| 1 | Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, removal of other deleterious matter and obstructions, trimming of bottom of excavation back filling, clearing up the site and disposal of all surplus materials etc., complete as per standard specification ForBox cutting for widening portion. (MORTH No. 111, 112, 301, 305, 900) |
| 2 | Road A |
| 3 | Granular Sub Base - Providing, laying, spreading and compacting graded stone aggregates for Granular Sub Base, including premixing the materials with water at OMC in mechnanical mix plant, conveyance of mixed materials by tipper to site, laying in uniform layers using pavers in Sub Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev-5 for Grade - VMaterial (MORTH No. 111, 112, 401, 900) |
| 4 | Road A |
| 5 | Wet Mix Macadam -Providing, laying, spreading and compacting graded stone aggregates for Wet Mix Macadam 250mm thick, including premixing the materials with water at OMC in mechnanical mix plant, conveyance of mixed materials by tipper to site, laying in uniform layers using pavers in Sub Base/ Base course on well prepared surface and compacting with vibratory rollerto acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev-5 (MORTH No. 111,112, 406, 900) |
| 6 | Road A |
| 7 | PrimeCoatOverWBM/WMMsurface - ProvidingandlayingPrimeCoatOverWBM/WMMsurfaceusing7KgofEmulsion Bitumen(SS1)per10sqmforpreparatorytoanotherbituminousconstructionoverit, includingcostofmaterial,labourcharges,rentalsformachinery,fuelandallother incidental charges etc., complete as perClause 502 of MORTH Rev-5 (MORTH No. 111 ,112, 501, 502, 900) |
| 8 | Road A |
| 9 | Tack Coat Over Primed Surface - ProvidingandlayingTackCoatoverWBM/WMMsurface(treatedwithprimer) using2.50KgofBitumenEmulsion(RS1)per10sqmforpreparatorytoanother bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete asper Clause 503 of MORTH Rev (MORTH No. 111,112,501, 503,900) |
| 10 | Road A |
| 11 | Tack Coat Over Existing BT Surface - ProvidingandlayingTackCoatOverExistingBTsurfaceusing2KgofBitumen Emulsion(RS1)per10sqmforpreparatorytoanotherbituminousconstruction overitincludingcostofmaterial,labourcharges,rentalsformachinery,fueland all other incidental charges etc., complete as perClause 503 of MORTH Rev-5e asper Clause 503 of MORTH Rev (MORTH No. 111,112,501, 503,900) |
| 12 | Road A |
| 13 | BM 50mm Thick Using Mini Hot Mix Plant - ProvidingandLaying50mmthickBituminousMacadamusingcourseaggregateandVG30 bitumenwhichshallconsistofconstructioninasinglecoursebase/bindercourse confirmingtothespecficationonapreviouslypreparedbase,(usingMiniHotMixPlantand PowerRoller)includingcostofmaterial,labourcharges,rentalsformachinery,fuelandall otherincidentalchargesetc.,completeasperclause 504MORTHRev-5(ForPatchWorks) (MORTH No. 111, 112, 504, 900) |
| 14 | Road A |
| 15 | DBM (Grade-I) 75mm Thick Using VG30 Bitumen - Providing, laying 75mmconsolidatedthick DenseBituminousMacadam using 0.40cum of 37.50-13.20mm, 0.35cum of 13.20-2.36mm and 0.36cum of 2.36mm & below size IRC metal with 71.30kgs of VG30 grade bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen, aggregate and mixing them in the required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to site, spreading the mix to uniform thickness of 75mm with mechanical paver to the specified gradesandcrosssectionsandconsolidatedbyVibratoryRollertotherequireddensityetc., including labour for attending to paver to site etc., including hire and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including all other incidental charges etc., complete as per specification using CMP as per clause 505 of MORTH rev-5 for Grade - I (MORTH No. 111, 112, 505, 900) |
| 16 | Road A |
| 17 | BC 30/40mm Thick (Grade-II) Using VG30 Bitumen -ProvidingandlayingBituminousConcreteto30/40mmthickusing0.13cumof19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heatingthebitumenandaggregatetorequiredtemperatureandmixingtheminrequired temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paversite,spreadingthemixtouniformthicknessof40mmwithmechanicalpavertothe specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler,tipper trucks, Paver Finisher, Vibratory roller andallothertoolsandplantrequired,includingfuelandallotherincidentalchargesetc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 - Grade - II. (MORTH No. 111, 112, 501, 507, 900) |
| 18 | Road A |
| 19 | COMPACTION ONLY FOR UTILIZING AVAILABLE BOX CUT EARTH- Providing compaction for embankment / making up of low berms using the available box cut earth including allhire andfuelchargesforpowerrollerforcompaction, water sprinkler, including all labour charges for laying, spreading, watering etc., complete and as directed by the departmental engineers. (MORTH No. 111, 112, 301, 305, 900) |
| 20 | Road A |
| 21 | Picking the existing bituminous road surface to a depth of 75 mm and disposing of scarified materials with a lift upto 3 m and lead upto 1 km as per specification and as per directions of Departmental officers (Morth No. 111, 112, 202) |
| 22 | Road A - Providing Kerb type Center Median and Paver Block at Km 19/2 of Sivagiri -Vadapalani road |
| 23 | Barrier Type Kerb - Providing Barrier Type Kerb for median/ islands using vibrated cement concrete ofgrade M20(1:1.5:3)using 20and12mmISSHBG metalfrom approvedquarry,includingcostandconveyanceofallmaterialstoworksite, includinghireandfuelchargesofallthemachineriesemployedforthiswork, includingalllabourchargesformixing,laying,curing,painting,includingall otherincidentalchargesetc.,completeasperdrawingandstandard specification. (Morth No. 111, 112, 408, 1000, 1700, 2200, 900) |
| 24 | Road A - Providing Kerb type Center Median and Paver Block at Km 19/2 of Sivagiri -Vadapalani road |
| 25 | Filling in between gap for median and island and above road level with approved materials deposited at site from roadway cutting and excavation for drain and foundation of otherstructures,spread,greaded and compacted as per CL:407 of MORTH ( Using Box cut earth)- Spreading charges only(Morth No. 111, 112, 304, 900) |
| 26 | Road A - Providing Kerb type Center Median and Paver Block at Km 19/2 of Sivagiri -Vadapalani road |
| 27 | SupplyingandlayingofTAMINPaverBlockofsize60mmthick(Supplyatsite)overa base of crushed stone filling including cost and conveyance of all materials to worksite,includingalllabourchargesforlaying,compactingincludinghireandfuel charges for all tools and plants employed for this work and all other incidental charges etc., complete as per standard specification.(MORTH No. 111, 112, 304, 900) |
| 28 | Road A- Providing Kerb type Center Median and Paver Block at Km 19/2 of Sivagiri -Vadapalani road |
| 29 | Calculation of SubTotal, GST and Total Amount carried out by system automatically |
| 30 | Basic cost of value put to tender as per estimate |
| 31 | Add GST at 18% |
| 32 | Total Value put to Tender |
| 33 | Differnce Amount (Excess/Less) |
| 34 | Quoted Amount (Basic Rate Only) |
| 35 | Add GST at 18% of of Quoted Amount |
| 36 | Total Value of Quoted Amount Including 18% of GST |
| 37 | Basic cost of value put to tender as per Estimate |
| 38 | Quoted Rate in Figures (Total Value of Contract Including 18% of GST ) |