| 1 | Part- I Repair and Maintanance Panchayat union Elemantary School (Tiled Roof) @ Sankankottai village in vengaloor Panchayat |
| 2 | chipping of wall and Roughening in the surface |
| 3 | Plastering with Cement Morter 1:5 mix 12 mm thick inculding cost and conveyanceof all materials to site and labour charges for curing etc |
| 4 | chipping of Flooring and Roughening in the surface |
| 5 | Plastering with Cement Morter 1:5 mix 12 mm thick inculding cost and conveyanceof all materials to site and labour charges for curing etc |
| 6 | Cement Concrete 1:4:8 (One Cement, Four M.Sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundationincluding dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification |
| 7 | Paving the floor with kota stone slab of size 610 x 610 of20mm (un-polished) in all floors laid in of cement mortor 1:3 (one cement three M.Sand), 20mm thick and pointed with colour cement neatly including polishing with polishing stone and oxalic acid etc., so as to perfectly smooth and glossy and including hire charges for polishing machine and power consumption charges etc. The kota stone slabs and other materials to be used shall be got approved by the Executive Engineer concerned before use on work, etc., complete as per standard speicification. |
| 8 | Supplying and painting the walls with two coats of oil bound distemper over one coat of water based cement primer including cost for distemper, primer, cleaning and scrapping the walls, rendering the wallssmooth with necessary putty, brushes, scaffolding arrangements, labour charges, etc., as per standard specification.(The colour and shade of the distemper shall be got approved by the Executive Engineer before use of work). |
| 9 | Painting two coats of newly plastered wall surface with ready mixed plastic emulsion paint of first class quality and of approved colour over a priming coat including thorough scrapping, clean removal of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying with standard specification. |
| 10 | Painting with Enamel paint two coat of old iron works such as steel Doors ,windows ,ventilators, etc., with best approved first quality of synthetic enamel paint of approved colour over the existing priming coats,etc. |
| 11 | Painting two coats with approved Black Oxide for Old Black boardof all materials to site and labour charges foretc.complete |
| 12 | Supply and fixing of LED 40 w have to provide per Class room |
| 13 | Supply and fixing ofFan 1200 mm have to provide per Class room |
| 14 | Part-II Renovation ofPanchayat union Elemantary School Toilet @ Sankankottai village in vengaloor Panchayat |
| 15 | chipping of wall and Roughening in the surface |
| 16 | Plastering with Cement Morter 1:5 mix 12 mm thick inculding cost and conveyanceof all materials to site and labour charges for curing etc |
| 17 | chipping of Flooring and Roughening in the surface |
| 18 | Paving the floor with pre-polished concrete anti-skid tiles (Required shape and design) of 20mm thick of approved quality and colour laid in Cement Mortar 1:3 (One Cement and Three crushed stone M.Sand) 20mm thick and pointed with white cement mixed with colouring pigment at the rate of 0.40 Kg. / sq.m., curing, etc., complete complying with standard specification and as directed by the departmental officers.(The make and brand of the tiles should be got approved by Executive Engineer before use on works)Using anti-skid tiles (Observed Data) |
| 19 | Dadooing walls with following best approved quality, white / colour glazed tiles of following sizes set in Cement Mortar 1:2 (One Cement and Two crushed stone M.Sand) 10mm thick and pointing the joints with white cement mixed with colouring pigments at the rate of 0.40 Kg. / sq.m. neatly in all floors, curing, etc., complying with standard specification and as directed by the departmental officers. |
| 20 | Supplying and painting the walls with two coats of oil bound distemper over one coat of water based cement primer including cost for distemper, primer, cleaning and scrapping the walls, rendering the wallssmooth with necessary putty, brushes, scaffolding arrangements, labour charges, etc., as per standard specification.(The colour and shade of the distemper shall be got approved by the Executive Engineer before use of work). |
| 21 | Painting two coats of newly plastered wall surface with ready mixed plastic emulsion paint of first class quality and of approved colour over a priming coat including thorough scrapping, clean removal of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying with standard specification. |
| 22 | Painting with Enamel paint two coat of old iron works such as steel Doors ,windows ,ventilators, etc., with best approved first quality of synthetic enamel paint of approved colour over the existing priming coats,etc. |
| 23 | Supplying and fixing in positon Indian Water Closet (Oriya type) of size 580 x 440mm white glazed earthern ware of approved quality and brand with \"P\" or \"S\" trap conforming to BIS with crushed stone M.Sandcushion and forming flooring alround the closet using 40mm broken brick jelly in lime concrete 1:2:5 (One lime, Two crushed stone M.Sandand Five brick jelly) 100mm thick and finishing the top to the required slope and including giving necessary connection to CI soil pipes (including the cost of 100mm dia CI pipe for a length of 600mm) by dismantling brick masonry wall / reinforced cement concrete roof / floor slab and making good the dismantled portion to the original condition with leakages etc., complete complying with standard specifications and as directed by the departmental officers.(The water closet should be got approved by the Executive Engineer before use on works). |
| 24 | GST |
| 25 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |