Emergent Patch Repair Of Potholes Of Left Side Inspection Path In-Between Ch. 906.00 & Ch. 997.53 Of K.B.C. Under Kotulpur (East) Section Of K.C. Sub-Division No.- X,Under K.C. Division No.-Iii , Bishnupur, During The Year 2025-26., Kotulpur-West Bengal
TDR : 50410385
Tender Notice
BOQ
Expired
Kotulpur
West Bengal
Emergent Patch Repair Of Potholes Of Left Side Inspection Path In-Between Ch. 906.00 & Ch. 997.53 Of K.B.C. Under Kotulpur (East) Section Of K.C. Sub-Division No.- X,Under K.C. Division No.-Iii , Bishnupur, During The Year 2025-26.
Name of Work: \"Emergent patch repair of potholes of left side inspection path In-between Ch. 906.00 & Ch. 997.53 of K.B.C. under Kotulpur (East) Section of K.C. Sub-Division No.- X,under K.C. Division no.-III , Bishnupur, during the year 2025-26.\"
Sl. No.
Item Description
1
Cutting and clearing jungles including shrubs, water weeds, bushes, trees, plants, upto 30 cm. girth including removing as directed by Engineer-in-charge.
2
Water Bound Macadam Sub BaseWater Bound Macadam Sub Base by consolidating Jhama metal / Laterite chelly or stone metal / shingles of specific size in hard crust to requisite thickness (measured after compaction) in layers including screening of metals etc. as necessary, hand packing, sweeping, watering and rolling in stages with power roller to proper line, grade and camber, lighting, guarding & barricading and making necessary earthen bundh of one metre width on each side where necessary to protect edges and preparing the bed by necessary cutting or filling and rolling all complete including the cost of all materials and hire and labour charges of all men and machineries and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5 th Revision). (ii) For Construction of Sub Base by consolidating Laterite (90 mm to 45 mm):Note: Add cost at site of 1.45 m³ of materials to arrive at the complete rate.
3
Supplying, spreading and consolidating Moorum to a depth of 75 mm at desired density and C.B.R. as per specification with power roller to proper gradient and camber including watering as necessary, and lighting, guarding, barricading and making adequate earthen bundh where necessary to protect the edges and curing with water for 2 to 3 days, mending cracks by rolling where necessary including all incidental charges of roller, cost of fuel & lubricants etc. complete as per specification. Note: Add cost at site of the materials to arrive at the complete rate. The compaction factor may be taken as 0.67.(The payment is to be made on the basis of the finished compacted volume of moorum.)
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.