| 1 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level. In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc. Depth upto 1.5 m |
| 2 | Brick work with FPS bricks of class designation 75 in foundation and plinth in: Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 3 | Cement plastering including T&P, scaffolding, material and complete labour, including cost of water, curing, racking of joints etc. with 15 mm cement plaster on the rough side of single or half brick wall of mix : including Providing /mixing of synthetic fibers compulsorily complying with IS 16481:2022 of 06 mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e. 125 gms per 50 kg Cement up to 900 gms per cum of Concrete/ mortar1:4 (1 cement : 4 fine/ coarse sand) |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level :1:1½:3 (1 Cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size). |
| 5 | Providing and laying lean cement concrete 1:4:8 in Sub- base over aprepared sub-grade with coarse and fine aggregate conforming toIS: 383, the size of coarse aggregate not exceeding 25 mm,aggregate cement ratio not to exceed 15:1, aggregate gradationafter blending to be as per table 600-1, cement content not to beless than 150 kg/ cum, optimum moisture content to be determinedduring trial length construction, concrete strength not to be less than10 Mpa at 7 days, mixed in concrete mixer, laidmanually,compacted with surface vibrator, finishing and curing complete asper clause 601, 112 of MoRT&H specification including all material,labour, machinery, lighting, guarding and maintenance of diversion. |
| 6 | Providing and laying un-reinforced, plain cement concrete mix withConcrete Mixer & vibrator pavement over a prepared sub base with43 grade cement , coarse and fine aggregate conforming to IS: 383,maximum size of coarse aggregate not exceeding 25 mm, mixed asper approved mix design, laid, spread, compacted and finished in a continuous operation including provision of contraction, expansion, Vconstruction and longitudinal joints etc including all material, labour,machinery, lighting, guarding and maintenance of diversion..PCC M-20 |