Tender For Estimate For 2 Km 11 Kv Line Conductor Aug. Work Shahganj To Jawaharkheda Dlf Under Shahganj D/C Of (Oandm) Budni
Tender Overview
Project Description
Estimate For 2 Km 11 Kv Line Conductor Aug. Work Shahganj To Jawaharkheda Dlf Under Shahganj D/C Of (Oandm) Budni
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 16-Sep-2025 | Corrigendum for 1st date extend for 2 Km 11 KV line Conductor Aug. work Shahganj to Jawaharkheda DLF under Shahganj D/c of (OandM) Budni | Date | 23-Sep-2025 |
| 2 | 24-Sep-2025 | Corrigendum for 2nd date extend for 2 Km 11 KV line Conductor Aug. work Shahganj to Jawaharkheda DLF under Shahganj D/c of (OandM) Budni | Date | 30-Sep-2025 |
BOQ
| Sl. No. | Item Description |
| 1 | 140 Kg.,8.0 Mtrs. long PCC pole |
| 2 | AAAC Raccoon conductor 0.075 sq. inch (80 sq.mm. Al.Eq.) |
| 3 | M S Angle 65X65X6 mm |
| 4 | M S Channel 100X50x6 mm |
| 5 | M S Channel 75X40x6 mm |
| 6 | 11 KV Pin Insulator Polymer Composit (5 KN) |
| 7 | 11 KV(45KN) Composite Polymer Disc Insulators |
| 8 | 11 KV Strain hardware (T&C type) fittings |
| 9 | M.S.Flat 50x6 mm |
| 10 | Red oxide paint |
| 11 | Aluminium paint |
| 12 | Earthing Coil of 115 Turns of 50 MM.Dia and 2.5 Mtr. Lead of 4.0 MM G.I Wire |
| 13 | Back filling of poles with boulders. |
| 14 | G.I. WIRES 4.0 MM. (8 SWG) |
| 15 | Danger Boards Enamelled 11 KV |
| 16 | Aluminium Binding wire and tape |
| 17 | Jointing Sleeves suitable for Rabbit (55Sq.mm.Al. Eq. ) AAAC conductor |
| 18 | M.S.Nuts with Bolts |
| 19 | Anti climbing devices ( Barbed wire 2.24 mm dia, 14 SWG) |
| 20 | Stone Block/Pre cast block for base pedding(450X450X75MM) |
| 21 | Additional Erection Charge |
| 22 | Dismentelling |
| 23 | CONDUCTOR ACSR SCRAP( Return material Side To Area Store BHOPAL ) |
| 24 | Labour Charges & all Fabrication Charges (STC Sub Division will provide the raw material like M.S. angle, M.S. Channel, M.S. flat, etc. to the contractor and the contractor will fabricate the itemslike V-cross arm, Top clamp, D.C. Channel, clamp, etc. as per site condition. Those fabrication charges are included in the Labour charges.) no extra amount will be paid. |
| 25 | Transportation Charges for All Equipments & Materialsfrom area store to site & Site to Area store Bhopal |
| 26 | GST on Transportation @5% |
| 27 | GST on (Contractor side Material + Labour) @18% |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedCorrigendum-2 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender