| 1 | Earth work excavation for foundation complying with reference clause of TNSS well sinking with in the initial lead of 10 mtr and initial lift of 2 mtrin hard stiff clay, stiff block cotton , hard red earth, shallsmurram earth mixed with small size boulders including all other labour charges etc., complete as per std., specification |
| 2 | Plain Cement Concrete 1:4:8 Mix (one part cement, four part sand and eight part of aggrigate) using 40 mm size ISS HBG metal from approved quarry including cost and conveyance of all materials to site. loading and unloading charges and labour charges for mixing. laying and curing etc., complete. complying with std., specifications. |
| 3 | Supplying and erecting centering for sides and soffits including supports and srtutting upto 3.29 m height for plane surfaces in all floors with cross bracings using miled steel sheets of size 30cm x 60cm and 10 gauge stiffened welded with miled steel sheets of size 25mm x 25mm x 3mm for boarding and laid over silver oak (country wood).Joists of size 10cm x 6.5cm dia spaced at about90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced 75cm centre to centre etc., complete complying with standard specification ans as directed for the following items as per MORTH Specification 1500. (For Column& Grade Beam )FORCOLUMNS |
| 4 | FOR GRADE BEAMS & FOOTINGS |
| 5 | FOR ROOFSLABS |
| 6 | Supplying fabricating and placing in position of RTS steel rods for reinforcement including the cost of steel and binding wire etc., complete and as directed by Departmental officers. |
| 7 | contenet of 400Kg/ cum and maximum water cement ratio of 0.45 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone sand (M- Sand) but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - The Coarse and Fine aggregates to be used should comply with the requiremnents of IS standards. |
| 8 | Plastering in Cement Mortor 1:3 Mix (one cement, three sand )10mm thick including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete. complying with std. specifications. |
| 9 | Brick Work in Cement Mortor 1:5 Mix (one cement, five sand ) using new best II class Bricks of size 9 x 41/2 x 3 from approved quarry including cost and conveyance of all materials to site. loading and unloading charges and labour charges for mixing, laying and curing etc. complete. complying with std. specifications. |
| 10 | Plastering in Cement Mortor 1:5 Mix (one cement, five sand ) 12 mm thick including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete. complying with std. specifications. |
| 11 | Plastering in Cement Mortor 1:4 Mix (one cement, four sand ) 20 mm thick including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete. complying with std. specifications. |
| 12 | Supplying and fixing of M.S.grill Tress with Purlion of approved design for MSPipeusing necessary mild steel flats for inner and outer members which should be fixed toframes inclusive of priming coat of best approved quality red oxide primer etc., complete complying with standared specifications. |
| 13 | Painting two coats ready mixed Approved Exterior Emulsion of first quality and of approved colour over a primingcoat including through scarbing clan removel ofone coat of priming with best Cement paintas directed by the department officers etc completeand including necessary plaster of paris whever regd.(S.l.No.358)-10sqmcomplete. as per std., specifications. |
| 14 | Painting two coats new iron workfor grills, with two coat synthetic enamel paint and approved quality and colour including priming coat .The rate is inclusive of cost of all materials, labour brushes and scaffolding charges etc., complete complying with standard specifications. |
| 15 | Paving the floor with design Antiskirt ceramic tiles (colour and shade as directed) of size 305 mm x 305mm x 6 mm in all floors over a base layer of cement mortar 1:3 (One part of Cement and Three part of Plastering Sand (P- Sand)), 20mm thick laid in-situ and pointed with same coloured cement |
| 16 | Dadooing the walls with best approved quality colour glazed tiles of size 300 x 200 x 6mm set in CM 1:2 (One of cement and two of sand) 10mm thick and pointing with colour cement using 0.4kg per m2 neatly in all floors as directed etc., complete complying with standard specifications. |
| 17 | Plastering in Cement Mortor 1:3 Mix (one cement, three sand )20mm thick including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete. complying with std. specifications. |
| 18 | Supply and fixing in position EWC type Colourwater closet includes \"P\" (or) \"S\" trap including cost and conveyance of all materials to site and all labour charges etc., to complete as per std.,specifications. |
| 19 | Supplying and fixing in Position of Indian Oriya pan type water closet with “P’’ or “S’’ trap to set in brick jelly concrete 1:4:8 Mix concrete 10 cm thick using 20mm brick jelly and top finished with c.m. 1:3 mix 20mm thick without any leakage etc. complete. |
