| 1 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel, stoney earth and earth mixed with small size boulders SS 20B and Sand, silt or other loose soil, wet sand, silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water wherever necessary refilling the sides of foundation with excavated soil other than sand in layers of 15cm thick well rammed and completed, cleaning and levelling the site etc., complete - Footings- First Depth Upto 2.00M |
| 2 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel, stoney earth and earth mixed with small size boulders SS 20B and Sand, silt or other loose soil, wet sand, silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water wherever necessary refilling the sides of foundation with excavated soil other than sand in layers of 15cm thick well rammed and completed, cleaning and levelling the site etc., complete - Plinth Beam |
| 3 | Supplying and filling in foundation andbasement with Well Gravel in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. |
| 4 | Plain Cement concrete 1:4:8 (one cement, four sand, eight aggregate) using 40mm gauge handbroken granitestone jelly for foundation including dewatering if foundnecessary and laid in layers of not more than 15 cmthick and compacted,etc., complete complying withstandard specfication. |
| 5 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid over silver oakjoists of size 10cm x 6.5cm spaced at about 75cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation - Plinth Beam |
| 6 | Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - For plane surfaces such asrectangular or square RCC columns, sunshades, top and bottom slab of RCC boxing, etc. |
| 7 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of sand, but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - The Coarse and Fine aggregates to be used should comply with the requirements of IS standards. (No separate payment will be made by the Department for the excess usage of materials) -Upto Basement |
| 8 | Suppling and fabricating and placing in position MS(or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost ofsteel and binding wire also in all floors. |
| 9 | Brick work in CM 1:5 (one cement & Five Crushed Stone Sand (M- Sand)) using II class ground moulded bricks of size 9\" X 43/8\"X 2 3/4\" including finishing, curing, etc., complete complying with standard specification - 100CFT |
| 10 | Plastering with cement mortar 1:5 (One part of Cement and Five part of Plastering Sand (P- Sand)) 12mm, thick in all floors including cost and conveyance of all materilas to site and labour charges etc,complete as per standard specifications |
| 11 | Painting two coats of newly plastered wall surface with ready mixed Cement paint of first quality and of approved colour over a priming coat including preparing the surface, clean removal of dirt and including necessary plaster of paris putty wherever required etc., complete complying with standard specification. |
| 12 | Supplying, fabricating, erecting structural steel work for roofing welded or bolted type using MS channels, angles, plates and round bars etc. conforming to IS specification including primer coating and enamal painting as per Design given by the departmental officers etc, complete as per standard specification |
| 13 | Paintingwith Ready Mixed Enamel Paint over the new iron works of approved quality and colour without priming coatincluding the cost all materials etc.,complete, in all floors. |