Work Of Issuing Connection For Public Charging (Ev Charging) To Upda Under Electricity Distribution Section Iii, Saifai Is To Be Done On Semi-Turnkey Basis Under Deposit Scheme Item
Tender Value
Ref. Documents
Estimated cost
Bid Submission
06 Jun 2025
0 days left
EMD
30430
Bank guarantee accepted
Document Fee
3540
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
saifai → Uttar Pradesh
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Work of issuing connection for public charging (EV Charging) to UPDA under Electricity Distribution Section III, Saifai is to be done on semi-turnkey basis under deposit scheme item
BOQ
| Sl. No. | Item Description |
| 1 | Carriage of Following Centralised Materials from Store Center Kunera Etawah to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. |
| 2 | STP Pole 11 MTR. |
| 3 | 400KVA 11/0.4KV TRANSFORMER NEW |
| 4 | MET CUB PILFER PROOF 11KV CTR 5/5 |
| 5 | 3X185 SQ.MM ALLUMINIUM CABLE XLPE 11KV |
| 6 | 3X120 SQ.MM ALLUMINUM CABLE XLPE 11KV |
| 7 | A.C.S.R WEASEL CONDUCTOR |
| 8 | ACSR DOG CONDUCTOR |
| 9 | 11 KV VCB OUTGOING |
| 10 | LT XLPE CABLE 3.5X150 SQMM |
| 11 | 11 KV CT/PT METERING POLE MOUNTED |
| 12 | 3PX4W TVM 11 KV |
| 13 | 3PH-4W STATIC LT TVM WITH MET CUBICLE |
| 14 | Supply & Fixing of Following De-Centralised Materials. Including the work of its loading and unloading at the respective ends & the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. |
| 15 | 3 PHASE DO FUSE SET |
| 16 | M.S DROPPER CHANNEL |
| 17 | RED OXIDE PAINT |
| 18 | 11 KV DISC INSULATOR WITH FITTING |
| 19 | CROSS ARM HOLDING CLAMP |
| 20 | TPMO 11 KV |
| 21 | M.S TOP CHANNEL 100X50X2240 |
| 22 | F-BRACKET WITH N&B |
| 23 | ALLUMINIUM CRIMPING LUG 400 SQ.MM |
| 24 | ALLUMINUM PAINT |
| 25 | CROSS ARMS V-TYPE 11 KV |
| 26 | MS T-OFF CHANNEL |
| 27 | NUT & BOLT |
| 28 | STONE PAD |
| 29 | PIN INSULATOR WITH PIN 11 KV |
| 30 | ALLUMINIUM CRIMPING LUG 150 SQ.MM |
| 31 | D.P CLAMP FOR STP |
| 32 | DANGER BOARD |
| 33 | BARBED WIRE |
| 34 | G.I PIPE |
| 35 | M.S ANGLE/ TF BASE ANGLE |
| 36 | CLAMP FOR M.S ANGLE |
| 37 | Erection, Concreting and plinting of Single support Pole 8.5with cement, coarse sand & stone ballast duly grouted including necessories clamps, accessories required fixing of HT/LT fittings as per Resspo norms. The support shall be grouted in cement, sand and brick ballast. It including the cost of all labour, T&P etc. required for proper completion of work. |
| 38 | Laying, sagging, stringing, binding & jumpering of ACSR Weasel Conductor on the newly erected pole asperRESPOmanualandasperdirectionofsupervising engineer,includingthecostofarrangementoflabour,T&P carrier etc. required for proper completion of work. |
| 39 | Laying, sagging, stringing, binding & jumpering of ACSR Dog Conductor on the newly erected pole asperRESPOmanualandasperdirectionofsupervising engineer,includingthecostofarrangementoflabour,T&P carrier etc. required for proper completion of work. |
| 40 | Erection and grouting of staycomplete including the work of nozzling etc. as per RESPO manual and also including the cost of arrangement of allgrouting material, labour, T&P etc. required for proper completion of work as per RESSPO Manual. |
| 41 | Fixing &connectingofEarthingRods as perRESSPOManual includingthecostoflabour,T&Petc.requiredforproper completion of work. |
| 42 | Laying Of LT XLPE Cabel 3.5x150 Sqmm |
| 43 | Laying Of 11 Kv 3x120 Sqmm. XLPE Cable |
| 44 | Laying Of 11 Kv 3x185 Sqmm. XLPE Cable |
| 45 | Laying Of GI Pipe Underground Minimum 3 Meters BelowAlong With Laying Of Sqmm XLPE Cable |
| 46 | Filling Of 11 Kv Heat Shrinkable Cable Jointing Kit (Indoor/Outdoor Type) with Supply Suitable for XLPE 3x120 Sqmm (including the cost arrangement of labour, T&P, carrier etc. required for proper completion of work) |
| 47 | Filling Of 11 Kv Heat Shrinkable Cable Jointing Kit (Indoor/Outdoor Type) with Supply Suitable for XLPE 3x180 Sqmm (including the cost arrangement of labour, T&P, carrier etc. required for proper completion of work) |
| 48 | Installation of New 11 KV VCB Outgoing and making all connection Properly. |
| 49 | Construction of 400 KVA T/F Plinth as per Resspo Norms. |
| 50 | Earthing Of VCB Pipe |
| 51 | Earthing for Body & Neutral Of Distribution Transformer including the cost of arrangement of Material, labour & T&P etc. Required for proper completion of work. |
| 52 | Fancing of 400 KVA Transformer with Fabrication, Erection & Grouting Complete. Required for proper completion of work. |
| 53 | Road Crossing Permission Charge. |
| 54 | Road Restoration Charge. |
| 55 | Laying Of Material Labour Charge. |
AI Tender Summary
Tender Timeline
Jun 01, 2025
11:30 IST
Tender Published
Tender notice published.
CompletedJun 06, 2025
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedJun 06, 2025
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender