| 1 | Dismantling the existingpaver blockin the existing road clearing away from the work site and carefully stacking the usefull materials for reuse on the road side as directed by the departmental officers including all labour and incidental charges etc., complete. |
| 2 | Road A |
| 3 | Excavation for Roadway and DrainageExcavation including removal and satisfactory disposal of all materias necessary for the construction of roadway and side drains in accordance with the specifications and the lines, grades and cross sections shown in the drawings or as indicated by the Engineer as per MORTH Rev. V Clause No. 111, 112, 301 to 305.a) Box Cutting for widening portion, Paver Block portion and Core wall |
| 4 | Road A |
| 5 | Laying,Spreading and compacting graded stone aggregates for Wet Mix Macadam, on well prepared Surface and compacting with Vibrator to acheive desired density including cost of Labour Charges, rentals for machinery, and other incidental charges etc, complete as per clause 406 of MORTH Rev. V |
| 6 | Road A |
| 7 | Construction of dry lean cement concrete sub base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150kg/cum, concrete strength not to be less that 10Mpa at 7 days, mixed at site, compacted using vibrator, finishing and labour charges |
| 8 | Road A |
| 9 | Providing and laying of tack coat over Dry Lean cement concrete surface using of 3.00 kg of bitumen emulsion (RS 1) per ten square metre for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 503 of MORTH Rev-5. |
| 10 | Road A |
| 11 | Providing and laying Tack Coat over Existing BT surface using 2 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5 |
| 12 | Road A |
| 13 | Providing, laying 80mm consolidated thick Bituminous Macadam using 0.20cum of 26.50- 13.20mm, 0.43cum of 13.20-2.36mm and 0.08cum of 2.36mm & below size IRC metal with 37 Kgs of VG30 Grade bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen, aggregate and mixing them in required temperature using Central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory Roller to the required density etc., including labour for attending to paver to site etc., including hire and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including all other incidental charges etc., complete as per specification using CMP as per clause 504 of MORTH Rev-5. |
| 14 | Road A |
| 15 | Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 |
| 16 | Road A |
| 17 | Vibrated cement concrete M15 Grade using 20 mm ISS HBG metal including cost and conveyance of all materials to site, including cost and labour charges for form work and centering, labour charges for laying, compacting, curing, and all incidental charges etc., complete foras per standard specification FOR Core Wall |
| 18 | Road A |
| 19 | Filling quarry dust from approved quarry including cost and conveyance of quarry dust and labour charges for filling the quarry dust etc., complete. For Paverblock portion |
| 20 | Road A |
| 21 | Reusingand Laying of TAMIN Paver Block of size 80mm thick (Available at site ) over a base of crushed stone filling including all labour charges for laying, compacting including Hire and fuel charges for all tools and plants employed for this work and all other incidental charges etc. complete as per standard Specification |
| 22 | Road A |
| 23 | Vibrated cement concrete M20 Grade using 20 mm ISS HBG metal including cost and conveyance of all materials to site, including cost and labour charges for form work and centering, labour charges for laying, compacting, curing, and all incidental charges etc., complete foras per standard specification |
| 24 | Road A |
| 25 | Vibrated Cement Concrete of grade M30 75mm thick using 25mm, 12mm, 6mm IRC HBG metal including cost and conveyance of all materials to work site including cement at site, including all labour charges for mixing concrete, laying hirecharges for tools and plants compacting curing with all leads for soft water, including all other incidental charges formwork, cost of premoulded expansion joints and fixing the same in position etc., complete for WEARING COAT. |
| 26 | Road A |
| 27 | Calculation of SubTotal, GST and Total Amount carried out by system automatically |
| 28 | Basic cost of value put to tender as per estimate |
| 29 | Add GST at 18% |
| 30 | Total Value put to Tender |
| 31 | Quoted Percentage |
| 32 | Quoted Value |
| 33 | Add GST at 18% of Final Quoted Value |
| 34 | Total Value of Contract Including 18% of GST |
| 35 | Basic cost of value put to tender as per Estimate |
| 36 | Quoted Rate in Figures (Total Value of Contract Including 18% of GST ) |
| 37 | Quoted Rate in Words |