Power Boards / Undertakings / PSU Closing in 0 days TDR #49680012

Running Contract For Various Distribution Works In Respect Of Aee/ Townoddanchatram => Limited

Issued by Boards / Undertakings / PSU · oddanchatram, Tamil Nadu
Tender Value
3 Lakhs
Estimated cost
Bid Submission
25 Jun 2025
0 days left
EMD
3000
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
oddanchatram → Tamil Nadu
EMD Exemption
Available
Quantity
Not Available

Project Description

Running Contract For Various Distribution Works In Respect Of Aee/ Townoddanchatram => Limited- 1 Route surveying andpeg marking of HT/LTlines 2 Loading and un loading of of 9.14 Mtr poles / 9 Mtr PSC 3 Loading and un loading of of 8.0m pole psc 4 Transport of conductor from road side to workspot upto 1KM stringing and sagging up to 7/2.50mm & 7/2.59mm including PVC Cable up to 25Sqmm of conductor including binding of pin and proper tightening 5 Transport of conductor from road side to workspot upto 1KM stringing and sagging up to 7/3.15 mm & 7/3.35 mm including PVC Cable up to 25Sqmm of conductor including binding of pin and proper tightening 6 Transport of conductor from road side to workspot upto 1KM stringing and sagging up to 7/4.09 mm ACSR including PVC Cable up to 25Sqmm of conductor including binding of pin and proper tightening 7 Transport of 9.0 Mtr PSC, 9.14 Mtr & and abovepoles including R.S Joist and Rail polesup to 8 KM 8 Transport of 8.0 Mtr PSC, and abovepoles including R.S Joist and Rail polesup to 8 KM 9 Excavation of pits in ordinary soil 9.14 Mtr Poles /9.0 Mtr PSC Poles/ All Metal poles(1.25x06x1.83M) 10 Excavation of pits in ordinary soil8.0mtr PSC Poles/ All Metal poles(1.25x06x1.83M) 11 Excavation of pits in ordinary soil forStay pit 12 Erection works( including refilling of excavation sand) 9.14 Mtr Poles 13 Erection works( including refilling of excavation sand) 8.0 Mtr Poles 14 Erection of stay set complete ( including refilling of excavation of sand) 15 Fixingof LT Sph X Arm/HT TI Fitting/ LT TI Fitting 16 Fixing of LT 3phX Arm 17 Fixing of 4 - 6 VX Arm 18 Fixing of tapping channel / Guarding X Arm 19 Fixing of 22 KV/33KV Pin Insulator/ PT insulator 20 Fixing of 22 KV Disc 21 Fixing of LT Shackle 22 Fixing of LT Pin insulator 23 Fixing of Aluminium Knob 24 Earthing of Poleincluding buring ,looping and binding 25 Mass concerting for pole 0.6Mx0.45Mx1.25M ( Cement ,Jelly,sand supplied by contractor) 26 Resagging of Cut Point Location 27 Flat guarding 28 Dismantling of 7.5m/8.0m Poles 29 Dismantling of9.14 Mtr. Poles 30 Dismantling of Stay set complete 31 Dismantling of conductors upto 7/2.59 MM and Coiling and Transporting from workspot to road side 32 Dismantling of conductors 7/3.35 MM and above and Coiling and Transporting from workspot to road side 33 Releasing of LT S ph X Arm/TI Fitting 34 Relaasing of LT 3 ph X Arm 35 Releasing of 4 - 6 V Cross Arm/Tapping channal 36 Dismantling of Transformer Structure materials 37 Dismantling of AB Switch at D.T.Structure 38 Dismantling of H.G. fuse set 39 Dismantling of Earth Pipe and Structure earthing complete 40 Dismantling of 2 Nos. Open type fuse unit set with all wiring complete(including bus bar arrangement) 41 Dismantling of Distribution Transformer 42 TransportingofLine Materials from Stores toworkspot 43 Loading and Un loading of Line Materials from Stores to worksite 44 loading /un Loading of D,Ts at field and stores without Crane 45 Erection of Top Channel, Bed Channel and Belding angle with all Structure Clamps 46 Erection of AB Switch with PT Insulators 47 Erection of HG Fuse Set 48 Erection of Distribution Transformer 49 Providing Jumbering of Structure 50 Erection of Cross Brassing Set complete 51 Transformer wiring in LT Side including Jumbering Bus Baretc. 52 Erection of LT Open tyoe fuse unit arrangement Single/Double (Including Jumbering) 53 Transformer Structure Poles Mass Concreting with coping 0.65x0.6Mx1.85M+0.65Mx0.6x0.35 coping 54 Painting of Structure complete excluding Distri.Tr.(one coat of Red Oxide) with painting materials (2kg x 150) 55 Painting of Structure complete excluding Distri.Tr.(one coat of Aluminium paint)with painting materials (1.5 Ltr x 350) 56 Colour washing of 2 Nos. Structure Poles excluding cost of Distember/Snowsem) with painting materials (2 kg x 60) 57 Paing of Transformer name Plate details including cost of the sheet (1.5 X 1) and paint 58 Painting name of SS at seating Channel including paint 59 Erection of Single pole Transformer Bed 60 Erection of Single pole A.B. Switch (G.OS) 61 Erection of Single pole H.G.Fuse set 62 Painting of all clamp , other materials and painting of Strucure pole( Excluding Paint) 63 LT cable arrangement 64 Provision of Distribution Transformer Name Board (Name of the 22/11 kv feeder, Name of the SS, Capacitty , Danger Board ) 65 Fabrication of centre support and erection of centre support including pits 66 Mass concreting for centre support for 2 feet including all materials 67 Fixing of Danger Board (Excluding Paint) 68 Erection of Plinth for (22 KV) Single pole Structure 69 Erection of Earth pipes and Structure earthing(complete) 70 Mass concreating PCC including cost of Jally,MSAND& cement,Lead ,Lift etc. with a mixture of 1:3:6 for 9m Square pole with copping for single pole 71 Providing Holes of all size Flat/Angles/Channels 72 Welding 73 Manufacturing of clamps & Altering of clamps 74 Transporting of Distribution Transformer by using private vehicle ( all capacities up to 30KM) 75 GST

BOQ

Name of Work:- Running Contract for Various Distribution Works in respect of AEE/ TownOddanchatram
Sl. No. Item Description
1Route surveying andpeg marking of HT/LTlines
2Loading and un loading of of 9.14 Mtr poles / 9 Mtr PSC
3Loading and un loading of of 8.0m pole psc
4Transport of conductor from road side to workspot upto 1KM stringing and sagging up to 7/2.50mm & 7/2.59mm including PVC Cable up to 25Sqmm of conductor including binding of pin and proper tightening
5Transport of conductor from road side to workspot upto 1KM stringing and sagging up to 7/3.15 mm & 7/3.35 mm including PVC Cable up to 25Sqmm of conductor including binding of pin and proper tightening
6Transport of conductor from road side to workspot upto 1KM stringing and sagging up to 7/4.09 mm ACSR including PVC Cable up to 25Sqmm of conductor including binding of pin and proper tightening
7Transport of 9.0 Mtr PSC, 9.14 Mtr & and abovepoles including R.S Joist and Rail polesup to 8 KM
8Transport of 8.0 Mtr PSC, and abovepoles including R.S Joist and Rail polesup to 8 KM
9Excavation of pits in ordinary soil 9.14 Mtr Poles /9.0 Mtr PSC Poles/ All Metal poles(1.25x06x1.83M)
10Excavation of pits in ordinary soil8.0mtr PSC Poles/ All Metal poles(1.25x06x1.83M)
11Excavation of pits in ordinary soil forStay pit
12Erection works( including refilling of excavation sand) 9.14 Mtr Poles
13Erection works( including refilling of excavation sand) 8.0 Mtr Poles
14Erection of stay set complete ( including refilling of excavation of sand)
15Fixingof LT Sph \"X\" Arm/HT TI Fitting/ LT TI Fitting
16Fixing of LT 3ph\"X\" Arm
17Fixing of 4\" - 6\" \"V\"\"X\" Arm
18Fixing of tapping channel / Guarding \"X\" Arm
19Fixing of 22 KV/33KV Pin Insulator/ PT insulator
20Fixing of 22 KV Disc
21Fixing of LT Shackle
22Fixing of LT Pin insulator
23Fixing of Aluminium Knob
24Earthing of Poleincluding buring ,looping and binding
25Mass concerting for pole 0.6Mx0.45Mx1.25M ( Cement ,Jelly,sand supplied by contractor)
26Resagging of Cut Point Location
27Flat guarding
28Dismantling of 7.5m/8.0m Poles
29Dismantling of9.14 Mtr. Poles
30Dismantling of Stay set complete
31Dismantling of conductors upto 7/2.59 MM and Coiling and Transporting from workspot to road side
32Dismantling of conductors 7/3.35 MM and above and Coiling and Transporting from workspot to road side
33Releasing of LT S ph \"X\" Arm/TI Fitting
34Relaasing of LT 3 ph \"X\" Arm
35Releasing of 4\" - 6\" V\" Cross Arm/Tapping channal
36Dismantling of Transformer Structure materials
37Dismantling of AB Switch at D.T.Structure
38Dismantling of H.G. fuse set
39Dismantling of Earth Pipe and Structure earthing complete
40Dismantling of 2 Nos. Open type fuse unit set with all wiring complete(including bus bar arrangement)
41Dismantling of Distribution Transformer
42TransportingofLine Materials from Stores toworkspot
43Loading and Un loading of Line Materials from Stores to worksite
44loading /un Loading of D,Ts at field and stores without Crane
45Erection of Top Channel, Bed Channel and Belding angle with all Structure Clamps
46Erection of AB Switch with PT Insulators
47Erection of HG Fuse Set
48Erection of Distribution Transformer
49Providing Jumbering of Structure
50Erection of Cross Brassing Set complete
51Transformer wiring in LT Side including Jumbering Bus Baretc.
52Erection of LT Open tyoe fuse unit arrangement Single/Double (Including Jumbering)
53Transformer Structure Poles Mass Concreting with coping 0.65x0.6Mx1.85M+0.65Mx0.6x0.35 coping
54Painting of Structure complete excluding Distri.Tr.(one coat of Red Oxide) with painting materials (2kg x 150)
55Painting of Structure complete excluding Distri.Tr.(one coat of Aluminium paint)with painting materials (1.5 Ltr x 350)
56Colour washing of 2 Nos. Structure Poles excluding cost of Distember/Snowsem) with painting materials (2 kg x 60)
57Paing of Transformer name Plate details including cost of the sheet (1.5 X 1) and paint
58Painting name of SS at seating Channel including paint
59Erection of Single pole Transformer Bed
60Erection of Single pole A.B. Switch (G.OS)
61Erection of Single pole H.G.Fuse set
62Painting of all clamp , other materials and painting of Strucure pole( Excluding Paint)
63LT cable arrangement
64Provision of Distribution Transformer Name Board (Name of the 22/11 kv feeder, Name of the SS, Capacitty , Danger Board )
65Fabrication of centre support and erection of centre support including pits
66Mass concreting for centre support for 2 feet including all materials
67Fixing of Danger Board (Excluding Paint)
68Erection of Plinth for (22 KV) Single pole Structure
69Erection of Earth pipes and Structure earthing(complete)
70Mass concreating PCC including cost of Jally,MSAND& cement,Lead ,Lift etc. with a mixture of 1:3:6 for 9m Square pole with copping for single pole
71Providing Holes of all size Flat/Angles/Channels
72Welding
73Manufacturing of clamps & Altering of clamps
74Transporting of Distribution Transformer by using private vehicle ( all capacities up to 30KM)
75GST

