| 1 | Cutting uprooting and clearing jungles including shrubs, water weeds, bushes, trees, plants, upto 30 cm. girth including removing as directed by Engineer-in-charge. |
| 2 | Supplying, dressing and stacking at site bamboo pins above 5 cm. diameter and upto 7.5 cm. diameter (Dia to be measured at mid length) |
| 3 | Driving bamboo pins in standing or flowing water including scaffolding and driving appliances a) Where boats are not necessary |
| 4 | Supplying, fitting and fixing with iron nails half splitbamboowailing pieces (av. dia. of bamboo not less than 5.0 cm.) |
| 5 | Supplying Nylon cage netting 1 metre x 1 metre x 1 metre size with knot having mesh size 17.5 cm x 17.5 cm constructed with nylon thread (210 x 24) having tensile strength not less than 250 Kg. / sq. cm. including carriage, delivery and stacking at site inclusive of all taxes complete. |
| 6 | Labour charges for dumping and placing in position properly filled in Nylon crates with filled in gunny / poly cement bags (minimum 25 nos. having capacity 50 kg) with local earth or sand, sewing and tying the crate with nylon wire within a lead of 150 m. and all lifts in river slope or bed by cutting trenches upto 50 cms depth, if necessary, or by boat including cost of hire charges of boat, boatmen and other necessary equipments and also including cost of bags, carriage and charge of filling bags with earth / sand but excluding cost of nylon crate as per direction of the Engineer – in – Charge.NB:- Volume of each earth/ sand filled bags should not be less than 0.028 m3.Size of Nylon crate is 1metre X 1metre X 1metre.(a) Where boats are not necessary |
| 7 | Supplying to site empty cement polythene bags (capacity 50kg) in good condition including stacking, incidental charges etc. all complete(capacity 50 Kg |
| 8 | Labour charges for filling empty cement gunny bag / polythene bag (capacity 50 kg) with all kinds of earth (wet or dry), sand or agreegates(stone / brick) and sewing as done in case of cement bags ,( tying with a knot after filling will not be accepted ) , and stacking within a lead of 30 metre as per direction of Engr-in-charge (cost is excluding the cost of any types of filling materials).Note: Volume of earth /sand filled bags should not be less than 0.028 cum./bag |
| 9 | Dumping in position earth/ sand filled gunny/ poly bags (capacity 50 kg) within a lead of 30 metre inclusive of all lifts |
| 10 | Earthwork in excavation in all kinds of soil for making embankments, repairs to the embankment, closing breaches etc. as per profile including supply and transporting the earth by truck or tractor or any other mechanical means on land, including loading, transporting, unloading and stacking with all lifts bothways and head load where necessary and depositing the same on embankments, clannels, filling depressions in requisite profile, leveling as per direction of the Engineer-in-charge within a lead of.NB :- Measurement to be taken on the basis of stack measurement/pre-post work section measurement after deduction of void as per norms. No extra payment will be made for stacking.(For compensation for earth for land owned and arranged by conductor add Rs. 25.00 per m3 extra over rate of E/W for land owned/arranged by the department. Royalty charge on earth @ 29.00 per m3 & Cesses charges @Rs. 5.30 per m3(i.e. Rs. 15.00 per 100 cft) as per govt notification which will be paid on production of necessary documents in support of payment made towards the royalties & Cesses.) |
| 11 | A) Beyond 500 m and upto 1.00 km |
| 12 | C) Beyond 2.00 km and upto 3.00 km |
| 13 | B) Beyond 4.00 km and upto 5.00 km |