| 1 | Demolishingbrickworkmanually/bymechanicalmeansincluding stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge and carting away debris out of AIESL Premises . |
| 2 | Plaster Breaking with dado |
| 3 | Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead. |
| 4 | Providing and constructing brick masonary |
| 5 | Brick work with common burnt clay machine moulded perforated bricks of class designation 12.5 conforming to IS: 2222 in superstructure above plinth level up to floor five level in cement mortar 1:6 (1 cement : 6 coarse sand):With Modular bricks |
| 6 | Providing and applying Internal plaster |
| 7 | Providind and applying 15-18 mm cement plaster in two coats under layer 12 mm thick cement plaster 1:5 (1 cement : 5 coarse sand) finished with a top layer 6 mm thick cement plaster 1:6 (1 cement : 6 fine sand). |
| 8 | Providing and applying External plaster |
| 9 | Providing and applying 18mm external sand faced plaster in two coats under layer 12 mm thick cement plaster 1:5 (1 cement : 5 coarse sand) and a top layer 6 mm thick cement plaster 1:3 (1 cement : 3 coarse sand) finished rough with sponge. |
| 10 | Carrying out structural repair |
| 11 | Providing and applying rust inhabitation coal/system to exposed reinforcement bars and also new reinforcement bars after removing scales and rust complete as per specification. |
| 12 | Providing & applying acrylic distemper |
| 13 | Distempering with 1st quality acrylic distemper (ready mixed) having VOC content less than 50 gram/litre, of approved manufacturer and of required shade and colour all complete to achieve even shade and colour :Two or more coats) over and including water thinnable priming coat with cement primer having VOC content less than 50 gram/litre |
| 14 | Providing and applying plaster of paris putty of 2-6 mm thickness over plastered surface to prepare the surface even and smooth complete including scaffolding as and where required. |
| 15 | Providing and applying Acrylic Smooth exterior emulsion paint: |
| 16 | Providing & applying exterior acrylic emulsion based paint(Asian-apex exterior/ultima, Dulux Weather shield or eqivalent make), with primer, as describedbelowintwoormorecolourshadesas approved by EIC at any location and at all levels & heights, including scaffolding, preparation of surface, fillingupthecrackswithBirla/wallplastexternal wallputty,crackfillingmaterial,curingallasper manufacturers specifications instructions and as directed by EIC complete. |
| 17 | One coat of exterior primer and two or more coats of exterior acrylic emulsion paint of Asian paint or ICI Dulux make. |
| 18 | Providing and applying synthetic enamel paint (SEP) |
| 19 | Providing and applying synthetic enamel paint (SEP) of Asian paints or ICI Dulux make paint with primer as described below of approved make and of first quality and of required colour and shade to give a smooth and even finish to any surfaces at any location and at all levels, including scaffolding, preparation of surface all as directed etc. complete. |
| 20 | Two or more coats of 1st quality SEP of Asian or ICI Dulux paints over painted surfaces or new surface. |
| 21 | Providing and fixing G.I. Pipes complete with G.I. fittings and clamps, including making good the walls etc. |
| 22 | 15mm15 mm dia nominal bore |
| 23 | 20 mm dia nominal bore |
| 24 | 25 mm dia nominal bore |
| 25 | Providing and fixing ball valve (brass) of approved quality, High or low pressure, with plastic floats complete : |
| 26 | 20 mm nominal bore |
| 27 | 25 mm nominal bore |
| 28 | Carting away Debris |
| 29 | Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved. |
| 30 | Steel Reinforcement for RCC Work includuing straightening, cutting, bending, placing in position and binding all complete above plinth level upto any level including scaffolding. |
| 31 | Thermo- Mechanically Treated bars of grade FE500D or more |
| 32 | Lintel work |
| 33 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 34 | Removing and dismantling existing rolling shutter with MS work in single section or built-up section including RSJ, angles, tees, flats, plates, gusset plates, channels etc., including dismembering using gas cutting, cutting machine lowering the same from any level and stacking up to the lead of 50 m. all as directed by EIC, etc., complete., including labour, tools , plants etc., complete. |
| 35 | Providing and fixing water spary gun with felxible pipe of 15 to 20 mm dia with necessary fittings, and hardware. Minimum pipe requirement shall be 4 meters for each water spray gun. Note: The contractor has to get the spray gun approved by the EIC & user department before its installation. |
| 36 | I HAVE FULLY UNDERSTOOD THE SCOPE OF WORK & AGREE TO ABIDE BY GENERAL CONDITION OF COTRACT. |