| 1 | Road Work |
| 2 | Picking the existing BT surface upto 50mm depth including levelling, sectioning, Bed rolling etc., complete (labour charges only) |
| 3 | Road A |
| 4 | Road E |
| 5 | Wet Mix Macadam (Table 400-13) Providing, laying, spreading and compacting graded stone aggregates for Wet Mix Macadam 250mm thick, including premixing the materials with water at OMC in mechnanical mix plant, conveyance of mixed materials by tipper to site, laying in uniform layers using pavers in Sub Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev-5 Specification no.111,112,406,900 |
| 6 | Road A |
| 7 | Road E |
| 8 | Prime coat Providing and laying Prime Coat over WBM/ WMM surface using 7 Kg of Emulsion Bitumen (SS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as perClause 502 of MORTH Rev-5 Specification no. 111, 112, 501,502,900- over WMM |
| 9 | Road A |
| 10 | Road E |
| 11 | Tack coat- Providing and laying Tack Coat over WBM/ WMM surface (treated with primer) using 2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as perClause 503 of MORTH Rev-5 Specification no.111,112,501, 503,900 |
| 12 | Road A |
| 13 | Road E |
| 14 | Tack coat- Providing and laying Tack Coat over Existing BT surface using 2 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as perClause 503 of MORTH Rev-5 Specification no.111,112,501, 503,900 |
| 15 | Road A |
| 16 | Road B |
| 17 | Road C |
| 18 | Road D |
| 19 | Road E |
| 20 | Providing and Laying 50mm thick Bituminous Macadam using course aggregate and VG30 bitumen which shall consist of construction in a single course base/binder course confirmingto the specfication on a previously prepared base, (using Mini Hot Mix Plant and PowerRoller) including cost of material, labour charges, rentals for machinery, fuel and all otherincidental charges etc., complete as per clause 504 MORTH Rev-5 (For Patch Works) |
| 21 | Road A |
| 22 | Road B |
| 23 | Road C |
| 24 | Advance B.T. Patches with bituminous premix chips upto 50mm thick using standard 45mm IRC size HBG metal cum of metal premix with 44Kgs of 80/100 grade bitumen per cum of metal in accordance with the requirement of the specifications to serve as base course and in conformity with the drawing or as directed by the Engineer. |
| 25 | Road D |
| 26 | Road E |
| 27 | Bituminous Macadam:Providing, laying 50mm consolidated thick Bituminous Macadam using 0.20cum of 26.50-13.20mm, 0.43cum of 13.20-2.36mm and 0.08cum of 2.36mm & below size IRC metal with 37Kgs of VG30 Grade bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen, aggregate and mixing them in required temperature using Central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory Roller to the required density etc., including labour for attending to paver to site etc., including hire and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including all other incidental charges etc., complete as per specification using CMP as per clause 504 of MORTH Rev-5 Specification no.111,112,501,503,900 - Grading II |
| 28 | Road A |
| 29 | Road B |
| 30 | Road C |
| 31 | Road D |
| 32 | Road E |
| 33 | Bituminous Concrete (Table500-17) Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00-9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 Specification no. 111, 112, 507, 900 complete in all respects - Grading II |
| 34 | Road A |
| 35 | Road B |
| 36 | Road C |
| 37 | Road D |
| 38 | Road E |
| 39 | Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, including compacting with power roller, watering, including all hire and fuel charges for all tools and plants, removal of other deleterious matter and obstructions, trimming of bottom of excavation back filling, clearing up the site and disposal of all surplus materials etc., complete as per standard specification. |
| 40 | Road A |
| 41 | Road B |
| 42 | Road C |
| 43 | Road D |
| 44 | Road E |
| 45 | Calculation of SubTotal, GST and Total Amount carried out by system automatically |
| 46 | Basic cost of value put to tender as per estimate |
| 47 | Add GST at 18% |
| 48 | Total Value put to Tender |
| 49 | Quoted Percentage |
| 50 | Quoted Value |
| 51 | Add GST at 18% of Final Quoted Value |
| 52 | Total Value of Contract Including 18% of GST |
| 53 | Basic cost of value put to tender as per Estimate |
| 54 | Quoted Rate in Figures (Total Value of Contract Including 18% of GST ) |
| 55 | Quoted Rate in Words |