AI Tender Summary

OUR REF NO 49680012
AUTHORITY Boards / Undertakings / PSU
TENDER VALUE 3 Lakhs
LAST DATE 25-06-2025
Authority
Authority Name Tamil Nadu Generation And Distribution Corporation Limited
Work Description Running Contract For Various Distribution Works In Respect Of Aee/ Townoddanchatram => Limited- 1 Route surveying andpeg marking of HT/LTlines 2 Loading and un loading of of 9.14 Mtr poles / 9 Mtr PSC 3 Loading and un loading of of 8.0m pole psc 4 Transport of conductor from road side to workspot upto 1KM stringing and sagging up to 7/2.50mm & 7/2.59mm including PVC Cable up to 25Sqmm of conductor including binding of pin and proper tightening 5 Transport of conductor from road side to workspot upto 1KM stringing and sagging up to 7/3.15 mm & 7/3.35 mm including PVC Cable up to 25Sqmm of conductor including binding of pin and proper tightening 6 Transport of conductor from road side to workspot upto 1KM stringing and sagging up to 7/4.09 mm ACSR including PVC Cable up to 25Sqmm of conductor including binding of pin and proper tightening 7 Transport of 9.0 Mtr PSC, 9.14 Mtr & and abovepoles including R.S Joist and Rail polesup to 8 KM 8 Transport of 8.0 Mtr PSC, and abovepoles including R.S Joist and Rail polesup to 8 KM 9 Excavation of pits in ordinary soil 9.14 Mtr Poles /9.0 Mtr PSC Poles/ All Metal poles(1.25x06x1.83M) 10 Excavation of pits in ordinary soil8.0mtr PSC Poles/ All Metal poles(1.25x06x1.83M) 11 Excavation of pits in ordinary soil forStay pit 12 Erection works( including refilling of excavation sand) 9.14 Mtr Poles 13 Erection works( including refilling of excavation sand) 8.0 Mtr Poles 14 Erection of stay set complete ( including refilling of excavation of sand) 15 Fixingof LT Sph X Arm/HT TI Fitting/ LT TI Fitting 16 Fixing of LT 3phX Arm 17 Fixing of 4 - 6 VX Arm 18 Fixing of tapping channel / Guarding X Arm 19 Fixing of 22 KV/33KV Pin Insulator/ PT insulator 20 Fixing of 22 KV Disc 21 Fixing of LT Shackle 22 Fixing of LT Pin insulator 23 Fixing of Aluminium Knob 24 Earthing of Poleincluding buring ,looping and binding 25 Mass concerting for pole 0.6Mx0.45Mx1.25M ( Cement ,Jelly,sand supplied by contractor) 26 Resagging of Cut Point Location 27 Flat guarding 28 Dismantling of 7.5m/8.0m Poles 29 Dismantling of9.14 Mtr. Poles 30 Dismantling of Stay set complete 31 Dismantling of conductors upto 7/2.59 MM and Coiling and Transporting from workspot to road side 32 Dismantling of conductors 7/3.35 MM and above and Coiling and Transporting from workspot to road side 33 Releasing of LT S ph X Arm/TI Fitting 34 Relaasing of LT 3 ph X Arm 35 Releasing of 4 - 6 V Cross Arm/Tapping channal 36 Dismantling of Transformer Structure materials 37 Dismantling of AB Switch at D.T.Structure 38 Dismantling of H.G. fuse set 39 Dismantling of Earth Pipe and Structure earthing complete 40 Dismantling of 2 Nos. Open type fuse unit set with all wiring complete(including bus bar arrangement) 41 Dismantling of Distribution Transformer 42 TransportingofLine Materials from Stores toworkspot 43 Loading and Un loading of Line Materials from Stores to worksite 44 loading /un Loading of D,Ts at field and stores without Crane 45 Erection of Top Channel, Bed Channel and Belding angle with all Structure Clamps 46 Erection of AB Switch with PT Insulators 47 Erection of HG Fuse Set 48 Erection of Distribution Transformer 49 Providing Jumbering of Structure 50 Erection of Cross Brassing Set complete 51 Transformer wiring in LT Side including Jumbering Bus Baretc. 52 Erection of LT Open tyoe fuse unit arrangement Single/Double (Including Jumbering) 53 Transformer Structure Poles Mass Concreting with coping 0.65x0.6Mx1.85M+0.65Mx0.6x0.35 coping 54 Painting of Structure complete excluding Distri.Tr.(one coat of Red Oxide) with painting materials (2kg x 150) 55 Painting of Structure complete excluding Distri.Tr.(one coat of Aluminium paint)with painting materials (1.5 Ltr x 350) 56 Colour washing of 2 Nos. Structure Poles excluding cost of Distember/Snowsem) with painting materials (2 kg x 60) 57 Paing of Transformer name Plate details including cost of the sheet (1.5 X 1) and paint 58 Painting name of SS at seating Channel including paint 59 Erection of Single pole Transformer Bed 60 Erection of Single pole A.B. Switch (G.OS) 61 Erection of Single pole H.G.Fuse set 62 Painting of all clamp , other materials and painting of Strucure pole( Excluding Paint) 63 LT cable arrangement 64 Provision of Distribution Transformer Name Board (Name of the 22/11 kv feeder, Name of the SS, Capacitty , Danger Board ) 65 Fabrication of centre support and erection of centre support including pits 66 Mass concreting for centre support for 2 feet including all materials 67 Fixing of Danger Board (Excluding Paint) 68 Erection of Plinth for (22 KV) Single pole Structure 69 Erection of Earth pipes and Structure earthing(complete) 70 Mass concreating PCC including cost of Jally,MSAND& cement,Lead ,Lift etc. with a mixture of 1:3:6 for 9m Square pole with copping for single pole 71 Providing Holes of all size Flat/Angles/Channels 72 Welding 73 Manufacturing of clamps & Altering of clamps 74 Transporting of Distribution Transformer by using private vehicle ( all capacities up to 30KM) 75 GST
Basic Detail
Tender No EE/ODC/ETS.No.04/25-26
Bidding Type Tender
Location
City oddanchatram
State Tamil Nadu
Key Dates
Publish Date 16 Jun 2025
Submission Date 25 Jun 2025
Open Date 26 Jun 2025
Finance
Tender Value 3 Lakhs
Tender Fee Ref. Documents
EMD 3000
Exemption Available
Document List
BOQ_680147.xls
Tendernotice_1.pdf
ba3b9ada-109d-4181-9457-6658ab6e2497.html

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Jun 16, 2025
11:30 IST

Tender Published

Tender notice published.

Completed
Jun 25, 2025
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Completed
Jun 26, 2025

Bid Opening Date

Technical bids will be opened and evaluated.

Completed

Tender Documents

Download All (ZIP) ↓
xls

BOQ_680147.xls

pdf

Tendernotice_1.pdf

html

ba3b9ada-109d-4181-9457-6658ab6e2497.html

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders