| 1 | Electrical Items : |
| 2 | Dismentalling of X-Arm/L.T. brackets and insulators etc. from the damaged pole/pole to be replaced/shifted. |
| 3 | Excavation of foundation and taken out the damaged pole/pole to be replaced/shifted from the ground. |
| 4 | Repairing of damaged S.T. Pole by providing M.S. ANGLE 65x65x6 mm(3 METER),Ms pole Clamp with Nut & Bolt(Clamping of both Ends), Concreting for Grouting and Muffing of pole with all material (2FEET Grouting And 1 feet Muffuing) and its welding including its all related work. |
| 5 | Loading, Carriage and unloading of STP poles from store to work site. |
| 6 | Loading, Carriage and unloading of damaged poles from work site to store. |
| 7 | Loading, Carriage and unloading of PCC Poles from store to work site. |
| 8 | Grouting of pole with cement brick ballast and coarse sand as per Standard Spacification. |
| 9 | Erection of Old/new Steel Tubular pole for H.T. O.H./ L.T. O.H. line and fitting of X-Arms/L.T. Brackets, insulators and other hardware fittings. |
| 10 | Making plinth of single pole of 400 mm dia, 600 mm height (200mm underground) with C.C. in ratio 1:4:8 of cements, stone ballast and coarse sand including cost of materials. |
| 11 | Erection of double pole structure including fixing of T.P.M.O. (if available) top channel, fuse set on fuse set channel etc. as per standard specifications. |
| 12 | Making plinth of Double Pole structure in size of 450x2250x600mm (200mm depth underground) with C.C. ratio 1:4:8 of cement, stone ballast and coarse sand including cost of materials. |
| 13 | Erection of Tri-Pole structure including fitting of channels etc. and proper alignment. |
| 14 | Painting of pole after rubbing cleaning with emery paper and coating with one coat of red oxide on full length of pole and then two coat of aluminum paint. |
| 15 | Excavation of foundation and taken out the damaged PCC pole to be replaced. |
| 16 | Grouting of PCC pole with cement brick ballast and coarse sand as per Standard Spacification. |
| 17 | Erection ofnew PCC pole for L.T. O.H. line and fitting of all related hardware |
| 18 | Increasing the pole length to Cross H.T./L.T. OH line by welding of M.S. pipe with all Material |
| 19 | Erection of stud pole/fly stay and fixing of stay wire etc. for complete erection. |
| 20 | Fixing of stay rod and its erection by fitting of stay clamp. Stay wire and its proper binding and tightening etc. |
| 21 | Dismentalling of binding wire from insulators and lossening of the conductor on each pole then lowering down the conductor & rolling in to bundles. |
| 22 | Loading, carriage and unloading of conductor from store to work site and vice versa |
| 23 | Re-sagging of conductor, on old line after erection of pole, binding of conductor etc. |
| 24 | Laying, stringing, tensioning and binding of Old & New Weasal conductor for H.T./L.T. O.H. |
| 25 | Laying, stringing, tensioning and binding of Old & New Dog conductor for H.T./L.T. O.H. |
| 26 | Fixing of guarding angle/guarding channel for laying of guarding Old & New |
| 27 | Laying, stringing, tensioning & final sagging ofEarth wire/G.I. wire Old & New |
| 28 | Cross lacing of guarding by G.I. wire (approximate 5 lacing of each span) |
| 29 | Opening of H.T. Jumpers from the existing 3 Phase 3 Wire H.T. O.H. line for erection work. |
| 30 | Opening of L.T. Jumpers from the existing L.T. O.H. line for erection work. |
| 31 | Making of H.T. Section points by brackets, clamps & Insulator, tightening of Line, binding of conductor & proper connection. |
| 32 | Making of L.T. Shackle point by brackets, clamps, G.I. Shakle strips and insulators, tightening of line, binding of conductors and proper connections. |
| 33 | Fabrication/modifications of M.S. Items as per requirement of site conditions. |
| 34 | Jumpering of H.T. Lines from the existing H.T.O.H. line. |
| 35 | Jumpering of L.T. Lines from the existing L.T.O.H. line. |
| 36 | Cutting of tree branches for normal clearance of H.T. as well as L.T.O.H. Lines. |
| 37 | Dismentalling of Aearial Bunched Cable from L.T. O/H (damage) line. |
| 38 | Loading, carriage and unloading of Aearial Bunched Cablefrom store to work site and vice versa. |
| 39 | Laying of Old & New Aearial Bunched Cable for Erection of L.T. O/H Line. |
| 40 | Mounting & Erection of single phase distribution box Old & New. |
