| 1 | CARRIAGE OF 11MTR. STP /8.5 MTR PCC POLE FROM ESC HASARI TO DIFFERENT CONSUMER WORK SIDE. |
| 2 | CARRIAGE OF LINE MATERIAL VIZ. CONDUCTOR, 11 KV XLPE CABLE, AB CABLE, STAY ROD, EARTHING ROD, GI WIRE, STAY WIRE AND OTHER LINE MATERIAL |
| 3 | ERRECTION OF 11MTR. STP / 9 MTR PCC POLE POLE WITH FIXING OF ALL ACCESSORIES INCLUDING IT\"S GRAUTING |
| 4 | ERECTION AND GRAUTING OF DOBLE POLE STRUCTURE WITH COMPLITE FITTING OF ALL ACCESSORIES. |
| 5 | CONSTRUCTION OF 11/.04/10/25/63/100 KVA SUB. STATION COMPLITE INCLUDING THE FITTING OF ALL ACCESSORIES. |
| 6 | CARRIAGE OF 250/400 KVA TRANFORMER FROM S.C.HASARI TO WORK SITE . |
| 7 | CARRIAGE OF 10/16//25/63/100 KVA TRANFORMER FROM E.S.C.HASARI TO WORK SITE . |
| 8 | THE WORK OF PROPER PLACEMENT OF TRANSFORMER ON DOUBLE POLE / TRANSFORMER PLINTH. |
| 9 | DRILLING OF HOLE ON 11 KVX- ARM, TOP CHANNLE T-OFF,DROPER CHANNLE AND OTHER ACCESSORIES INCLUDING THE WORK OF ITS CARRIGE |
| 10 | FIXING OF EARTHING ROD COMPLITE. |
| 11 | ERRECTION AND GRAUTING OF STEY SET COMPLITE AS PER RESPO\". |
| 12 | PIT DIGGING OF HARD ROCKY/ DAMMAR/ RCC SURFACE ETC. |
| 13 | PAINTING OF 11 KV 11 MTR LONG STP WITH RED OXIDE/ SILVER OXIDE PAINT. |
| 14 | ERRECTION OF 11KV LINE FROM EXISTING 11KV LINE TO NEW CONSTRUCTED DOUBLE SINGLE POLE STRUCTURE AT DIFFERENT PLACE\"S. |
| 15 | LAYING /FIXING OF LT P.V.C.CABLE INCLUDING THE WORK OF CRIMPING OF LUG\"S AND CONNECTION TO TANSFORMER /LINE. |
| 16 | GUARDING OF 11KV LINE WITH G.I WIRE,ANGLE AND NUT BOLT ETC. AS PER RESPO. |
| 17 | LAYING OF ACSR WEASEL / RABIT CONDUCTOR INCLUDING IT\"S SAGGING STRINGING, BINDING AND JUMPRING ETC. |
| 18 | LAYING OF ACSR RECOON/ DOG CONDUCTOR INCLUDING IT\"S SAGGING STRINGING, BINDING AND JUMPRING ETC. |
| 19 | LAYING OF AB CABLE OF SIZE 3X50/95/120 SQMM ON POLE. |
| 20 | INSTALLATION OF LT DISTRIBUTION BOX 3PH.ON POLE. |
| 21 | GIVING THE CONNECTION THROUGH INSTALLED DISTRIBUTION BOX. |
| 22 | CARRIAGE OF 11 KV MEETRING CUBICAL 10/5A,15/5A,20/5A AND AVOBEFROM ESC HASARI TO DIFFERENT CONSUMER WORK SITE. |
| 23 | LAYING OF 11 KV XLPE CABLE OF SIZE 3X25/35/70/120 SQMM ON POLE WITH THE HELP OF GI WIRE &UNDER THE SURFACE /CABLE TRINCH. |
| 24 | INSTALLATION OF 11 KV MEETRING CUBICAL 10/5A,15/SA,20/SA AND AVOBE TO DIFF ERENT CONSUMER WORK SITE.INCLUDING ITSGRAUTING |
| 25 | FIXING /MOUNTNING OF 11 KV TERMINATION KIT OF SIZE 3X25/35/70/120 SQMM. |
| 26 | CONNECTION THE CABLE THROUGH MEETRING CUBICAL AND DOUBLE POLE. |
| 27 | CONSTRUCTION OF TRANFORMER PLINTH OF SIZE-5X5X4 FEET AS PER DIRECTION OF THE ENGINEER. WITH THE HELP OF BRIC,RIVER SAND & STONE BLAST INCLUDES THE COST OF LABOUR, T&P PROVIDED BY THE CONTRACTOR FOR PROPER COMPLETION OF WORK. |
| 28 | FABRICATION AND FIXING OF SPECIAL TYPE H BRACKET MADE OF 100X50X5 MS CHANLE AND 50X50X5 MS ANGLE WITH NUT BOLT & CLAMPS ETC. |
| 29 | EARTHING OF DISTRIBUTION TRANSFORMER BY EARTHING ELECRODE BY G.I. ELECRODE OF 80 MM DIA B GRADE, COMPLETE TO THE REQUIRMENT OF S.SPECIFICATION. ITS INCLUDE THE COST OF ALL MATERIAL, LABOUR, T&P PROVIDED BY THE CONTRACTOR FOR PROPER COMPLETION OF WORK. |
| 30 | DISMENTLING OF OLD DAMAGE POLE/DUE TO ERRECTED NEW POLE FROM DIFFRENT WORK SITE INCLUDING ITS CARIAGE FROM WORK SITE TO JE STORE / ESC HASARI JHANSI. |
| 31 | TREE CHOPING |
| 32 | PROVIDED FIXING OF NUT & BOLT |
| 33 | PROVIDED FIXING OF DANGER BOARD (IF NOT AVILABLE IN ESC JHANSI.) |
| 34 | PROVIDED FIXING OF BARBED WIRE (IF NOT AVILABLE IN ESC JHANSI.) |
| 35 | PROVIDED FIXING OF I-HOOK FOR LT ABC (IF NOT AVILABLE IN ESC JHANSI.) |
| 36 | PROVIDED FIXING OF SUSPENTION CLAMP FOR LT ABC (IF NOT AVILABLE IN ESC JHANSI.) |
| 37 | PROVIDED FIXING OFDEAD END CLAMP FOR LT ABC (IF NOT AVILABLE IN ESC JHANSI.) |
| 38 | PROVIDED FIXING OF 11 KV HEAT SHIRINK CABLE JOINTING KIT OF SIZE 3X70/120SQMM (IF NOT AVILABLE IN ESC JHANSL) |
| 39 | Wire Mess Fencing |
| 40 | Digging of Cable Trench and Cover With first Class Bricks protection anf filling the river sand including back filling by sand for laying of 11KV/LT cable. |