| 1 | Removal of the Black Topped (BT) surface to 50 to 70mm depth using Milling machine,including conveying the milled waste materials away from the worksite to an average distanceincluding hire and running charges for the machine, conveyance charges, unloading atunobjectionable place, cleaning the milled surface as to avoid slippery including all other incidental charges etc. complete as per the direction of the departmental officers |
| 2 | Providing and laying Tack Coat over Existing BT surface using 2 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5 |
| 3 | Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00-9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30 kgs of VG40 bitumen for premixing per 10 sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross-sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver at site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause111, 112, 501, 507 & 900 of MORTH Rev-5 (Grading-II) |
| 4 | Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, including compacting with power roller, watering, including all hire and fuel charges for all tools and plants, removal of other deleterious matter and obstructions, trimming of bottom of excavation back filling, clearing up the site and disposal of all surplus materials etc., complete as per standard specification. For making up of low berms with conveyance of average lead 3km |
| 5 | Calculation of SubTotal, GST and Total Amount carried out by system automatically |
| 6 | Basic cost of value put to tender as per estimate |
| 7 | Add GST at 18% |
| 8 | Total Value put to Tender |
| 9 | Negotiated Percentage |
| 10 | Final Negotiated Value |
| 11 | Add GST at 18% of Final Negotiated Value |
| 12 | Total Value of Contract Including 18% of GST |
| 13 | Basic cost of value put to tender as per Estimate |
| 14 | Quoted Rate in Figures (Total Value of Contract Including 18% of GST ) |