| 1 | Dismentling of damage ccincluding stacking dismental material with in 60m distence etc all comp. |
| 2 | Dismentling of damage brick work including stacking dismental material with in 60m distence etc all comp. |
| 3 | Dismentling of damage rcc work including stacking dismental material with in 60m distence etc all comp. |
| 4 | Earth work in excavation means (hydraulic )excavator/manual means in foundation trenches are drains (not exceeding 1.5 mtr in width or 10swm on plan ), excavation soil and disposal off sarface exavated soil as directed , within lead of 50 m.including dressing of side and ramming of bottoms, lift up to 1.5 m, including getting out the all kinds of soil. |
| 5 | providing and laying in cement conc Concrete 1:4:8(1 Cement4 fine sand and 8cm. gauge stone Ballast)and curing comp including cost of form work in foundation and floorsetc all comp. |
| 6 | E/W Surface Excavation no exceeding 30 cm in depth but ecceeding 1.5 m width as well as 10 sqm on plan including getting out disposal of excavatued earth up to 50m and lift up to 1.5 m as directed by the engineeer in charge etc all complete |
| 7 | Construction of G.S.B Etc all comp. |
| 8 | M-150 b/w with 1:4 cement & C.sand mortar etc all comp. Super structure |
| 9 | Supply of polythene125micronthick plastic sheet for . |
| 10 | Cartage of earth and dismental material upto 3.00km including loading unloading etc all comp. |
| 11 | 15 mm thickthick cement plaster( of neet cement of cement and marble dust on rough side 1 :4 cement c. sand for celling etc all comp. |
| 12 | construction of a chamber .60x.60x.9 etc all comp. |
| 13 | construction of gully pit as per knn design .60x.60x.75 etc all comp. |
| 14 | R/l main hole up to requred level etc all comp. |
| 15 | Supply/fixing and Jointing RCC hume pipe 250mm dia etc all comp. |
| 16 | Supply and fixing manhole Rcc coller etc all comp. |
| 17 | Supply and fixing manhole cover including all labor material T&P etc all comp. |
| 18 | providing and laying in position machine best and machine mix design M-25 grade cement concrete for rainforest cement concrete work using cement content as per approved design mix including pumping of concrete to site of laying but including loading the cast of centring shuttering finishing and reinforcement including and mixture in recommended propagation as per IS 9103 to escalate rated setting of concrete improve work imparing strength and durabilities as per direction of engineer in charge (note,-cement content consider in this item is @ 330 kg per cubic meter.Excess/less cement used as per design mix is payable /recoverable separately)all comp. |
| 19 | M.S. or iron in plain work such as reinforcement concrete or reinforced brick work (when not icluding over rate ) wrought torequired shape as necessary including bending for proper complition of the work and including suply of steel its wastage bend hooks and authorized ocerlaping shall be measured up two floor two level (over all rate ) |
| 20 | 18% GST |