| 1 | Normal groundExcavation of pole pit (1.25m * 0.5m*1.5m)7.32m, 7.5m, 8m, 8.23m Poles |
| 2 | Normal Ground Erection of7.32m, 7.5m, 8m, 8.23m Poles |
| 3 | Rocky ground Excavation of pole pit (1.25m * 0.5m*1.5m)7.32m, 7.5m, 8m, 8.23m Poles |
| 4 | Rocky ground Erection of7.32m, 7.5m, 8m, 8.23m Poles |
| 5 | Normal Ground Excavation of pole pit (1.25m * 0.6m*1.83m) 9m, 9.14m Poles |
| 6 | Normal Ground Erection of9m, 9.14m Poles |
| 7 | Normal Ground of Excavation of pole pits (1.25m*0.6m*1.83m) for RSJ pole 36\" |
| 8 | Normal Ground of erection of 36\" RSJ pole |
| 9 | Rocky Ground of Excavation of pole pit (1.25m * 0.6m*1.83m) 9m, 9.14m Poles |
| 10 | Rocky Ground of Erection of9m, 9.14m Poles |
| 11 | Rocky Ground of Excavation of pole pits (1.25m*0.6m*1.83m) for RSJ pole 36\" |
| 12 | Rocky Ground of erection of 36\" RSJ pole |
| 13 | Transporting of poles fromroad side to pole pit -7.32m, 7.5m, 8m, 8.23m Poles |
| 14 | Transporting of poles fromroad side to pole pit -9m,9.14m RCC/PSC pole |
| 15 | Transporting of poles fromroad side to pole pit -36\" RSJ pole |
| 16 | Loading and Unloading of Poles-7.32m, 7.5m, 8m, 8.23m Poles |
| 17 | Loading and Unloading of Poles-9m,9.14m RCC/PSC pole |
| 18 | Loading Unloading of poles-36\" RSJ pole |
| 19 | Loading Unloading of linematerials |
| 20 | Concreting of pole as per Board Standards (2\"*2\"*5\"). The material such as sand, jelly, etc., have to be supplied by the contractor. Cement supplied by contractor (Cement concrete mix 1:4:8 using 40mm hard broken stone including cost of labour charges.for placing Transporting of sant,jally,from box and water curing for 14 days etc,.compleat. |
| 21 | Coping of pole (0.6m*0.6m*0.35m) |
| 22 | Concreting of stay (0.3m * 0.3m * 1.5m) including materials except cement. |
| 23 | Coil earthing per pole & pole earthing |
| 24 | Normal Ground-Excavation of stay pit (1.00m * 0.5m*1.5m)withtransporting of materials to site (for Stay Set) |
| 25 | Normal Ground -Erection of Stay Set |
| 26 | Rocky Ground-Excavation of stay pit (1.00m * 0.5m*1.5m)withtransporting of materials to site (For Stay Set) |
| 27 | Rocky Ground -Erection of Stay Set |
| 28 | Fixing of V & Channel Cross Arm 3.5\" including transporting of materials from road side to site |
| 29 | Fixing of V & Channel Cross Arm 4.5\" including transporting of materials from road side to site |
| 30 | Fixing of 3 phase Cross Armincluding transporting of materials from road side to site |
| 31 | Fixing of 1 phase Cross Armincluding transporting of materials from road side to site |
| 32 | Fixing of HT LT TI Fitting including transporting of materials from road side to site |
| 33 | Erection of HT side arm with stud including transporting of materials from road side to site |
| 34 | Erection of LT side arm with stud including transporting of materials from road side to site |
| 35 | Fixing of insulator (per location) including transporting of materials from road side to site |
| 36 | Fixing of Tapping Channel X Arm |
| 37 | Fixing of 11 KV Strain Disc |
| 38 | HT lines Stringing , Sagging, binding including transporting of materials from road side to site for-7/2.59 ACSR (1 Span/wire) |
| 39 | HT lines Stringing , Sagging, binding including transporting of materials from road side to site for-7/3.35ACSR (1 Span/wire) |
| 40 | HT lines Stringing , Sagging, binding including transporting of materials from road side to site for-7/4.09 ACSR (1 Span/wire) |
| 41 | For HT line clear works for 7/2.59 ACSR (1 Span/wire) |
| 42 | For HT line clear works for 7/3.35 ACSR (1 Span/wire) |
| 43 | For HT line clear works for 7/4.09ACSR (1 Span/wire) |
| 44 | LT lines Stringing , Sagging, binding including transporting of materials from road side to site for-7/2.59 ACSR (1 Span/wire) |
| 45 | LT lines Stringing , Sagging, binding including transporting of materials from road side to site for-7/3.35ACSR (1 Span/wire) |
