| 1 | Carriage of following material from store center PVVNL to site & vice-versa of work including loading & unloading at both ends maximum distance up to 100 Km. :- |
| 2 | PCC/STP Pole 8.5/11 Mtr. Long. |
| 3 | LT AB Cable 3x95+1x70+1x16 sq.mm |
| 4 | Stay Set Complete |
| 5 | 33 KV XLPE Cable 3x300 sq.mm |
| 6 | 33 KV Cable Jointing Kit 3x300 sq.mm |
| 7 | 33 kv Pin Insulator with Pin |
| 8 | 33 kv Disc Insulator with Fitting |
| 9 | 33 kv V type X-arm |
| 10 | Earthing Rod Complete |
| 11 | ACSR RABBIT Conductor |
| 12 | G.I WIRE 8 SWG |
| 13 | G.I WIRE 6 SWG |
| 14 | Errection PCC/STP Pole 8.5/11 Mtr. long after digging a pit of size 1.6 mtr deep in all type of Soil including grouting ratio (1:4:8) & back filling of the pole with proper ramming after completion of work. (as per UPPCL Respo). |
| 15 | Laying, lifting of LT AB Cable 3x95+1x70+1x16 sq.mm (as per UPPCL Respo). |
| 16 | Laying of 33 XLPE Cable 3x300 sq.mm (as per UPPCL Respo). |
| 17 | Laying of ACSR RABBIT Conductor (as per UPPCL Respo). |
| 18 | Fixing of 33 KV Pin Insulator with fitting (as per UPPCL Respo). |
| 19 | Fixing 33 kv Disc Insulator with Fitting (as per UPPCL Respo). |
| 20 | Fixing of 33 KV X-arm V type (as per UPPCL Respo). |
| 21 | Fixing of 33 KV Jointing Kit 3x300 sq.mm (as per UPPCL Respo). |
| 22 | Fixing of Stay set for 33 kv & 11 kv complete after digging a pit of size 1.6 mtr deep and grouting the same in block of size 0.60 x 0.60 x 0.30 mtr and nuzzling at the both ends and filling the pit with excavated earth soil with proper ramming.(As Per Direction of Supervising Engineer). |
| 23 | Fixing of MS Earthing rod of each 33 kv & 11 KV line and pole after drive of electrodes if size 20mm x 250 mm and connection the earthing point with GI wire.(As Per Direction of Supervising Engineer). |
| 24 | Fixing of 11 KV X-arm (as per UPPCL Respo). |
| 25 | Providing and fixing HDPE Pipe 6\" for 300 sq.mm cable along Rod (as per UPPCL Respo). |
| 26 | Providing and fixing GI Pipe 6\" dia (Supporting for Cable for DP) (as per UPPCL Respo). |
| 27 | Providing and fixing Holding Clamp (as per UPPCL Respo). |
| 28 | Providing and fixing Stone Pad (as per UPPCL Respo). |
| 29 | Providing and fixing F bracket (as per UPPCL Respo). |
| 30 | Grouting of Pole (as per UPPCL Respo). |
| 31 | Grouting of Stay (as per UPPCL Respo). |
| 32 | Providing and fixing of MS Nut and bolts (As Per Direction of Supervising Engineer). |
| 33 | Providing and fixing of Distribution Box with clamp 3 phase (As Per Direction of Supervising Engineer). |
| 34 | Providing and fixing of LT Insulator Piercing Connector(As Per Direction of Supervising Engineer). |
| 35 | Providing and fixing ofInsulator Suspension Clamp with J hook(As Per Direction of Supervising Engineer). |
| 36 | Providing and fixing ofDead and Clamp with J hook(As Per Direction of Supervising Engineer). |
| 37 | Providing and fixing of F clamp for Top Insulator(As Per Direction of Supervising Engineer). |
| 38 | Labour charge with laying material by HDD method(As Per Direction of Supervising Engineer). |
| 39 | Laying & Fixing of G.I Wire 8 SWG(As Per Direction of Supervising Engineer). |
| 40 | Laying & Fixing of G.I Wire 6 SWG(As Per Direction of Supervising Engineer). |
| 41 | Back Carriage of LT AB Cable 3x95+1x70+1x16 sq.mm(As Per Direction of Supervising Engineer). |
| 42 | Back Carriage of Old and used Line Material Such as Clamp/Channel/Cross Arm/Conductor etc(As Per Direction of Supervising Engineer). |