| 41 | Mounting & Erection of three phase distribution box. Old & New |
| 42 | Opening and reconnection of consumer connections for shifted/replaced of pole. |
| 43 | Making of cable box for 11/6.6 KV 3x50 to 3x300 mm2 for XLPE/PILLCA cable (Jointing kit will be provided by Kesco.) |
| 44 | Stringing of H.T./L.T. Cable in different sizes as same as H.T./L.T. overhead line Single Core L.T. Cable |
| 45 | Stringing of H.T./L.T. Cable in different sizes as same as H.T./L.T. overhead line 3 ½ Core L.T. Cable |
| 46 | Stringing of H.T./L.T. Cable in different sizes as same as H.T./L.T. overhead line 11 KV H.T. Cable |
| 47 | Construction of T/F plinth, suitable for mounting of distribution transformer. Size of the plinth will be 1.2 x 1.2 x 1.2 meter solid with brick work. 75 mm thick C.C. in ratio 1:3:6 with cement, coarse sand and brick ballast laid on the base and 75 mm thick done on all the exposed sides to the plinth. |
| 48 | Loading, carriage & unloading of distribution Transformers (Up to 630 K.V.A.) from store to site & vise-versa. |
| 49 | Erection of Distribution T/F on plinth/D/pole structure. |
| 50 | Connection of H.T. Jumper from fuse set to H.T. Busing of the transformer. |
| 51 | Fitting of L.T. D.B. by brackets & clamps on double pole structure & L.T. Cable Connection from T/F Cable to L.T.D.B. |
| 52 | Connection of L.T. cable from L.T.D.B to L.T.O.H. |
| 53 | To provide of Distribution T/F fencing of frame size 3x2.4 Mtr. including cost of M.S. Agnle size 40x40x5 and M.S. Flat size 35x5, fixing of welded steel wire fabric on steel frames by welding of 10 SWG wire fabric, including Painting of two coats of paint on iron based surfaces with ready mixed paint to give bus green shade including clening of oil & dust. |
| 54 | Reparing Distribution T/F fencing with all Material and Painting of two coats of paint on iron based surfaces with ready mixed paint to give bus green shade including clening of oil & dust. |
| 55 | Reparing of T/F plinth, Size of the plinth will be 1.2 x 1.2 x 1.2 Cubic Mtr including civil matrial will be solid with brick work 75 mm thick C.C. in ratio 1:4:8 with cement, coarse sand and brick ballast with step. |
| 56 | Digging of pit and making of 300x300x450 mm chamber with brick & sand work covered with RCC surrounding the GI Pipe with Cover. all material shall be provided by contractor with cost of all material. |
| 57 | Deep Bore GI Pipe Earthing including supply Size GI Pipe 40mm dia, Thickness minimum 3 mm, B-Class 80 feet long with socket cutter and connection of pipe to distribution T/F Neutral or Body with 25x3mm G.I. Strip of length 80 feet inside the GI pipe, 100 Kg Salt and 100 Kg charcoal Powder for each earthing. all material shall be provided by contractor with cost of all material. |
| 58 | Disconnection of H.T./L.T. Lines, Shifting of T/F from ground to a safe place for construction of T/F plinth. |
| 59 | Shifting of T/F from ground to plinth and re-connection of H.T. L.T. Lines as well as earthing for proper completion. |
| 60 | Taking out new/old H.T. Cable from cable drum and then after tranportation from store to work site or vice-versa. |
| 61 | Taking out new/old L.T. Cable from cable drum and then after tranportation from store to work site or vice-versa. |
| 62 | Digging of cable trench in Normal Soil (size of 30cm. Wide and 60 to 90 Cm. meter deep as per site requirement for laying of cable) |
| 63 | Digging of cable trench in Kharanja Road (size of 30cm. Wide and 60 to 90 Cm. meter deep as per site requirement for laying of cable) |
| 64 | Digging of cable trench in Metallic Road (size of 30cm. Wide and 60 to 90 Cm. meter deep as per site requirement for laying of cable) |
| 65 | Laying of H.T. Cable in the above digging, trench, covering with bricks, sand and back filling. |
| 66 | Laying of L.T. Cable in the above digging, trench, covering with bricks, sand and back filling. |
| 67 | Laying of H.T. Cablethrough Hume/C.I./MS. Pipe in digged trench and back filling. |
| 68 | Laying of L.T. Cablethrough Hume/C.I./MS. Pipe in digged trench and back filling. |
| 69 | Taking out (old & used) H.T. cable by digging of trench from site and then rolling in to bundles. |
| 70 | Taking out (old & used) L.T. cable by digging of trench from site and then rolling in to bundles. |
| 71 | Restoration of Metallic/RCC road after proper reparing with appropriate materials. |