| 1 | S&F PP-R Tank Connector of Size 25mm complete all as specified and as directed. |
| 2 | ..do.. but 32mm |
| 3 | S&F PP-R Feamale Threaded Coupling with brass insert of Size 25mm x 1/2 \" complete all as specified and as directed. |
| 4 | ..do..but size 25mm x 3/4 \" |
| 5 | ..do..but size 32mm x 1/2 \" |
| 6 | ..do..but size 32mm x 3/4 \" |
| 7 | S&F PP-R Male Threaded Coupling with brass insertof Size 32mm x 1/2 \" complete all as specified and as directed. |
| 8 | --do-- but size 32mm x 3/4\" |
| 9 | S&F PP-R plain reducer of size 32 mm x 25 mm complete all as specified and as directed. |
| 10 | S&F PP-R End Cap of Size 25 mm complete all as specified and as directed. |
| 11 | --do-- but size 32mm |
| 12 | S&F PP-R Plain Elbow 90º of size 25mmcomplete all as specified and as directed. |
| 13 | --do-- but size 32mm |
| 14 | S&F PP-R Coupling of size 25mm complete all as specified and as directed. |
| 15 | --do-- but size 32mm size |
| 16 | S&F GI pipe nipple 25mm complete all as specified and as directed. |
| 17 | --do-- but size 32mm size |
| 18 | S&F GI pipe reducer of size 32/25mm complete all as specified and as directed. |
| 19 | S&F in repairs of Ball brass valves of 25mm, high pressure, with polythene float and flynut complete, screwed for iron pipe or brass ferrule and fixed complete all as specified and as directed. |
| 20 | S&F in replacement of PP-R Gate valves with brass insert of Size 25mm complete all as specified and as directed. |
| 21 | -do- butsize 32 mm |
| 22 | S&F in repairs 3-layer 25 mm outer dia, ISI marked PP-R (polypropylene random copolymer) concealed pipes SDR 7.4 (PN16) UV stabilized and antimicrobial fusion welded having thermal stability for hot & cold water supply including all PP-R plain & brass threaded polypropelene random fittings fixed to walls, ceilings or in floors with PPR wall Clamps etc complete all as Directed and specified. |
| 23 | S&F in repairs 3-layer 32 mm outer dia, ISI marked PP-R (polypropylene random copolymer) concealed pipes SDR 7.4 (PN16) UV stabilized and antimicrobial fusion welded having thermal stability for hot & cold water supply including all PP-R plain & brass threaded polypropelene random fittings laid in trenches complete all as Directed and specified. |
| 24 | --do-- but size 63mm outer dia |
| 25 | M&L for cutting the existing 25/32 mm PPR Pipe from the tank inlet and connecting it to the PP-R tank connector by Heat fusion method complete all as specified and as directed.Note: Tank connector is measured under relevent item of this scheduled. |
| 26 | M&L for connection of PP-R distribution branch with PP-R main of sizes 16 to 40 mm by providing and fixing tee including cutting and making fusion joint etc. all as specified and as directed. |
| 27 | M&L for connection of PP-R distribution branch with PP-R main of sizes 50 to 75 mm by providing and fixing tee including cutting and making fusion joint etc. all as specified and as directed. |
| 28 | Collection of water sample from different sources of pumpHouses under AGE(I) Suryalanka for water testingby Govt authorised Certified Labouratory as per IS-10500 for drinking water as under including Cost of sterlization bottle . (a) Colour hazen (b) Odour(c) Taste (d) Turbidity, NTU (e) PH value(f) Total dissolved solid, mg/ltr (g) Total Hardness (as CaCo3) mg/ltr(h) Chloride (as Cl2), mg/ltr (j) Nitrate (as NO3) mg/ltr(k) Iron (as Fe), mg/ltr(l) Coli form and Ecoli Mg/LNote: Quoated rate includes carrying of water to the laboratory. |
| 29 | Supply Only of Liquid Chlorine Sodium Hypochlorite (Grade-I) for Drinking Water, Chlorine percentage by mass by Vol is 4.0-6.0% (all Characteristics are as per IS-11673) in sealed non - Chemical reactioned/Oxidation LDPE containers of 60kg Tanks, as required on Monthly basis with Manufacturers test certificate and Date markes not more than 02 week old complete all as specified and as directed. |