| 20 | Supply and delivery of PVC and GI Pipe including cost and conveyance of all materials to siteand all labour charges etc.as per standard specification. ( Excluding Pipe Laying Labourcharges )50mm dia pvc pipe 10kg/cm3 |
| 21 | 63mm dia pvc pipe 6kg/cm4 |
| 22 | 90mm dia pvc pipe 6kg/cm6 |
| 23 | 110mm dia pvc pipe 6kg/cm7 |
| 24 | Laying and jointing of PVC and GI Pipes including cost and conveyance of all materials to site and fixingall labour charges etc. complete as per standard specification.( ExcludingPipe Cost )50 mm to 75 mm dia pvc pipes |
| 25 | 90 mm to 110 mmdia pvc pipes |
| 26 | Supply and run of 2 of 4 sq.mm. (56 / 0.3) PVC insulated SC unsheathed copper conductor of 1100V grade in 25mm dia GI pipe (Class \"B\") suitably bent at both ends with necessary angle iron upright and end supports for mains [ SD NO. 70 ] |
| 27 | Supply and run of 4 of 6 sq.mm. (84 / 0.3) PVC insulated SC unsheathed copper conductor of 1100V grade in suitable PVC rigid pipe concealed in wall and ceiling with continuous earth wire connection by 14 SWG TC wire and making good of the concealed portion with suitable colour [ SD NO. 63 ] |
| 28 | Wiring with 2 x 1.5 sq.mm. (22 / 0.3) PVC insulated SC unsheathed copper conductor of 1100V grade in suitable PVC rigid pipe concealed in wall and ceiling with PVC accessoires in flush with wall with 3mm thick hylum sheet cover with TW switch box and 5A FT switch and making good of the concealed portion with suitable colour for PVC concealed light / fan Point (for electronic regulator) (5 points per coil)[ SD NO. 21 ] |
| 29 | Supply and fixing of single box type 4\"40W fluorescent fitting complete with copper choke and condensor with conduit pipe suspension from the ceiling with PVC unsheathed copper leads from terminals to the fitting with tube [SD89] |
| 30 | Supply and fixing of WT bulk head fitting with guard (Philips / Bajaj / Crompton / K. Lite) suitable for11W CFL lamp with CFL. SD-83 |
| 31 | Providing UPVC (Un-Plasticized Polyvinyl Chloride) Door: Providing and fixing casement doors fabricated from un-plasticized polyvinyl chloride (uPVC) sections. Profiles: The profiles should be three chamber system which provides high insulation properties with outer frame 60mm x 55mm with an outer wall thickness of 2.4mm. The window unit should be designed with all corner joints mitred and fusion welded. Windows should be steel reinforced with 25 x 24 x 25mm steel reinforcement with a thickness of 1mm to have dimensional stability. The sash should be of 60 x 102mm. The mullion should be of 60 x 74mm. The profiles should have co-extruded seals. Hardware: All the hardware like friction stays, handles should be screwed with self tapping screws. The handles, locks should be designed so that they cannot be released from outside.Glazing: The window system should be glazed with 5mm plain float glass / 6mm bison lam Installation: The profiles should be cut to length and welded 45 degrees. The window should be designed such that the water drainage does not pass through the reinforcement chamber. The window system should be fixed directly to the plastered brick wall using self expanding nylon plug and driving ms electroplated screws into plug.(SOR Item no.268,P.No.65) |
| 32 | Providing UPVC (Un-Plasticized Polyvinyl Chloride) Ventilator: Providing and fixing casement Ventilator: fabricated from un-plasticized polyvinyl chloride (uPVC) sections. Profiles: The profiles should be three chamber system which provides high insulation properties with outer frame 60mm x 55mm with an outer wall thickness of 2.4mm. The window unit should be designed with all corner joints mitred and fusion welded. Windows should be steel reinforced with 25 x 24 x 25mm steel reinforcement with a thickness of 1mm to have dimensional stability. The sash should be of 60 x 102mm. The mullion should be of 60 x 74mm. The profiles should have co-extruded seals. Hardware: All the hardware like friction stays, handles should be screwed with self tapping screws. The handles, locks should be designed so that they cannot be released from outside.Glazing: The window system should be glazed with 5mm plain float glass / 6mm bison lam Installation: The profiles should be cut to length and welded 45 degrees. The window should be designed such that the water drainage does not pass through the reinforcement chamber. The window system should be fixed directly to the plastered brick wall using self expanding nylon plug and driving ms electroplated screws into plug.(SOR Item no.270,P.No.66) |
| 33 | Supply and delivery and Fixing of HDPEtank 1000 Lts.Capacity As per Is12701 / 1996 inculingloading , unloading , transportation cost and conveyance of all materials and all labour charges. etc., complete |
| 34 | Provisions for Supply and fixing of Water supply Arrangements Materials including cost and conveyance all labour charges etc., complete |
| 35 | Provisions for Supply and fixing ofSeweage Arrangements Materials including cost and conveyance all labour charges etc., complete |
| 36 | Provisions for Supply and fixing of ElectricalArrangements Materials including cost and conveyance all labour charges etc., complete |