Tender For Annual Plan-174/26-Kumily Gp 2025-2026- Kuryan Nagar Munippara Road Concrete Ward 18-General Civil Work - Road 2 3.9.2.B:Excavation In Hard Rock (Blasting Prohibited)<Br> Excavation For Roadway In Hard Rock (Blasting Prohibited) With Rock Bre
Tender Overview
Project Description
Tender For Annual Plan-174/26-Kumily Gp 2025-2026- Kuryan Nagar Munippara Road Concrete Ward 18-General Civil Work - Road 2 3.9.2.B:Excavation in Hard Rock (blasting prohibited)<br> Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in tippers and disposal with a lift upto 1.5 m and lead upto 1000 metres, trimming bottom and side slopes in accordance with requirements of lines, grades and cross- sections as per Technical Specification Clause 302.3.5 <br>(B) Mechanical Means 3 OD281585/2025-2026:DOWEL BARS - Supplying and providing MS dowel bars of size 16 mm dia of 1m long (0.5m in rock and 0.5m in concrete ) including drilling holes of 20mm dia to a depth of 1m in rock and filling the gap with cement grout( 0.10kg/each) etc complete. 4 11.4.3.1:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203<br>III. P.C.C. grade M 20 (i) Nominal mix (1:2:4) 5 11.1.1.1:Excavation for Structures <br> Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. <br> I. Ordinary soil <br> (i) Upto 3 m depth 6 OD281591/2025-2026:DRY RUBBLE MASONRYwith hard stone, Without Through/Bond stone in foundation and superstructure including packing to compactness to lines and levels, cost and conveyance of all materials labour charges etc. complete as per approved drawing and relevant technical specifications. (From 75.7.1) 7 OD281607/2025-2026:DRY RUBBLE MASONRYwith hard stone (using Dept. Stone), Without Through/Bond stone in foundation and superstructure, including packing to compactness to lines and levels, excluding cost and conveyance of all materials but including labour charges etc. complete as per approved drawing and relevant technical specifications. (From 75.7.1) 8 11.4.4:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203<br> IV. R.C.C grade M 20 9 11.8:Supplying, fitting and placingTMT bar reinforcement in foundation complete as per drawings and technical specifications Clauses 1000 and 1202 10 3.5.2:Excavation in Soil with Dozer with lead upto 100 m <br> Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections. 11 75.8.1:Providing Plain cement concrete for road work CC 1:2:4 (1 cement: 2 fine aggregate: 4course aggregate) laid to required slope and camber in panels (@ 3 m c/c) as requiredincluding compaction, finishing and tamping etc .complete. Max. size of courseaggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification (i) Nominal mix (1:2:4)
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 04-Oct-2025 | Time extension | Date | 04-Oct-2025 |
BOQ
| Sl. No. | Item Description |
| 1 | Road |
| 2 | 3.9.2.B:Excavation in Hard Rock (blasting prohibited)<br> Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in tippers and disposal with a lift upto 1.5 m and lead upto 1000 metres, trimming bottom and side slopes in accordance with requirements of lines, grades and cross- sections as per Technical Specification Clause 302.3.5 <br>(B) Mechanical Means |
| 3 | OD281585/2025-2026:DOWEL BARS - Supplying and providing MS dowel bars of size 16 mm dia of 1m long (0.5m in rock and 0.5m in concrete ) including drilling holes of 20mm dia to a depth of 1m in rock and filling the gap with cement grout( 0.10kg/each) etc complete. |
| 4 | 11.4.3.1:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203<br>III. P.C.C. grade M 20 (i) Nominal mix (1:2:4) |
| 5 | 11.1.1.1:Excavation for Structures <br> Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. <br> I. Ordinary soil <br> (i) Upto 3 m depth |
| 6 | OD281591/2025-2026:DRY RUBBLE MASONRYwith hard stone, Without Through/Bond stone in foundation and superstructure including packing to compactness to lines and levels, cost and conveyance of all materials labour charges etc. complete as per approved drawing and relevant technical specifications. (From 75.7.1) |
| 7 | OD281607/2025-2026:DRY RUBBLE MASONRYwith hard stone (using Dept. Stone), Without Through/Bond stone in foundation and superstructure, including packing to compactness to lines and levels, excluding cost and conveyance of all materials but including labour charges etc. complete as per approved drawing and relevant technical specifications. (From 75.7.1) |
| 8 | 11.4.4:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203<br> IV. R.C.C grade M 20 |
| 9 | 11.8:Supplying, fitting and placingTMT bar reinforcement in foundation complete as per drawings and technical specifications Clauses 1000 and 1202 |
| 10 | 3.5.2:Excavation in Soil with Dozer with lead upto 100 m <br> Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections. |
| 11 | 75.8.1:Providing Plain cement concrete for road work CC 1:2:4 (1 cement: 2 fine aggregate: 4course aggregate) laid to required slope and camber in panels (@ 3 m c/c) as requiredincluding compaction, finishing and tamping etc .complete. Max. size of courseaggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification(i) Nominal mix (1:2:4) |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender