| 1 | Earth work excavation for foundation and depositing on bank with in the initial lead of 10m and a lift of 2m in hard stiff clay, stiff block cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders etc. complete. complying with std. specifications.SS 20 B |
| 2 | Plain Cement Concrete 1:4:8 Mix (one part cement, Four part M sand and Eight part of aggrigate) using 40mm size ISS HBG metal machine crushed from approved quarry including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete. Complying with std. specifications. |
| 3 | Supplying and erecting Centering for sides and soffits including supports and strutting upto 3.29 m high for plane surfaces such as RCC slabs, Rectanular beams, Lintels and Stair case waist slabs conopy etc., in all floors with all cross bracings using mild steel sheets of size 90cm x 60cm and BG 10 stiffened with welded mild steel angles of size 25mm x 25mm x 3mm for boarding laid over country wood joists of size 10cm x 6.50cm spaced at about 90cm centre to centre and supported by Casuarian props of 10cm to 13cm dia spaced at 75cm centre to centre etc., complete and as directed by departmental Engineers. |
| 4 | Columns |
| 5 | Plinth Beam |
| 6 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - |
| 7 | Supplying fabricating and placing in position of steel rods using TMT. or Ribbed Tor Steel including cost of binding wire, cost of labour charges for fabrication and placing in positionetc. Complete. Complying with std. specifications. |
| 8 | SUPPLY AND FIXING MS STRUCTURE,TENSILE POLYESTER FABRIC MINIMUM OF 950 GSM TENSILE MEMBRANE INCLUDING MS STRUCTURAL STEEL WORK IS FINISHED WITH ONE COAT OF PRIMER AND ONE COAT OF PAINT WITH STAY ACCESSORIES,PATTERNING,CUTTING,HF WELDING WITH INSTALLATION AND BASEPLATE FOUNDATION BOLT INCLUDING TRANSPORTATION( 100 FT * 16 FT ) ( As per quotation ) |
| 9 | Reinforced Cement Concrete 1:1½:3 Mix (One part cement, one and half part m.sand and three part of aggregate)using 20mm size ISS HBG metal machine crushed from approved quarry including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing but excluding cost of reinforcement etc.Complete with std.Specifications. TNDSS NO: 30 V, VI (S3), VII-3. |
| 10 | All figures quoted should be inclusive of GST Charge |