| 1 | Route surveying andpeg marking of HT/LTlines |
| 2 | Loading and un loading of of 9.14 Mtr poles / 9 Mtr PSC |
| 3 | Loading and un loading of of 8.0m pole psc |
| 4 | Transport of conductor from road side to workspot upto 1KM stringing and sagging up to 7/2.50mm & 7/2.59mm including PVC Cable up to 25Sqmm of conductor including binding of pin and proper tightening |
| 5 | Transport of conductor from road side to workspot upto 1KM stringing and sagging up to 7/3.15 mm & 7/3.35 mm including PVC Cable up to 25Sqmm of conductor including binding of pin and proper tightening |
| 6 | Transport of conductor from road side to workspot upto 1KM stringing and sagging up to 7/4.09 mm ACSR including PVC Cable up to 25Sqmm of conductor including binding of pin and proper tightening |
| 7 | Transport of 9.0 Mtr PSC, 9.14 Mtr & and abovepoles including R.S Joist and Rail polesup to 8 KM |
| 8 | Transport of 8.0 Mtr PSC, and abovepoles including R.S Joist and Rail polesup to 8 KM |
| 9 | Excavation of pits in ordinary soil 9.14 Mtr Poles /9.0 Mtr PSC Poles/ All Metal poles(1.25x06x1.83M) |
| 10 | Excavation of pits in ordinary soil8.0mtr PSC Poles/ All Metal poles(1.25x06x1.83M) |
| 11 | Excavation of pits in ordinary soil forStay pit |
| 12 | Erection works( including refilling of excavation sand) 9.14 Mtr Poles |
| 13 | Erection works( including refilling of excavation sand) 8.0 Mtr Poles |
| 14 | Erection of stay set complete ( including refilling of excavation of sand) |
| 15 | Fixingof LT Sph \"X\" Arm/HT TI Fitting/ LT TI Fitting |
| 16 | Fixing of LT 3ph\"X\" Arm |
| 17 | Fixing of 4\" - 6\" \"V\"\"X\" Arm |
| 18 | Fixing of tapping channel / Guarding \"X\" Arm |
| 19 | Fixing of 22 KV/33KV Pin Insulator/ PT insulator |
| 20 | Fixing of 22 KV Disc |
| 21 | Fixing of LT Shackle |
| 22 | Fixing of LT Pin insulator |
| 23 | Fixing of Aluminium Knob |
| 24 | Earthing of Poleincluding buring ,looping and binding |
| 25 | Mass concerting for pole 0.6Mx0.45Mx1.25M ( Cement ,Jelly,sand supplied by contractor) |
| 26 | Resagging of Cut Point Location |
| 27 | Flat guarding |
| 28 | Dismantling of 7.5m/8.0m Poles |
| 29 | Dismantling of9.14 Mtr. Poles |
| 30 | Dismantling of Stay set complete |
| 31 | Dismantling of conductors upto 7/2.59 MM and Coiling and Transporting from workspot to road side |
| 32 | Dismantling of conductors 7/3.35 MM and above and Coiling and Transporting from workspot to road side |
| 33 | Releasing of LT S ph \"X\" Arm/TI Fitting |
| 34 | Relaasing of LT 3 ph \"X\" Arm |
| 35 | Releasing of 4\" - 6\" V\" Cross Arm/Tapping channal |
| 36 | Dismantling of Transformer Structure materials |
| 37 | Dismantling of AB Switch at D.T.Structure |
| 38 | Dismantling of H.G. fuse set |
| 39 | Dismantling of Earth Pipe and Structure earthing complete |
| 40 | Dismantling of 2 Nos. Open type fuse unit set with all wiring complete(including bus bar arrangement) |
| 41 | Dismantling of Distribution Transformer |
| 42 | TransportingofLine Materials from Stores toworkspot |
| 43 | Loading and Un loading of Line Materials from Stores to worksite |
| 44 | loading /un Loading of D,Ts at field and stores without Crane |
| 45 | Erection of Top Channel, Bed Channel and Belding angle with all Structure Clamps |
| 46 | Erection of AB Switch with PT Insulators |
| 47 | Erection of HG Fuse Set |
| 48 | Erection of Distribution Transformer |
| 49 | Providing Jumbering of Structure |
| 50 | Erection of Cross Brassing Set complete |
| 51 | Transformer wiring in LT Side including Jumbering Bus Baretc. |
| 52 | Erection of LT Open tyoe fuse unit arrangement Single/Double (Including Jumbering) |
| 53 | Transformer Structure Poles Mass Concreting with coping 0.65x0.6Mx1.85M+0.65Mx0.6x0.35 coping |
| 54 | Painting of Structure complete excluding Distri.Tr.(one coat of Red Oxide) with painting materials (2kg x 150) |
| 55 | Painting of Structure complete excluding Distri.Tr.(one coat of Aluminium paint)with painting materials (1.5 Ltr x 350) |
| 56 | Colour washing of 2 Nos. Structure Poles excluding cost of Distember/Snowsem) with painting materials (2 kg x 60) |
| 57 | Paing of Transformer name Plate details including cost of the sheet (1.5 X 1) and paint |
| 58 | Painting name of SS at seating Channel including paint |
| 59 | Erection of Single pole Transformer Bed |
| 60 | Erection of Single pole A.B. Switch (G.OS) |
| 61 | Erection of Single pole H.G.Fuse set |
| 62 | Painting of all clamp , other materials and painting of Strucure pole( Excluding Paint) |
| 63 | LT cable arrangement |
| 64 | Provision of Distribution Transformer Name Board (Name of the 22/11 kv feeder, Name of the SS, Capacitty , Danger Board ) |
| 65 | Fabrication of centre support and erection of centre support including pits |
| 66 | Mass concreting for centre support for 2 feet including all materials |
| 67 | Fixing of Danger Board (Excluding Paint) |
| 68 | Erection of Plinth for (22 KV) Single pole Structure |
| 69 | Erection of Earth pipes and Structure earthing(complete) |
| 70 | Mass concreating PCC including cost of Jally,MSAND& cement,Lead ,Lift etc. with a mixture of 1:3:6 for 9m Square pole with copping for single pole |
| 71 | Providing Holes of all size Flat/Angles/Channels |
| 72 | Welding |
| 73 | Manufacturing of clamps & Altering of clamps |
| 74 | Transporting of Distribution Transformer by using private vehicle ( all capacities up to 30KM) |
| 75 | GST |