| 1 | Centralised Materials- A |
| 2 | PCC Pole 8.5mtr. long |
| 3 | ACSR weasel conductor for Jumpering & Tapping of 11KV Line |
| 4 | LT XLPE Cable 3.5x70 sqmm |
| 5 | 11KV XLPE Cable 3x70 sqmm |
| 6 | LT XLPE Cable 1x630 sqmm |
| 7 | 11 KV XLPE Cable 3x300 sqmm |
| 8 | 11 KV XLPE Cable 3x185 sqmm |
| 9 | 11 KV Pin Insulator polymeric |
| 10 | 11 KV Disc Insulator polymeric |
| 11 | 11 KV Disc Fitting |
| 12 | 11KV Stay Set (16x1800mm) (Stay Set Complet) |
| 13 | Earthing of Pole by MS Earthing Road of 20x2500mm (Complet Earthing) |
| 14 | Top Channel (100x50x2240mm) |
| 15 | 11KV MS Dropper Angle for Fuse System |
| 16 | 11 KV Cable Box O/D 3x185 sqmm |
| 17 | 11 KV Cable Box I/D 3x185 sqmm |
| 18 | 11 KV Cable Box O/D 3x70 sqmm |
| 19 | 11 KV Cable Box I/D 3x70 sqmm |
| 20 | 11 KV Cable Box O/D 3x300 sqmm |
| 21 | 11 KV Cable Box I/D 3x300 sqmm |
| 22 | 11 KVV-Type Cross Arm |
| 23 | 11KV VCB O/G 200/100/5A |
| 24 | Substation Base Angle |
| 25 | 63KVA Transformer |
| 26 | Decentralized Materials- B (Including GST) |
| 27 | Aluminium Lug 70sqmm |
| 28 | Aluminium Lug 185sqmm |
| 29 | LT Crimping Aluminium Lug 400/630 sqmm |
| 30 | Nuts & Bolts of Various Size |
| 31 | F- Clamp |
| 32 | Stone Pad |
| 33 | Clamp for T-OFF |
| 34 | Singal Core Cable 1x185sqmm |
| 35 | Holding Clamp for Double Pole S/S |
| 36 | Labour & Maintainance charges - C (Including GST) |
| 37 | Work of Carriage of8.5 Mtr. PCC pole from store centre Sahupuri/Rajatalab to site with loading & unloading. |
| 38 | Work of Erection of 8.5 Mtr. PCC Doble pole with digging & Fitting of fixtures as per RESSPO standard. |
| 39 | Work of Carriage of11KV XLPE Cable 3x70 / 3x185 / 3x300 sqmm from store centre Sahupuri/Rajatalab to site as per RESSPO standard. |
| 40 | Work of Carriage ofLT XLPE Cable 3.5x70 / 1X630 sqmm from store centre Sahupuri/Rajatalab to site as per RESSPO standard. |
| 41 | Work of Cable Laying of 11KV XLPE 3x70sqmm Cable After digging & Making of Cable Trench Method Including Loop as per RESSPO standared. |
| 42 | Work of Cable Laying of 11KV XLPE 3x185sqmm Cable After digging & Making of Cable Trench Method Including Loop as per RESSPO standared. |
| 43 | Work of Cable Laying of 11KV XLPE 3x300sqmm Cable After digging & Making of Cable Trench Method Including Loop as per RESSPO standared. |
| 44 | Work of Cable Laying & Commissioning ofLT XLPE 3.5x70sqmm Cable with all requard material (Lug. Crimping Lug etc.) as per RESSPO standared. |
| 45 | Work of Cable Laying & Commissioning ofLT XLPE 1x630 / 1x185 sqmm Cablewith all requard material (Lug. Crimping Lug etc.) as per RESSPO standared. |
| 46 | Work of Carriage & Erection of 11KV Cable Jointing Kit 3x70 / 3x185 / 3x300 sqmm Indoor / Outdoor from store centre Sahupuri/Rajatalab to site as per RESSPO standard. |
| 47 | Work of Carriage & Erection of ACSR Weasel Conductor with All Accessories (Clamp, PG Clamp, MS Angle Clamp, Droper Angle for Fuse set etc.) including loading & unloading from store centre Sahupuri/Rajatalab to work site. |
| 48 | Work of Carriage & Erection of11KV Pin Insulator including loading & unloading from store centre Sahupuri/Rajatalab to work site. |
| 49 | Work of Carriage & Erection of11KV V-Type X-Arm including loading & unloading from store centre Sahupuri/Rajatalab to work site. |
| 50 | Work of Carriage & Erection of11KV Disc Insulator including loading & unloading from store centre Sahupuri/Rajatalab to work site. |
| 51 | Work of Carriage & Erection of11KV stay set comlete including loading & unloading from store centre Sahupuri/Rajatalab to work site. |
| 52 | Work of Carriage & Erection ofEarthing comlete including loading & unloading from store centre Sahupuri/Rajatalab to work site. |
| 53 | Work of Carriage & Mounting of63KVA Transformer and Energizing including loading & unloading from store centre Sahupuri/Rajatalab to work site. |
| 54 | Work of Carriage of11KV VCB Outgoing from store centre Sahupuri/Rajatalab to site with loading & unloading. |
| 55 | Work of Commissioning 11KV VCB Outgoing. |
| 56 | Work of Chemical pipe earthing of Distribution transformer 30feet deep for Neutral by using B-Class, G.I. Pipe of 1.5\" Dia with the help of GI Strip 30x5 mm duly galvanized shall be used. All required materials shall be supplied by the contractor. |
| 57 | Construction of Wire mesh Fencing with 1 door for DTR including Grounting of foot & Proper Fixing as per RESSPO Norms. (Size 8\"x7\"x6\") of DTR with Supply of Materials. |
| 58 | Work of construction of plinth of T/F (2X2X1.5M)including cement, Sand, Concrete in the ratio of 1:4:8 as per RESSPO standard. |
| 59 | Work of Pole / Stay Grouting (Cement, Sand, Concrete in the ratio of 1:4:8.)as per RESSPO standard |