| 1 | Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc. (the tail pieces if required will be paid separately): 350 mm i/d |
| 2 | Providing and fixing of 15 mm nominal diameter water meter as per IS 779:1994 Inferential type dry dial, mechanical driven, non megnatic drive, straight reading cyclometer type, 7-inline consequent digits with one centre point for easy reading complete in all respect. |
| 3 | `Cloud based software comprising of Middleware, Database and Front-end web interface through suitable Dashboards, Aggregation screens and GIS assisted drill-down from macro to micro to be provided. Application data hosting and maintenance for Five years included in scope. Cloud servicesof Ministry of Electronics and InformationTechnology (Meity), Government of India empaneled cloud service providers shall be taken like Microsoft, Amazon, Google, BSNL etc. Cloud service provider must adhere the security standards and guidelines issued by Meity from time-to-time.As the data belongs to the State Government of Haryana, therefore the application and data hosted on Cloud must be kept and stored in data centres located in India only. Any change in application requirement or infrastructure shall be borne by the Implementation agency.Implementation agency shall carry out the Application Security Audit from a Certified Auditor (CA). Application anddata shall be kept confidential and only the authorized users shall have the access to it.Implementation Agency shall be responsible for any data theft or data leakages. |
| 4 | SIM Card: SIM Cards for five year maintenance of all the instrument above as required. (For B/Stn. ) |
| 5 | `Radar and Water Level Transmitter: Supply, Installation, testing, Commissioning with five year maintenance of Radar and Water Level Transmitter alongwith according to water level in OHSR (for OHSR) Ingress Protection – IP 66, Measuring range – Up to 20 M, Process temp.- -40 to 60 deg. C, Full PVDF Body – For a long sensor lifetime. **Unit Rate given, actual quantity to be ascertained while placing order. (For B/Stn.)` |
| 6 | `RTU: Functional Integration at RTU-cum-Gateway for Motorized Control Valve in Pump Control Panel(For B/Stn.)` |
| 7 | `Automation Panel: `Automation Panel for integration with VFD with Pump Control Panel, along with Auto/Manual Selection Switch as well as On/Off push button to be provided. Manual selection between pump 1 and pump 2 depending on which to be operated and which to be stand by to be provided, along with all relay interlocks and provision of operation of pumps through potential free/open collector digital outputs of RTU-cum-Gateway device. The panel will contain RTU-cum-Gateway with necessary I/Os and edge controller Motorized control valve in Local / Remote or Auto/ Manual modes of operation in tandem with Cloud Scheduler or Level sensor-based functions.Panel will contain SMPS with rechargeable battery backup (min. 24 hrs.) along with facility to connect all field instruments with 24 VDC power supply. `(For B/Stn.)` |
| 8 | `Online Chlorine Sensor : Supply, Installation, Testing, Commissioning with five year maintenanceof Online Chlorine Sensor. (For B/Stn.)` |
| 9 | `Electromagnetic Flowmeter: Supply, Installation, testing, Commissioning five year maintenance, Electromagnetic Flowmeter along with its installation complete in all respect as per specifications.Size as per site requirement.(IP-68), RS-485 ModBus. Line size 150 mm, installed at pump End / Source. (For B/Stn.: InletplusOutlet) |
| 10 | `Butterfly Valve: Supply, Installation, testing, Commissioning with five year maintenanceof Butterfly Valve with Electrical Actuator Body Material - CI/DIPressure Rating – PN16 Feedback - 100% Open and 100% close. **Unit Rate given, actual quantity to be ascertained while placing order 150 mm (For B/Stn.)` |
| 11 | `CLEAR WATER PUMP: Supplying, erection, testing and commissioning of Horizontal motor pumping set forClear water having head as per the indicated requirements of discharge in LPM and power capacity in BHP as per IS marked ` 5800 LPM x 45.00 M (For 1st W/W) |
| 12 | NS Item -(6.00 MLD) Design and construction of automated PLC controlled water treatment plant including interconnecting DI pipe from raw water pump to inlet box of WTP, CWT, and Suction Well for CW, inlet channel, Alum dozing, Flash mixing, Clari floculator, filter box, overhead Reservoir for back wash including pump sets and electric control panel, waste water tank including pump sets and electric control panel, DI pipes, DI specials, manhole covers, air scour equipment, chemical house and all other civil/mechanical/electric installations complete in all respects as per DNIT (Sluice valves ) 6.00 MLD CAPACITY excluding OandM during Defect liability period of 12 months after trial run period of 3 months and 5 years thereafter. @@@ |
| 13 | NS Item -(4.50 MLD) Design and construction of automated PLC controlled water treatment plant including interconnecting DI pipe from raw water pump to inlet box of WTP, CWT, and Suction Well for CW, inlet channel, Alum dozing, Flash mixing, Clari floculator, filter box, overhead Reservoir for back wash including pump sets and electric control panel, waste water tank including pump sets and electric control panel, DI pipes, DI specials, manhole covers, air scour equipment, chemical house and all other civil/mechanical/electric installations complete in all respects as per DNIT (Sluice valves ) 4.50 MLD CAPACITY excluding OandM during Defect liability period of 12 months after trial run period of 3 months and 5 years thereafter. @@@ |
| 14 | Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc. (the tail pieces if required will be paid separately) 400 mm diameter class 1 |
| 15 | Design, Supply, installation and testing of VFD along with distribution panel in enclosure for motor rating of 4700 LPM 15 Mtr. Head (30 HP). Enclosure shall be IP54. The panel shall be equipped with MCCB TP with suitable rating, Spreader link TP, Extended rotary handle, Volt meter digital, Volt selector switch, Amp meter, Amp selector switch, C.T with suitable rating, Control MCB SP with suitable rating, PLA Relay, Pushbutton red plus green with element, Indicator ON/Off, Aluminium Bus bar/suitable rating power and Control wiring labour and margin, Fabrication with minimum Sheet thickness of 2 mm for load bearing and non-load bearing side. VFD should be capable of protecting motor from high and low voltage and earth fault as well. VFD should restrict harmonics up to 35% VFD should be capable of providing starting torque up to 200% while starting motor. It should have class 3C3 (Avg)conformal coating so that components are safe from dust and moisture. Communication -Built-in RS485 Modbus RTU, Ambient Temperature -Heavy Duty: -10 ~ 50 deg C Normal Duty: -10 ~ 40 deg C, PCB Protection Conformal Coating complying to IEC 60721-3-3 class 3C3, Application Humidity Below relative humidity 95% RH (no condensation) Altitude 0 to 1,000 m Without deration 1,001 to 4,000 m With deration of 1% per rise in 100 m, Vibration Up to 9.8 m/sec2 (1.0 G), Global Compliance CE, UL, RoHS, Control Method V/F Control, Sensorless Vector Control, Slip Compensation, Closed Loop Vector Control. Starting Torque 200% at 0.5Hz in Sensorless Vector Control and 150% at 3Hz in V/F, Frequency Control Range 0 to 400Hz in V/F, 0 to 300Hz in Sensorless 1, 0 to 120Hz in Sensorless 2 / Vector, Frequency Precision Setting- Digital: 0.01Hz, Analog: 0.03Hz (60Hz Base). complete with all other accessories as required. (For R/W Machinery at 1st W/W) |
| 16 | Design, Supply, installation and testing of VFD along with distribution panel in enclosure for motor rating of 5800 LPM 45 Mtr. Head (100 HP). Enclosure shall be IP54. The panel shall be equipped with MCCB TP with suitable rating, Spreader link TP, Extended rotary handle, Volt meter digital, Volt selector switch, Amp meter, Amp selector switch, C.T with suitable rating, Control MCB SP with suitable rating, PLA Relay, Pushbutton red plus green with element, Indicator ON/Off, Aluminium Bus bar/suitable rating power and Control wiring labour and margin, Fabrication with minimum Sheet thickness of 2 mm for load bearing and non-load bearing side. VFD should be capable of protecting motor from high and low voltage and earth fault as well. VFD should restrict harmonics up to 35% VFD should be capable of providing starting torque up to 200% while starting motor. It should have class 3C3 (Avg)conformal coating so that components are safe from dust and moisture. Communication -Built-in RS485 Modbus RTU, Ambient Temperature -Heavy Duty: -10 ~ 50 deg C Normal Duty: -10 ~ 40 deg C, PCB Protection Conformal Coating complying to IEC 60721-3-3 class 3C3, Application Humidity Below relative humidity 95% RH (no condensation) Altitude 0 to 1,000 m Without deration 1,001 to 4,000 m With deration of 1% per rise in 100 m, Vibration Up to 9.8 m/sec2 (1.0 G), Global Compliance CE, UL, RoHS, Control Method V/F Control, Sensorless Vector Control, Slip Compensation, Closed Loop Vector Control. Starting Torque 200% at 0.5Hz in Sensorless Vector Control and 150% at 3Hz in V/F, Frequency Control Range 0 to 400Hz in V/F, 0 to 300Hz in Sensorless 1, 0 to 120Hz in Sensorless 2 / Vector, Frequency Precision Setting- Digital: 0.01Hz, Analog: 0.03Hz (60Hz Base). complete with all other accessories as required. (For C/W Machinery at 1st W/W) |
| 17 | RAW WATER PUMP: Supplying, erection, testing and commissioning of Horizontal motor pumping set for Raw water having head as per the indicated requirements of discharge in LPM and power capacity in BHP as per IS marked ` 4700 LPM x 15 M (For 1st W/W) |
| 18 | Design, Supply, installation and testing of VFD along with distribution panel in enclosure for motor rating of 3250 LPM 15 Mtr Head 20 HP. Enclosure shall be IP54. The panel shall be equipped with MCCB TP with suitable rating, Spreader link TP, Extended rotary handle, Volt meter digital, Volt selector switch, Amp meter, Amp selector switch, C.T with suitable rating, Control MCB SP with suitable rating, PLA Relay, Pushbutton red plus green with element, Indicator ON/Off, Aluminium Bus bar/suitable rating power and Control wiring labour and margin, Fabrication with minimum Sheet thickness of 2 mm for load bearing and non-load bearing side. VFD should be capable of protecting motor from high and low voltage and earth fault as well. VFD should res`trict harmonics up to 35% VFD should be capable of providing starting torque up to 200% while starting motor. It should have class 3C3 (Avg)conformal coating so that components are safe from dust and moisture. Communication -Built-in RS485 Modbus RTU, Ambient Temperature -Heavy Duty: -10 ~ 50 deg C Normal Duty: -10 ~ 40 deg C, PCB Protection Conformal Coating complying to IEC 60721-3-3 class 3C3, Application Humidity Below relative humidity 95% RH (no condensation) Altitude 0 to 1,000 m Without deration 1,001 to 4,000 m With deration of 1% per rise in 100 m, Vibration Up to 9.8 m/sec2 (1.0 G), Global Compliance CE, UL, RoHS, Control Method V/F Control, Sensorless Vector Control, Slip Compensation, Closed Loop Vector Control. Starting Torque 200% at 0.5Hz in Sensorless Vector Control and 150% at 3Hz in V/F, Frequency Control Range 0 to 400Hz in V/F, 0 to 300Hz in Sensorless 1, 0 to 120Hz in Sensorless 2 / Vector, Frequency Precision Setting- Digital: 0.01Hz, Analog: 0.03Hz (60Hz Base). complete with all other accessories as required. (For R/W Machinery at 2nd W/W) |
| 19 | RAW WATER PUMP: Supplying, erection, testing and commissioning of Horizontal motor pumping set for Raw water having head as per the indicated requirements of discharge in LPM and power capacity in BHP as per IS marked ` 3250 LPM x 15 M (For 2nd W/W) |
| 20 | Design, Supply, installation and testing of VFD along with distribution panel in enclosure for motor rating of 4025 LPM 60 mtr. Head 90 HP. Enclosure shall be IP54. The panel shall be equipped with MCCB TP with suitable rating, Spreader link TP, Extended rotary handle, Volt meter digital, Volt selector switch, Amp meter, Amp selector switch, C.T with suitable rating, Control MCB SP with suitable rating, PLA Relay, Pushbutton red plus green with element, Indicator ON/Off, Aluminium Bus bar/suitable rating power and Control wiring labour and margin, Fabrication with minimum Sheet thickness of 2 mm for load bearing and non-load bearing side. VFD should be capable of protecting motor from high and low voltage and earth fault as well. VFD should res`trict harmonics up to 35% VFD should be capable of providing starting torque up to 200% while starting motor. It should have class 3C3 (Avg)conformal coating so that components are safe from dust and moisture. Communication -Built-in RS485 Modbus RTU, Ambient Temperature -Heavy Duty: -10 ~ 50 deg C Normal Duty: -10 ~ 40 deg C, PCB Protection Conformal Coating complying to IEC 60721-3-3 class 3C3, Application Humidity Below relative humidity 95% RH (no condensation) Altitude 0 to 1,000 m Without deration 1,001 to 4,000 m With deration of 1% per rise in 100 m, Vibration Up to 9.8 m/sec2 (1.0 G), Global Compliance CE, UL, RoHS, Control Method V/F Control, Sensorless Vector Control, Slip Compensation, Closed Loop Vector Control. Starting Torque 200% at 0.5Hz in Sensorless Vector Control and 150% at 3Hz in V/F, Frequency Control Range 0 to 400Hz in V/F, 0 to 300Hz in Sensorless 1, 0 to 120Hz in Sensorless 2 / Vector, Frequency Precision Setting- Digital: 0.01Hz, Analog: 0.03Hz (60Hz Base). complete with all other accessories as required. (For C/W Machinery at 2nd W/W) |
| 21 | CLEAR WATER PUMP: Supplying, erection, testing and commissioning of Horizontal motor pumping set forClear water having head as per the indicated requirements of discharge in LPM and power capacity in BHP as per IS marked `4025 LPM x 60.00 M (For 2nd W/W) |
| 22 | Electromagnetic Flowmeter: Supply, Installation, testing, Commissioning five year maintenance, Electromagnetic Flowmeter along with its installation complete in all respect as per specifications. Size as per site requirement.(IP-68), RS-485 ModBus. Line size 400 mm, installed at pump End / Source. (For Raw Water Pumping Station) ` |
| 23 | Operation and maintenance of complete scope of the DNIT i.e 6.00 MLD WTP at 1st W/W and 4.50 MLD WTP 2nd W/W including SCADA system, all raw water and clear water pumping machinery at Pumping Station and Water Works, rising mains various sizes, (pipe line) at head works and all mechanical works, electrical works , civil structures gas chlorination systemand IOT based monitoring automation etc. complete in all respect and all other works contingent thereto. for 12 months during defect liability period after trial run period of 3 months and 5 years thereafter and all other works contingent thereto. |