| 1 | Supply of Structural steel/rolled steel materials for Embedded parts consisting of sill beam, wall liners & track base,top seal base,vertical lift sliding Gate leaf consisting of skin plate, Horizontal girders, End vertical girders, stiffeners, seal flats, lifting brackets, pad bases,Steel hoist bridge for single stem Nut type screw gear box hoist consisting of supporting beams, cross beams, base plates, anchor bolts, stiffeners, chequered plates,etc. including consumables all complete as per specification and approved drawings with all lead and lifts as per direction by the Engineer-in-charge including cess,contractor profit & OHC. |
| 2 | Supply of Stainless steel materials for sill beam S.S seal seat, S.S track, S.S side seal seat, top seal base SS seal seat etc all complete as per specification and approved drawings with all lead and lifts as per direction by the Engineer-in-charge including cess and contractor profit & OHC. |
| 3 | Fabrication cost of embedded parts & 1st stage embedments, studs, nuts, bolts, vertical lift sliding Gate leaf,Steel hoist bridge etc, with all accessories including machinery, fixtures, labour, cutting, alligning, welding, cleaning, drilling and boring, finishing, including consumables, all complete as per specification and approved drawings with all lead and liftsof 3346.32KG as per direction by the Engineer-in-charge including cess and contractor profit & OHC. |
| 4 | Cost of Erection, positioning, aligning, fixing, trial and commissioning including unloading and shifting up to location of all components of 1st stage and 2nd stage Embedded parts, Vertical Gate leaf, Steel hoist bridge assembly with all accessories including machinery, fixtures, labour, cutting, aligning, welding, cleaning, handling and rehandling all complete as per specification and drawings with all lead and lifts required at the erection site including cess,contractor profit &ohc. |
| 5 | Painting of all structural components including cleaning, degreasing, handling, cost of paint, applying of one coat primer of 40 micron thick and three coats of final paint of 100 micron each, all inclusive of labour, materials and consumables as per relevand IS code specifications and drawing with all lead & lifts including cess,contractor profit &ohc. |
| 6 | Bolts, Nuts, studs, washers etc |
| 7 | Bronze pad |
| 8 | Lifting pin |
| 9 | Bottam rubber seal |
| 10 | Dia 32 Side seal |
| 11 | Anchor bars |
| 12 | dia 63 screw rod with square thread |
| 13 | dia 63 round rod |
| 14 | Nut type screw Gearbox assembly suitably square threaded for 63mm dia screw rod all inclusive of cost of material,cost of thrust bearing,machining & assembly charges. |
| 15 | operating handle |
| 16 | greese & gear oil |
| 17 | Concrete cutting,2ⁿᵈ stage concreting ,coffer dam,dewatering includingcontractor profit,labour cess & ohc. |
| 18 | Transportation of above said half-finished materials, generator, welding transformer,.derrick & other T&p, from workshop to worksite to & fro around 110 km. |