Package No. 8 [Renovation Of Building 4 Nos At Munasandhai Pums In Munasandhai Panchayat]
Tender Value
7.60 Lakhs
Estimated cost
Bid Submission
02 Jul 2025
0 days left
EMD
8000
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
arimalam → Tamil Nadu
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Package No. 8 [Renovation of Building 4 Nos at Munasandhai PUMS in Munasandhai Panchayat]
BOQ
| Sl. No. | Item Description |
| 1 | Repairs to RCC Roof School Building @ Munasanthai PUMS (Near SH Building) in MunasanthaiPanchayat |
| 2 | Chipping of concrete and roughening the surface including cost of conveyance of all labour charges etc., complete |
| 3 | Dismantling Existing pressed Tilesand RemoveingDebrices away from Siteincluding all cost and conveyance and all Labour charges etc Complete |
| 4 | Finishing the top of the roof with one course of Machine PressedTiles of size 23x23x2 cm of approved quality laid in CM 1:3(One cement and three sand) 12 mm thick mixed with water proofing compound conforming to ISS by 2% weight of cement used and the joint pointed neatly to full depth of tiles with the same water proofing compound mixed with cement mortar,red oxide, etc., complete complying with standard specification(30% New tiles ) |
| 5 | Providing granolithic floor finish with ISS metal to 25mm thick including cost and conveyance of all materials to site and all labour charges for mixing, laying, curing etc complete |
| 6 | White washing two coats using shell lime including cost and conveyance and all labour charges etc complete |
| 7 | Black Board Paintingtwo coats over one coat of Primary Coat including cleaning preparing the surface including cost and conveyance of all materials to site and all labour charges etc complete(For OLD Wall) |
| 8 | Distembering two coats with best approved distemberincluding cost and conveyance of all materials to site and all labour charges etc complete |
| 9 | Exterior Emulsion over one coatincluding Cleaning, preparing the Surfaceincluding cost and conveyance of all materials to site and all labour charges etc complete(For OLD Wall) |
| 10 | Painting two coats using Enamel Paint for Old Iron Work including cost and conveyance of all materials to site and all labour charges etc complete |
| 11 | Provision for Cup Board (Sub Estimate) |
| 12 | Provinding Cup-board Shutter With Frame Using Termite /Water Proof Plywood of 19mm Thick Over Which laminated Sheet of 0.8mm thick fixed inside the Shutter and 1mm thick fixed in the outside if the shutter using fevicol along with necessary furniture fittings ,Such as,hydralic hings ,tower bolt,handles ,multi Purpose locks etc .,as directed by the Departmental officers,the design Pattern,Water Proof Plywood ,Laminate sheet and other materials Should be got approved from the Executive Engineer before use on Work |
| 13 | Provision forPedestal for Keeping Drinking water Container (Sub Estimate) |
| 14 | Earth work excavation and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B |
| 15 | Supply of M sandand filling conveyanceto the siteand all labour charges for fillingas per standard speecifications |
| 16 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete |
| 17 | Brick work in cement mortar 1:5 mix using country bricks83/4\"x43/8\"x23/4\"and conveyance of all materials to site and all labour charges etc complete |
| 18 | Plastering with cement mortar 1:5 mixto12mmthick including cost and conveyance of all materials to site and all labour charges etc complete |
| 19 | Paintingtwo coats with Emulsion Paintover one coat of Primary Coat including Cost and Conveyance of allmaterials to site and all Labour charges etc complete. |
| 20 | Supplying & fixing with Cuddapah Slabs 20-30mm thick for Cup Board thick and Pointed with Cement mortar 1:3-10 Sqm |
| 21 | Repairs to RCC Roof School Building @ Munasanthai(North Face Buliding) PUMS in MunasanthaiPanchayat |
| 22 | Chipping of concrete and roughening the surface including cost of conveyance of all labour charges etc., complete |
| 23 | Dismantling Existing pressed Tilesand RemoveingDebrices away from Siteincluding all cost and conveyance and all Labour charges etc Complete |
| 24 | Finishing the top of the roof with one course of Machine PressedTiles of size 23x23x2 cm of approved quality laid in CM 1:3(One cement and three sand) 12 mm thick mixed with water proofing compound conforming to ISS by 2% weight of cement used and the joint pointed neatly to full depth of tiles with the same water proofing compound mixed with cement mortar,red oxide, etc., complete complying with standard specification(30% New tiles ) |
| 25 | Providing granolethic floor finish with ISS metal to 25mm thick including cost and conveyance of all materials to site and all labour charges for mixing, laying, curing etc complete |
| 26 | Plastering with cement mortar 1:5 mixto12mmthick including cost and conveyance of all materials to site and all labour charges etc complete |
| 27 | White washing two coats using shell lime including cost and conveyance and all labour charges etc complete |
| 28 | Black Board Paintingtwo coats over one coat of Primary Coat including cleaning preparing the surface including cost and conveyance of all materials to site and all labour charges etc complete(For OLD Wall) |
| 29 | Distembering two coats with best approved distemberincluding cost and conveyance of all materials to site and all labour charges etc complete |
| 30 | Exterior Emulsion over one coatincluding Cleaning, preparing the Surfaceincluding cost and conveyance of all materials to site and all labour charges etc complete(For OLD Wall) |
| 31 | Painting two coats using Enamel Paint for Old Iron Work including cost and conveyance of all materials to site and all labour charges etc complete |
| 32 | Provision forPedestal for Keeping Drinking water Container (Sub Estimate) |
| 33 | Earth work excavation and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B |
| 34 | Supply of M sandand filling conveyanceto the siteand all labour charges for fillingas per standard speecifications |
| 35 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete |
| 36 | Brick work in cement mortar 1:5 mix using country bricks83/4\"x43/8\"x23/4\"and conveyance of all materials to site and all labour charges etc complete |
| 37 | Plastering with cement mortar 1:5 mixto12mmthick including cost and conveyance of all materials to site and all labour charges etc complete |
| 38 | Paintingtwo coats with Emulsion Paintover one coat of Primary Coat including Cost and Conveyance of allmaterials to site and all Labour charges etc complete. |
| 39 | Supplying & fixing with Cuddapah Slabs 20-30mm thick for Cup Board thick and Pointed with Cement mortar 1:3-10 Sqm |
| 40 | Renovation to Common Toilet@ Munsanthai PUMSin Munsanthai Panchayat |
| 41 | Chipping of concrete and roughening the surface including cost of conveyance of all labour charges etc., complete |
| 42 | Supplying and Fixing of creamic Tilesincluding cost and conveyance of all materials to site and all labour charges etc., complete. |
| 43 | Dadooing of walls with glazed tiles of size 15 cm x15cmx6mm laid in CM 1:2, 10mm thick & pointing with white cement using 0.4kg/cm2including cost and conveyance of all materials to site and all labour charges etc., complete. |
| 44 | Distempering the old walls and ceiling one coat with best oil bound distemper of approved quality including preparation of surfaces (the colour and quality should be got approved by the Executive Engineer before use) the rate includes cost of brushes, high scaffolding charges, neat finishing, cost of brushes etc., complete complying with standard specification and as directed by the Departmental Office |
| 45 | Distempering the old walls and ceiling one coat with best oil bound distemper of approved quality including preparation of surfaces (the colour and quality should be got approved by the Executive Engineer before use) the rate includes cost of brushes, high scaffolding charges, neat finishing, cost of brushes etc., complete complying with standard specification and as directed by the Departmental Officer |
| 46 | Painting two coats using Enamel Paint for Old Iron Work including cost and conveyance of all materials to site and all labour charges etc complete |
| 47 | Supplying and fixing of RCC rings for Leach pit including all charges etc complete |
| 48 | 900mm Rings for Toilet |
| 49 | 600mm Rings for Urinel |
| 50 | Supplying and fixing of cover slabincluding all charges etc complete |
| 51 | 900mm Cover Slab |
| 52 | 600mm Cover Slab |
| 53 | Supply and Fixing of Indian type Water closet 580x440mm of approved quality etc complete |
| 54 | Repairs to RCC Roof Kitchen Shed @ Munasanthai PUMS in MunasanthaiPanchayat |
| 55 | Finishing the top of roof with one course of Pressed tiles conveyance of all materials to site and all labour charges etc complete for 10 Sqm 30% New Tiles |
| 56 | Chipping of concrete and roughening the surface including cost of conveyance of all labour charges etc., complete |
| 57 | Providing granolithic floor finish with ISS metal to 25mm thick including cost and conveyance of all materials to site and all labour charges for mixing, laying, curing etc complete |
| 58 | Plastering with cement mortar 1:3 mixto 10 mm thick including cost and conveyance of all materials to site and all labour charges etc complete |
| 59 | White washing two coats using shell lime including cost and conveyance and all labour charges etc complete |
| 60 | Distembering two coats with best approved distemberincluding cost and conveyance of all materials to site and all labour charges etc complete |
| 61 | Exterior Emulsion over one coatincluding Cleaning, preparing the Surfaceincluding cost and conveyance of all materials to site and all labour charges etc complete(For OLD Wall) |
| 62 | Painting two coats using Enamel Paint for Old Iron Work including cost and conveyance of all materials to site and all labour charges etc complete |
| 63 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column \"BB\" for all works in this package}(Refer Clause 1 & 61 of Section 2 of Instruction to Bidders (ITB) of SBD) |
AI Tender Summary
Tender Timeline
Jun 30, 2025
11:30 IST
Tender Published
Tender notice published.
CompletedJul 02, 2025
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedJul 02, 2025
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender