| 1 | Safe Loading, Carriage and unloading of following materials from Store Centre to Pit site/JE Dump Store. |
| 2 | Line Material |
| 3 | 11 KV 3x185 XLPE Cable |
| 4 | H/S I/D 11 KV 3x185 sqmm J/kit |
| 5 | H/S O/D 11 KV 3x185 sqmm J/kit |
| 6 | H/S S/TH 11 KV 3x185 sqmm J/kit |
| 7 | 11 KV VCBO/G CTR 200/100/5,350 MVA |
| 8 | Cable Route marker |
| 9 | 11M, ST Pole - SP - 55 Galvanised |
| 10 | M S Channel 100x50 mm 2400 mm Long |
| 11 | Polymeric 11 KV Pin Insulator |
| 12 | G I Pipe 150 mm Dia |
| 13 | ACSR Dog Conductor |
| 14 | Dragging of ST Pole digging of pit site , digging of pit errection ,fixing of necessary item such as Top Channel, along with grouting (As per RESPO Norms) Dropper Channel, 11 pin insulator with Pin ,as per RESPO Specification. (Only Pole and insulator will be Provided by the Department.) |
| 15 | Cable Hosting of 11 KV 3x185/ sq. mm XLPE Cable at the following including jumpering etc complete with help of GI Pipe as PerRESPO Norms. GI pipe and other required material shall be supplied by contractor. |
| 16 | Earthing of poles as per RESPO norms (All the Materials Supplied by the department) |
| 17 | Errection and testingof 11 KV VCBO/G CTR 200/100/5,350 MVA ,( Includes : Laying of cablein trench of substation, connecting it to a VCB with Indoor , connecting of VCB with exsisting Bus bar, Earthing of VCB , construction of plinth of VCB)(Only VCB , 3x183 sq mm cable ,H/S I/D 11 KV 3x185 sqmm J/kit will be provided by Department) |
| 18 | Laying of3x185 11 KV XLPE cable by drill method as per RESPO Norms. Only cable supplied by Department. |
| 19 | Laying of3x185 sq.mm 11 KV XLPE cable by manual method as per RESPO Norms. Only cable supplied by Department. |
| 20 | Supply and fixing of GI Pipe 6\" Dia with clamp and nut bolt as per RESPO Norms |
| 21 | Supply and fixing of Danger board with Clamp as per RESPO Norms |
| 22 | Supply and fixing of Number Plate with Clamp as per RESPO Norms |
| 23 | Fixing OUTDOOR / INDOOR END TERMINATION JOINTING KIT FOR 11 KV 3X185 SQMM XLPE CABLE |
| 24 | Fixing ST JOINTING KIT FOR11 KV 3X185 SQMM XLPE CABLE |
| 25 | G.S.T.Extra as per rules. |
| 26 | IMPORTANT INSTRUCTION / NOTICE -On completion of the work, close view updated photographs of the said work along with GEO Tag must be made available. |