| 1 | Construction of PUE School Toilet @ Nallanpillaipetral Pt |
| 2 | Earth workexcavation and depositing on bank with in initial leadlift in hard gravelly soilforfoundation etc. complete. |
| 3 | Plain Cement concrete 1:4:8 mix using 40mm ISS metal including all cost and conveyance ofall materials to site and all labour charges etc complete. |
| 4 | Brick work CM 1:5 mix using good country bricks including cost and conveyance of all materials to site and all labour charges etc complete. |
| 5 | Supplying and errecting centering are strutting including necessary supports for place surface for RCC columns footing pedestal beam criticals pears etc.,using mild steel angles of sizes 90 x 90 x 10 cm gauge stifness welded mild steel of sizes 25 x 25 x 3 cm for boarding laying over silver oak joists of single 10cm - 6.5cm space of 75cm ceter to center |
| 6 | R C C 1:11/2:3 mix usinig 20mm ISS HBG metal including all cost and conveyance of labour charges etc., Complete.( Super Structure) |
| 7 | Supplying and Fabrication of steel for RCC works including all cost of cutting bending and tying of steels and kept ready for concrete in position etc., |
| 8 | Plastering with cement 1:3-10mm thick includingcost and conveyance of al materials to site and all labour charges etc complete. |
| 9 | Plastering with cement 1:5-12mm thick includingcost and conveyance of al materials to siteand all labour charges etc complete. |
| 10 | Paving the flooring with special type of flooring tiles (Cement based Hydraulically pressed Anti skid tiles (20mm thick) in CM 1:3, 20mm thick |
| 11 | Dadooing walls Plain Galzed tiles of size 150x150x6mm |
| 12 | Supplying and painting the walls with two coats of oil bound distemper over one coat of water based cement primer including cost for distemper, primer, cleaning and scrapping the walls, rendering the wallssmooth with necessary putty, brushes, scaffolding arrangements, labour charges, etc., as per standard specification. |
| 13 | Painting two coatwith ready mixedplastic emulsion of firstquality paint and of approved colour over apriming coatincluding thorogh scarpping clean removal of dirt etc., complete as per standard specification. |
| 14 | Cost and supply of IWC |
| 15 | Cost and supply of EWC |
| 16 | Provision for Steel Door Size 0.75x1.80m |
| 17 | Provision for Steel Door Size 1.05x1.80m |
| 18 | Provision for Water Supply Arrangement |
| 19 | Provision for RCC Jolley |
| 20 | Provision forName boardcharges |
| 21 | Provision for Photographic charges |
| 22 | Construction of PUM School Toilet @ Seranur in Sirunampoondi Pt |
| 23 | Earth workexcavation and depositing on bank with in initial leadlift in hard gravelly soilforfoundation etc. complete. |
| 24 | Plain Cement concrete 1:4:8 mix using 40mm ISS metal including all cost and conveyance ofall materials to site and all labour charges etc complete. |
| 25 | Brick work CM 1:5 mix using good country bricks including cost and conveyance of all materials to site and all labour charges etc complete. |
| 26 | Supplying and errecting centering are strutting including necessary supports for place surface for RCC columns footing pedestal beam criticals pears etc.,using mild steel angles of sizes 90 x 90 x 10 cm gauge stifness welded mild steel of sizes 25 x 25 x 3 cm for boarding laying over silver oak joists of single 10cm - 6.5cm space of 75cm ceter to center |
| 27 | R C C 1:11/2:3 mix usinig 20mm ISS HBG metal including all cost and conveyance of labour charges etc., Complete.( Super Structure) |
| 28 | Supplying and Fabrication of steel for RCC works including all cost of cutting bending and tying of steels and kept ready for concrete in position etc., |
| 29 | Plastering with cement 1:3-10mm thick includingcost and conveyance of al materials to site and all labour charges etc complete. |
| 30 | Plastering with cement 1:5-12mm thick includingcost and conveyance of al materials to siteand all labour charges etc complete. |
| 31 | Paving the flooring with special type of flooring tiles (Cement based Hydraulically pressed Anti skid tiles (20mm thick) in CM 1:3, 20mm thick |
| 32 | Dadooing walls Plain Galzed tiles of size 150x150x6mm |
| 33 | Supplying and painting the walls with two coats of oil bound distemper over one coat of water based cement primer including cost for distemper, primer, cleaning and scrapping the walls, rendering the wallssmooth with necessary putty, brushes, scaffolding arrangements, labour charges, etc., as per standard specification. |
| 34 | Painting two coatwith ready mixedplastic emulsion of firstquality paint and of approved colour over apriming coatincluding thorogh scarpping clean removal of dirt etc., complete as per standard specification. |
| 35 | Cost and supply of IWC |
| 36 | Cost and supply of EWC |
| 37 | Provision for Steel Door Size 0.75x1.80m |
| 38 | Provision for Steel Door Size 1.05x1.80m |
| 39 | Provision for Water Supply Arrangement |
| 40 | Provision for RCC Jolley |
| 41 | Provision forName boardcharges |
| 42 | Provision for Photographic charges |
| 43 | Providing Paver Block Pavement @ Periyamur Mariyamman Kovil Near in Devathanapettai Pt |
| 44 | Earth work excation in hard gravelly soil SS20 B for foundation including all charges 0-.30m |
| 45 | Cement concrete mix 1:4:8 using 40mm gauge hand broken granite stone jelly |
| 46 | Supplying and erracting centering for rcc work includuing all charges |
| 47 | Cement concrete mix 1:2:4 using 20mm gauge hand broken granite stone jelly |
| 48 | Supply and Filling Msandfrom Approed Qarry include all charges |
| 49 | Paving with Paver Blocks 80mm Thick laid as interlocking block including all charges |
| 50 | Provision forName boardcharges |
| 51 | Provision for Photographic charges |
| 52 | Providing Paver Block Pavement @Puthur Pillaiyar Kovil Near in Manalapadi Pt |
| 53 | Earth work excation in hard gravelly soil SS20 B for foundation including all charges 0-.30m |
| 54 | Cement concrete mix 1:4:8 using 40mm gauge hand broken granite stone jelly |
| 55 | Supplying and erracting centering for rcc work includuing all charges |
| 56 | Cement concrete mix 1:2:4 using 20mm gauge hand broken granite stone jelly |
| 57 | Supply and Filling Msandfrom Approed Qarry include all charges |
| 58 | Paving with Paver Blocks 80mm Thick laid as interlocking block including all charges |
| 59 | Provision forName boardcharges |
| 60 | Provision for Photographic charges |
| 61 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |