| 1 | Supply |
| 2 | Industrial grade PC with Windows 11 Operating system.Server: 02 nos.OWS: 03 nos.OWS cum Engg PC: 01 no.Gateway: 02 nos.( • 4URack mount Chassis with Visual Alarm Notification, Lockable front door prevents unauthorized access• LGA115 19thGeneration Intel®Core™i7ATXDD R4,SATA3.0,USB3.1&6COMs.• Chip set H310• 400W ATX Power supply• CPUIntelCorei7-9700(3.0GHz,8Core,8Threads,12MBCache)9th generation with industrial CPU cooler• 32GB DDR4 RAM 1600/2400 Max Support(32GB)• 1TB SATAHDD Enterprises• Support s Dual display DVI,VGA• 4USB(2xUSB3.1Gen1,2xUSB2.0)• 2XRJ45Lanport10/100/1000MBPS• 2xRS-232,4forG2version(3xRS-232,boxheader;1xRS- 232/422/485 with auto-flow control, box-header)• PCI5(32-bit/33MHz), 1xPCIex4(Gen2) , 1xPCIex16(Gen3)• DVDR/W• Windows11Pro64bit) |
| 3 | SCADA software loaded in PC (All Softwares required to complete upgradation work) |
| 4 | Laptop for remote access ( 15 Inches i7 processor, 8GB Window 11) |
| 5 | 27” Monitor( LED, HP/ DELL/Equivalent make) |
| 6 | Printer A4 size( HP/cannon/Equivalent make. Wireless Print copy ,SCAN , Hi-Speed USB 2.0, Ethernet, Up to 21 PPM, Black& White) |
| 7 | Cards for Upgradation of existing BCU (if required)400KV bay: 12 nos.220KV Bay: 05 nos.Auxliary BCU: 01 no.( Compatible for existing BCU, model micom C264, make Areva) |
| 8 | Cards for Upgradation of existing busbar relays (if required)400KV: CU 04 nos.220KV: CU 02nos. & PU 10nos.( Compatible for existing Busbar CU, model P741 and P746, make Areva/ Schinder) |
| 9 | GPS Master Clock along with Antenna and 30-meter Coaxial Antenna Cable( • Masibus/Equivalent make 19”Rackmount• GPS Master Clock along with Antenna and30-meter Co axial Antenna Cable.•Model: MC-1-U-1-1-0-U1-2 Having IRIG-B (Modulated) – 1 port• IRIG-BTTL– 1port• RS232–1portRS485–1portNTP–1portPPM/ PPH–1port Aux. Supply: 90-370V DC, 85-260VAC, 47-55Hz,) |
| 10 | WorksDesign, engineering, writing, testing, configuration, Integration work or any other work related to upgradation of existing SCADA system |
| 11 | Hardware Replacement & Integration work of existing BCU |
| 12 | Integration work of new 220KV bay |
| 13 | Installation, testing, Commissioning work of GPS system including time synchronizing of existing equipments and SCADA system |
| 14 | Hardware Replacement & Integration work of existing Busbar scheme |