| 1 | ST pole 11/9 Mtr. |
| 2 | PCC Pole 8.5 Mtr. |
| 3 | 11/0.4 KV 250KVA T/F. |
| 4 | LT Cable 1x240/630/ 400 sqmm |
| 5 | 11 KV XLPE Cable 3x120 sqmm. |
| 6 | 11 KV XLPE Cable 3x120/70 sqmm Termination Kit. |
| 7 | 11 KV Polymer Insulator. |
| 8 | 11 KV Disc Insulator. |
| 9 | 11 KV Disc Fitting. |
| 10 | 33 KV Breaker. |
| 11 | ABC Cable 3x120/95/50/25sqmm. |
| 12 | ACSR Weasel conductor. |
| 13 | G I wire. |
| 14 | Earthing rod |
| 15 | Safe Carriage of 9/11 Mtr ST pole/PCC Pole from Dump site to pit site. |
| 16 | Fabrication erection of substation type double pole on ST pole along with fixing of necessary clamp ,accessories required including supply and fixing of MS channel on top dropperwith arrangement of fixing of 3 Nos pin insulator as per respo specification ,making 11 KV Busbar by single core PVC .Only pole and pin with insu-lator clamp nut bolt provided by department |
| 17 | Erection of PCC Pole 8.5 Mtr. Long, single pole fabrication and fixing of accessories 11 KV/LT line, refilling of earth and proper ramming. Only PCC pole provide by the department. |
| 18 | Laying of LT Cable 1x240/400/630 sqmm with suitable size of Al lugall material provide by department. |
| 19 | Hoisting of LT Cable on pole clamping on pole only cable provided by department. |
| 20 | Proper Jumpering of LT Cable on O/H Line. |
| 21 | Prepare proper space for construction of plinth. |
| 22 | Construction of T/F plinth of size 2x2x1.2 Mtr with first class bricks and masonry work in the ratio 1:4 cement and course sand filing of structure completely as per norms with RCC Top 1:2:2 cement sand and course sand stone grit with MS bar and MS channel for resting of T/F. All material provide by contractor except T/F. |
| 23 | Fabrication and fixing of wiremesh fencing around the 11/0.4KV T/F and DP Box made as per requirement 2mtr height 45x45x5 mm angle frame and 1 No horizontal runner by 40x5 mm MS flat then welding of wiremesh on it 50x25mm made of 12 SWG,diagonal bracing of all the frame panel welded with MS flat 25x3mm support, grouting properly by cement concrete and course sand all material provided by contractor. |
| 24 | Painting of wire mesh fencing with 1 coat of red oxide and 2 coat of Green enamel paint |
| 25 | Fabrication and fixing of DP box stand made of MS Angle, grouting and plinthing of the same all material provided by contractor |
| 26 | Fabrication and fixing of Metalic Distribution Pillar boxon stand with Nut bolt made of 20 SWG BP Sheet with door 18 SWG BP Sheet ,with fixing of 2 Nos MS Angle for mounting of Fuse unitthen fixing of fuse unit500 Amp 650 Volt and 3 Nos copper Bus Bar and 1 No Al Busbarall material arrange by contractor. |
| 27 | Earthingof Pipe type with 60 feet deep boring and providing Jindal make pipe \"B\" class 1.25\" dia and GI strip 32x5 6mtr long attached with clamps and GI pipe. |
| 28 | Laying of 11 KV cable 3 x120 sqmm in pukka roadDouble circuit by digging of trench upto 1 Mtr Deep putting cable boxing with bricks and sand refilling of earth and proper ramming |
| 29 | Hoisting of cable will be passed through GI pipe required size duly clamped with pole at the bottom middle and top of the pole. |
| 30 | High pressure testing of 11KV Cable by high-pressure equipment. |
| 31 | Proper jumpering of cable both side with supply system. |
| 32 | Erection and commissioning of AB Conductor of size 3x120/95/50/25 sqmm. |
| 33 | Supply and fixing of clamps |
| 34 | Holding clamp. |
| 35 | Crimping Al Lugs 240/400/630 sqmm. |
| 36 | Copper L-Piece for T/F. |
| 37 | Copper Control Cable 4x2.5mm. |
| 38 | Nut bolts off size. |
| 39 | Danger board with clamp. |
| 40 | Sundry Item. |
| 41 | Pipe and cable holding clamp. |
| 42 | Grouting binding nozzelling of stay set complete including fixing of necessary clamps accessories. All Materialmaterial provided by contractor. |
| 43 | Ordinary Earthing by MS Earth rod2500 mm long by GI wire upto top channel all material provide by Department. |
| 44 | Fixing and installation of 11KV /33KV O/D type XLPE Jointing Kit, only jointing kit provide by department. |
| 45 | Providing fabrication and fixing of DO Fuse set |
| 46 | Providing Fabrication and fixing of 11KV TPMO Set A B Switch with GI pipe and handle |
| 47 | Groutingof pole by cement course sand and brick ballast Civil material provided by Contractor |
| 48 | Painting of ST pole by 2 coat of red oxide and 2 coat of Al paint Paint provided by contractor |
| 49 | Safe installation of 11/0.4 KV 250 KVA T/F its connection from 11KV line and LT Line Labour & T&P Provided by contractor. |
| 50 | Stringing and sagging of 11 KV Line on ACSR Conductor. |
| 51 | Construction of plinth of size 2x1.5x0.9 mtr suitable for upper structure for VCB including grouting of anchor bolts in proper alignment and level, including excavation of foundation base concreting in CC 1:6:12 cement, fine sand, brick ballast ,1st class brick work in cement mortar of ratio 1:4 ratio 1:4:8 and RCC work in ratio 1:2:4 cement, course sand and stone grit of 20 mm. |
| 52 | Installation of 33 KV VCB complete work with making earth connection, earth mat, earthing with GI strip 50x6mm including control wiring, commissioning & testing only VCB provided by department. |
| 53 | Dismantling of damaged 33 KV VCB. |
| 54 | Chemical type earthing3 Mtr long backfill compound bentonite its connect by GI Strip 32x5 mm with DP Box and Wiremesh Fencing All material provided by contractor. |
| 55 | GST will be paid extra as per rule. |