| 46 | For LT line clear works for 7/2.59 ACSR (1 Span/wire) |
| 47 | For LT line clear works for 7/3.35 ACSR (1 Span/wire) |
| 48 | Spilt Neutral Guarding |
| 49 | Flat Guarding |
| 50 | Erection of Transformer /Dismantling upto 200 KVA |
| 51 | Erection of Transformer/Dismantling250 KVA |
| 52 | Erection of feeder cable with open type fuse unit per feeder |
| 53 | Erection of feeder cable with open type fuse unit per feeder and for each addl feeder |
| 54 | Erection of feeder cable Bus bar arrangement with open type |
| 55 | Erection of DT metering |
| 56 | Loadingof Distribution transformer below 250KVA |
| 57 | Unloading of Distribution transformerbelow 250KVA |
| 58 | Loadingof Distribution transformer250KVA |
| 59 | Unloading of Distribution transformerbelow 250KVA |
| 60 | Erection of centre Support ( incl. Concrete) |
| 61 | Dismantling of Center support |
| 62 | Alteration of clamps |
| 63 | Drilling less than 23 mm holes per hole/slatted hole |
| 64 | Cutting of channel |
| 65 | Cutting of Flat |
| 66 | Cutting of Angle |
| 67 | RSJ Pole Cutting |
| 68 | LT-Changing of pin point to cut point |
| 69 | HT-Changing of pin point to cut point |
| 70 | Erection ofservice connection materials -Single phase |
| 71 | Erection ofservice connection materials -Three Phase |
| 72 | Dismantling of deteriorated poles with concrete in damaged condition including grill separation etc., |
| 73 | Dismantling of poles without concrete in damaged condition including grill separation etc., |
| 74 | Providing jumpering at cut point |
| 75 | Tree clearance in HT or LT locationFor ordy. Tree clearance and Throng bushes & trees Each Labour /Head/Day |
| 76 | Tree clearance in HT or LT locationFor coconut Trees and palmrah tree each Labour/Head/Day |
| 77 | Set right of leaning of HT pole or LT pole including X arms, TI fittings |
| 78 | Resagging of Conductor 7/2.59 |
| 79 | Resagging of Conductor 7/3.35 |
| 80 | Resagging of Conductor 7/4.09 |
| 81 | Erection of Tapping Structure ( Double pole) complete as per TNEB standard including painting |
| 82 | Erection ofDistribution Transformer double pole Structure complete as per TNEB standard including painting feeders arrangement colour washing of RCC poles etc fixing of poles type to be unit HT/LT LAS and jumbering 3 nos earth pits with earth trough except erection of distribution Transformer |
| 83 | Erection of of 11 KV Single pole Structure including erection of DT complete as per TNEB TNEB standard including painting feeders arrangement colour washing of RCC poles etc fixing of poles type to be unit HT/LT LAS and jumbering 3 nos earth pits with earth trough except erection of distribution Transformer |
| 84 | Erection of Guarding X arm |
| 85 | Dismantling of Stay Set complete including stay rod |
| 86 | Dismantling of Stay set complete Without Stay rod |
| 87 | Dismantling of conductor of 7/2.59 including transporting the conductors to the nearset road side and stocking in coils |
| 88 | Dismantling of conductor of 7/3.35including transporting the conductors to the nearset road side and stocking in coils |
| 89 | Dismantling of conductor of 7/4.09 including transporting the conductors to the nearset road side and stocking in coils |
| 90 | Dismantling of Transformer structure materials complete set and transporting the same from the location to the road side |
| 91 | Dismantling of V Cross arm |
| 92 | Dismantling of 3 Phase X Cross Arm |
| 93 | Dismantling of Single phase X Cross |
| 94 | Dismantling of HT/LT TI Fitting |
| 95 | Dismantling of HTpin insulators |
| 96 | Dismantling of LT pin Insulators |
| 97 | Dismantling of strain Disc |
| 98 | Dismantling of Tapping/Guarding channel X Arm |
| 99 | Hiring of JCB |
| 100 | Hiring of crane |
| 101 | Exceeding 1 hour for every Hour |
| 102 | Transporting of charges of DT/line materials using private vehicle upto 20 KM(up and Down) |
| 103 | Beyond 20 KM for every KM |