Total dissolved Solids) (g) pH (h) Iron as Fe(j) Nitrate as N(k) Arsenic as As (l) Chloride as Cl (m) Sulphate as SO4(n) Alkalinity as CaCO3 (o) Hardness(p) Calcium as Ca (q) Magnesium as Mg (r) Conductivity(s) Fluoride as F(t) Coliform Count (u) Residual Chlorine (v) E-Coli |
| 69 | M & L for Straight plain brass ferrules (or connecting screws) screwed both ends and fixed for 25 mm dia with all fittings complete all as specified and as directed by Engineer-in-Charge. |
| 70 | M & L for Drilling and tapping cast iron water mains (in position) for branch connections of the internal dia 25 mm with all fittings complete all as specified and as directed by Engineer-in-Charge. |
| 71 | Supply only calcium hypochlorite for water treatment following generic specification and specification complete all as specified and directed by Engineer-in-Charge:-Generic Specifications:-(a)Common name:- Stable Bleaching Powder/ High strength Bleaching Powder(b)Description/Apperance:-Dry free flowing and free from lupms (c)Toxic & Undesirable Substance :-Should not induce substance beyond accepeted limit as given in IS 10500(2012) in treated and disinfected.(d)Packing:- 20-25 Kg bags/40-45 kg Durms.Packing in drums is preferable to reduce fire hazard in places of high ambient temperature.Specification:-(a) Available Chlorine - 65 %(b) Stability-1/15Max(c) Particle size(passing through 1.70mm IS sieve-99.5 %(d) water insoluble matter-6% Max(e) Calcium Hydroxide-4% Max(f) Sodium Chloride -15 % MaxNote: Test Certificate each batch of chlorine to be submitted at the time of delivery. |