| 1 | Work Feeder Bi fircation Under EDD Nautanwa Under Business Plan 2025-26 |
| 2 | PART-ALoading,safe carriageand unloading of Following Materialfrom Electricity Store Center Maharajganj to work site |
| 3 | S.T. POLE 11 Mtr. M.-IS 410 SP-50 |
| 4 | P.C.C. POLE 11 Mtr. |
| 5 | P.C.C. POLE 8.5 Mtr. |
| 6 | A.C.S.R. WEASEL CONDUCTOR |
| 7 | 11 KV O/G VCB |
| 8 | 11 KV 3x185 sqmm XLPE Cable |
| 9 | 11 KV V TYPE STEEEL CROSS ARM |
| 10 | 11KV COMPOSIT POLYMER PIN INSULATOR |
| 11 | 11KV COMPOSIT POLYMER DISC INSULATOR |
| 12 | Stay Set Complete |
| 13 | Earthing Complete |
| 14 | T-Off Channel |
| 15 | Top channel |
| 16 | Cable Jointing Kit Indoor |
| 17 | Cable Jointing Kit Outdoor |
| 18 | Cross Bracing |
| 19 | Gurading Angle |
| 20 | PART-BSupply of following Decentralized Item |
| 21 | CROSS ARM HOLDING CLAMP |
| 22 | Nut and Bolt |
| 23 | F - Braket |
| 24 | F - Braket Clamp |
| 25 | Stone Pad |
| 26 | Alluminium Binding Wire 6swg |
| 27 | Barbed Wire |
| 28 | I Bolt with Nut |
| 29 | G.I wire |
| 30 | Tee off Channel Clamp |
| 31 | Top,Channel Clamp |
| 32 | PART-CWORK AT SITE AS PER SPECIFICATION |
| 33 | Concreting of Stay |
| 34 | Erection and Grouting of Pole with all assesories |
| 35 | Erection and Grouting of earthing Complete |
| 36 | Laying 11 KV 3x185 sqmm XLPE cable |
| 37 | Installation of 11 KV VCB |
| 38 | Plinth and foundation for VCB Panel |
| 39 | Chemical Earthing for VCB Panel |
| 40 | Installation of ACSR Weasel Conductor |
| 41 | Installation of Cable Jointing Kit Indoor |
| 42 | Installation ofCable Jointing Kit Outdoor |
| 43 | Installation ofT-Off Channel |
| 44 | Installation ofTop channel |
| 45 | Installation ofCROSS ARM HOLDING CLAMP |
| 46 | Installation ofNut and Bolt |
| 47 | Installation ofF - Braket |
| 48 | Installation ofF - Braket Clamp |
| 49 | Installation ofStone Pad |
| 50 | Installation ofAlluminium Binding Wire 6swg |
| 51 | Installation ofBarbed Wire |
| 52 | Installation ofTee off Channel Clamp |
| 53 | Installation ofTop,Channel Clamp |