| 1 | ROAD WORK |
| 2 | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specifications Clause 201 for Rural Roads of MORD. i)By Mechanical Means. b)In area of thorny jungle. |
| 3 | Earthwork in cutting to form road section in correct profile including removal of spoils not exceeding initial lead of 50m and initial lift of 1.5m (Mode of measurement: pre works and post works). (ii) In mixed soil (i,e. clay mixed with kankar, pebbles, moorum etc.) |
| 4 | Supplying, spreading and compacting Sand to required thickness, in layers not exceeding 150 mm to proper gradient and camber, inundating each layer by water and packing and ramming layer by layer to achieve desired compaction, including lighting, guarding, barricading and making adequate earthen bundh where necessary, curing with water as per direction, mending cracks and depressions by ramming wherever necessary. |
| 5 | Water Bound Macadam Sub Base by consolidatingJhama metal / Laterite chelly or stone metal /shingles of specific size in hard crust to requisitethickness (measured after compaction) in layersincluding screening of metals etc. as necessary,hand packing, sweeping, watering and rolling instages with power roller to proper line, grade andcamber, lighting, guarding & barricading andmaking necessary earthen bundh of one metrewidth on each side where necessary to protectedges and preparing the bed by necessary cuttingor filling and rolling all complete including the cost ofall materials and hire and labour charges of all menand machineries and compacting to the requireddensity, as per Clause 404 of Specifications for Road& Bridge Works of MoRT&H (5th Revision).(i) For Construction of Sub Base by consolidatingJhama metal (63 mm to 45 mm) with moorumscreening : |
| 6 | Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements, in any part of foundation of bridges / culverts with graded stone chips of appropriate nominal sizes, including screening and cleaning of coarse aggregates, zfine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, cost of curing with water, including cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge, cost for quality control, sampling, testing etc. including cost of formwork but excluding reinforcement complete as per drawing and technical specifications. PCC M20 |
| 7 | Tack Coat:- Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS: 8887-1978 on the prepared surface cleaned with Hydraulic broom,moistening the surface including cost and carriage of emulsion, hire charges of machinery and labour, cost of fuel and lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (iii) On Cement concrete pavement(Using Bitumen emulsion at the rate of 0.30 to 0.35 kg per sqm.) |
| 8 | Bituminous ConcreteProviding and laying bituminous concrete with Hot Mix Plant using crushed aggregates, filler materials (Cement /hydrated lime /Rock dust) and premixed with bituminous binder of specified grading @5.2% (min) for Gr.-1 & @5.4% (min) for Gr.-2, as per table 500-17 and mix design done as per table 500-10 and job mix formula as per ci. 505.3.3, including screening, cleaning of chips and preparing a uniform and quality mix, transporting the hot mix to work site, laying the mixed materials at specified laying temperature as specified in Table 500-2 with a hydrostatic paver finisher with sensor control to the required grade, level and alignment over prepared surface coated with tack coat, rolling with smooth wheeled and vibratory or tandem rollers or with a pneumatic tyre roller of 12 to 15 tonne weight with a tyre pressure of at least 0.56 MPa, to achleve the desired density as per clause 505.3.5, including cost and carrlage of bitumen, crushed aggregates, filler materlals and hire charges of machinery and equipment for construction and quality control, complete as per Clause 507 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).B.For Grading 2(13.2 mm nominal size, 30mm/40 mm thick.) (iii) Using Drum mix Type HMP of minimum capacity 40-60 TPH. |
| 9 | Mastic AsphaltProviding and laying Mastic asphalt wearing course with paving grade bitumen meeting the requirements given in table 500-29 using approved coarse aggregate, fine aggregate, filler material and bitumen, prepared by using Mastic cooker including cost and carriage of all ingredients, cost of heating aggregates and binder, mixing in specified proportions conforming to approved Job Mix Formula and laid to required level and slope after cleaning the surface, compacting, sealing the construction joints and surface finishing conforming to specifications including providing antiskid surface with bitumen pre-coated fine-grained hard stone chipping of 13.2 mm nominal size at the rate of 0.005 cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surfaces not less than 100°C, protruding 1 mm to 4 mm over mastic surface, including the hire charges of all tools and plants and machinery, pay of operators, cost of fuel and lubricants and all other incidental charges and quality control all complete as per Clause 516 of Specifications for Road & Bridge Works of MoRT&H(5th Revision). (i) 25 mm thickness |
| 10 | Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface :-Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes complete as per Clause 803 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). |
| 11 | Road Studs: Supplying & fixing of Raised Pavement Markers / Road Studs / Cats Eye made of polycarbonate moulded body and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face which shall support a load of 13635 kg tested in accordance to ASTM D 4280 Type H and complying to clause no 804 of MoRT&H\"s specification for Road &Bridge Works (Fifth Rev.). Marker height shall not be less than 10 mm and shall not exceed 20 mm, width shall not exceed 130mm and with minimum reflective area of 13 sq.cm. on each side and slope to the base shall be 35 ± 5 degree. Fixing will be without nails but by using epoxy resin based adhesive as per manufacturer\"s recommendation including site clearance etc. and complete as directed by the Engineer in Charge .The contractor will have to provide a test certificate from a reputable national/international laboratory conforming the above specifications. |
| 12 | Supplying and laying Polythene Sheet (150gm / sq.m.) overdamp proof course or below flooring or roof terracing or in foundation or in foundation trenches. |
| 13 | Filler joint(iv) Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand and 6% bitumen by weight |
| 14 | Retro-Reflectorised Traffic SignsProviding and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC :67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing and Clause 801 of Specifications for Road & Bridge Worksof MoRT&H (5th Revision). iv) 80 mm x 60 mm rectangular |
| 15 | 125mm. thickbrickworkwith1st class bricks incementmortar (1:4) in ground floor. |
| 16 | Labour for Chipping of concrete surface before taking up Plastering work. |
| 17 | Supplying&laying as per IRC-SP:063-2004 paver unit of any shade of approvedquality as per relevant IS code, laid inpattern as directed in pavement, footpath, driveway (paverblockonly), etc including necessary under lay complete in all respect with all labour and material. [Border concrete if necessary to be paid separately]. (c)60mm thick interlocking designer concrete paver block M 35 grade for light-traffic zone,commercial & office complex,tourist resort as per IS:15658-2006 |
| 18 | DRAINAGE WORK |
| 19 | Earth work in excavation of foundation of structures as per drawing and technical specification,including setting out, removing, spreading or stacking of spoils within a lead of 150 m. as directed and including trimming the sides of the trenches, leveling, dressing and ramming the bottom,and backfilling with approved material complete as per direction of the Engineer-in-Charge. upto 3 m depth (iv)Without pumping out water but including shoring as required. |
| 20 | Earthwork in filling in foundation trenches with good earth in layers not exceeding 15cm. including watering and ramming layer by layer complete with earth obtained from excavation of foundation or from fresh excavation of land arranged by Department within a lead of 150 m. |
| 21 | Supplying and laying Polythene Sheet (150gm / sq.m.) overdamp proof course or below flooring or roof terracing or in foundation or in foundation trenches. |
| 22 | Sand filling in foundation trenches and at the back of abutments, wing-walls etc. with good local sand free from earth in layers not exceeding 15 cm. including inundating each layer by profuse water and poking and ramming layer by layer complete including supply of sand. Quality of sand is to be approved by the Engineer-in-charge. |
| 23 | Providing and laying Design Mix concrete for plain / reinforced concrete work in any part of bridge (excluding bottom plugging) with coarse aggregates of appropriate nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete but excluding cost of labour and materials for formwork & reinforcement works. (a) M-15 Grade Using concrete mixer. |
| 24 | Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements, in any part of foundation of bridges / culverts with graded stone chips of appropriate nominal sizes, including screening and cleaning of coarse aggregates, zfine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, cost of curing with water, including cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge, cost for quality control, sampling, testing etc. including cost of formwork but excluding reinforcement complete as per drawing and technical specifications. RCC Grade M25 |
| 25 | Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements, in any part of foundation of bridges / culverts with graded stone chips of appropriate nominal sizes, including screening and cleaning of coarse aggregates, zfine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, cost of curing with water, including cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge, cost for quality control, sampling, testing etc. including cost of formwork but excluding reinforcement complete as per drawing and technical specifications.RCC M20 |
| 26 | Supplying, fitting and placing un-coated HYSD bar reinforcement in Bridge Foundation including initial straightening, straightening of coils bars, removal of loose rust (if any), cutting to requisite length bending, binding with annealed wire not less than 1 mm in size and conforming to IS 280 at every intersection hooked and bent to correct shape and placed on forms etc. including cost of black annealed wire and cost of loading, unloading, carriage of all steel materials complete as per drawing and technical specifications and direction of Engineer-in-charge. |
| 27 | Artificial stone in floor, dado, staircase etc with cement concrete (1:2:4) with stone chips, laid in panels as directed with topping made with ordinary or white cement In ground floor. (as necessary) and marble 3 mm. thick topping (High polishing grinding on this item is not permitted with ordinary cement).(ii) 25 mm. thick |
| 28 | Labour for Chipping of concrete surface before taking up Plastering work. |
| 29 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](ii) With 1:4 cement mortar(a) 20 mm thick plaster |
| 30 | Neat cement punning about 1.5mm thick in wall, dado, window sill, floor etc. NOTE:Cement 0.152 cu.m per100 sq.m. |
| 31 | ADD FOR GST @ 18% |
| 32 | ADD FOR CESS @ 1% |