| 1 | Supply, Carraige and Erection of following material against replacement/installation/Laying of item/Erection of material as per RESPO Drawings/Estimate. Work includes all cartage/carriage(Store to Site), T&P, commissioning and any other work which is required for completion of work. as per RESPO norms.(Qty will be + - 50%) |
| 2 | Supply and Erection of Clamp with N&B as per RESPO Norms.(X Arm Holding Clamp, F--Clamp, Gaurding Angle Clamp,Suspension, Dead and End Clamp, Clamp for DB, Eye hock Clamp, stay clamp, PG Clamp, LT Clamp, Channel Clamp, E Clamp & F Bracket etc) |
| 3 | Supply and Erection of Nut & Bolt Off sizeas per RESPO Norms. |
| 4 | Supply and Erection of 11 KV I/D & O/D cable jointing kit suitable for 3X120/3X185 Sqmm (Indoor/Outdoor) with proper Termination as per RESPO Norms. |
| 5 | Supply and Erection of 33 KV I/D & O/D cable jointing kit suitable for 3X300 SqMM Sqmm (Indoor/Outdoor) with proper Termination as per RESPO Norms. |
| 6 | Supply and Erection of G.I. Pipe 6\" DIA |
| 7 | Carriage of Various size PCC/STP Poles from store center or from any other place to the respective site of work Distence up to 75 km through the Kachha Pacca road including the work of its loading & unloading at the respective ends also including the work of its dragging etc. and also including the cost of labour, T & P and carrier etc. required for proper completion of work. |
| 8 | Carriage of Line material viz. Weasel/Rabbit/Racoon /Dog Conductor, G.I. earth wire, cross arm, angle, channel, Cable Boxes, Static meter insulators, clamps and other line material from store center or from any other place to the respective site of work through the Kachha Pacca road including the work of its loading & unloading at the respective ends also including the work of its dragging etc. and also including the cost of labour, T & P and carrier etc. required for proper completion of work. |
| 9 | Carriage of 250/100/63/25/16/10 KVA T/Ffrom store center or from any other place to the respective site of work through the Kachha Pacca road including the work of its loading & unloading at the respective ends also including the work of its dragging etc. and also including the cost of labour, T & P and carrier etc. required for proper completion of work |
| 10 | Erection and grouting of P.C.C/STP Double pole including the work of complete H.T. fittings as per RESPO manual and as per direction of engineer Incharge including the cost of labour, T & P and carrier etc. required for proper completion of work. The support shall be grouted with cement, sand and brick ballast/stone ballast In ratio 1:4:8 including the cost of arrangement of cement, sand, brick ballast/stone ballast, stone pad etc. as per actual site requirement. |
| 11 | Erection and grouting of P.C.C/STP Single pole including the work of complete H.T. fittings as per RESPO manual and as per direction of engineer Incharge including the cost of labour, T & P and carrier etc. required for proper completion of work. The support shall be grouted with cement, sand and brick ballast/stone ballast In ratio 1:4:8 including the cost of arrangement of cement, sand, brick ballast/stone ballast, stone pad etc. as per actual site requirement. |
| 12 | Erection and grouting of stay set including the work of nozelling etc. as per RESPO manual and also including the cost of all grouting material, labour, T & P etc. required for proper completion of work. |
| 13 | Dismentling of Rusted Weasal/Racoon /DOG conductor wire and G.I Wire as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T & P, carries etc. required for proper completion of work and scrap submited site to store. |
| 14 | Laying, Sagging, Stringing, Binding and Jumpering etc. of Weasal/Racoon /DOG conductor on the newly erected pole as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T & P, carries etc. required for proper completion of work. |
| 15 | Mounting of 250/100/63/25/16/10 KVA T/F on the double pole / plinth structure and connection thereof |
| 16 | Laying of PVC, ABC, 11 KV-33KV XLPE 3X185/3X120/ 3X70SqMM and more different size As per respo manual |
| 17 | Safe carriage from Anepur store to site and Installation and grouting of meter Pilferunit as per respo manual |
| 18 | Safe carriage from Anepur store to site and Installation of CTPT Double metering unit on double pole of large and heavy consumer as per respo manual |
| 19 | Guarding of 11 K.V. Line Crossing |
| 20 | Trimming of Tree Branches in New 11 K.V Line. |
| 21 | Fixing of earthing Rod as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T & P, carries etc. required for proper completion of work. |