|
| 1 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrockrequiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum |
| 2 | Plain Cement Concrete 1:4:8 (one part of cement, four part of Crushed Stone Sand (M- Sand) and eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification |
| 3 | Supplying and erecting centering for vertical plain/ RCC concrete walls of supply channel, retaining wall etc upto 90Cm height with necessary supports,all cross bracing with mild steel size of 90cm x60 cm and gauge BG 10 stiffened with welded mild steel sheet angles of size 25 mm x25 mm x3mm for bearing laid silver Oak/ Country wood joist of size 7.50 cm x5.0 cm spaced @ about 90 cm C/C and supported by Casurina props of 10 cm to 13 cm spaced @ 75 cm C/C etc,, complete complaying withstandered specfications and as directed by the departmental officers. |
| 4 | A) 1.00 M Below Side Centering |
| 5 | B) 1.00 M Above Side Centering |
| 6 | Suppling and fabricating and placing in position MS(or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost ofsteel and binding wire also in all floors. |
| 7 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - |
| 8 | Supply and fixing ofManhole Cover 60 x 60cm (Heavy Duty) with Frame Inculding cost and conveyance etc.., complete |
| 9 | Reinforced Cement Concrete 1:1½:3 Mix (One part cement, one and half part m.sand and three part of aggregate)using 20mm size ISS HBG metal machine crushed from approved quarry including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing but excluding cost of reinforcement etc.Complete with std.Specifications. TNDSS NO: 30 V, VI (S3), VII-3. |