| 30 | Supply Only Bleaching Powder, available Chlorine percentage by mass is 32-34%after 30 days of the manufacturing, (all Characteristics are as per IS-1065) in laminated HDPE having two inner liners, Container shall be marked with manufacturer grade, Mass complete all as specified and as directed. |
| 31 | De-watering the existing UG Sump of 50,000 Glns capacity and cleaning the internal surfaces of sump to remove scales, mud and other foreign materials, applying surfaces with mixture of bleaching powder and water, finally washing with fresh water and treating with one coat of white wash to internal wall and bottom surfaces etc complete for one time, writing in capital letter with black paint as \"Cleaned on (date) & next due on (date), letter\"s height not less than 5cm complete all as specified and as directed at Suryalanka Pump House and Bapatla Pump House. |
| 32 | De-watering the existing Static Water Tanks of capacity not more than 10,000 Glns capacity and cleaning the internal surfaces to remove scales, mud and other foreign materials, applying surfaces with mixture of bleaching powder and water, finally washing with fresh water and treating with one coat of white wash to internal wall and bottom surfaces etc complete for one time, writing in capital letter with black paint as \"Cleaned on (date) & next due on (date), letter\"s height not less than 5cm complete all as specified and as directed. |
| 33 | De-watering the existing Shallow wells of capacity not more than 20,000 Glns capacity and cleaning the internal surfaces to remove scales, mud and other foreign materials, applying surfaces with mixture of bleaching powder and water, finally washing with fresh water and treating with one coat of white wash to internal wall and bottom surfaces etc complete for one time, writing in capital letter with black paint as \"Cleaned on (date) & next due on (date), letter\"s height not less than 5cm complete all as specified and as directed. |
| 34 | De-watering the existing OH Reservoir of capacity 20,000 Glns at 18 mtr staging and cleaning the internal surfaces to remove scales, mud and other foreign materials, applying surfaces with mixture of bleaching powder and water, finally washing with fresh water and treating with one coat of white wash to internal wall and bottom surfaces etc complete for one time, writing in capital letter with black paint as \"Cleaned on (date) & next due on (date), letter\"s height not less than 5cm complete all as specified and as directed.Note :- The unit rate quoted for item No-29 to 32 shall deemed to be included for the following complete all as specified and as directed:-(a) 250 gm of bleaching powder to be used for every 10 liter of fresh water.(b) All the inlet/outlet/over flow wash out connection shall be cleaned as rust free and any leakage in joints shall be made good.(c) The water available in the tanks/ Shallow Well/UG sums/OH Reservior shall be bailed out to the nearest open drain available.(d) Any damage caused during cleaning the existing assets shall be made good by the contractor without any extra cost.(e) Painting of of pipe inlet/outlet/washout/overflow pipe with various colours as existing along the tank height duly scrapped and applying one coat of red oxide paint and two coats of synthetic enamel paint. |
| 35 | Excavationin trenches not exceeding 1.5 m wide and not exceeding 1.5 m in depth and gettingout in soft/ loose soil, for under ground electric cable, pipes etc complete all as specified and as directed. |
| 36 | Returning, filling-in, including, spreading, watering and well ramming in layers notexceeding 25 cm thick each, in soft /loose soil complete all as specified and as directed. |
| 37 | Removal of surplus soil to a distance not exceeding 50 mtr and depositing where directed by Engineer –in- Charge at a level not exceeding 1.5mtr above the starting point complete all as specified and as directed. |