| 1 | Loading, carriage & unloading of following materials from centre storeto work site and its stacking. Distance approx (0-45) kms. Under work area of EDD-Mitauli Lakhimpur. |
| 2 | (A) Line Material. |
| 3 | (B) PCC pole 8.5/9 Mtr long |
| 4 | (C) STP Pole 9/11 Mtr. long. |
| 5 | (D)- T/F 10/16/25/63/100 KVA |
| 6 | (E)- T/F 250 KVA |
| 7 | (F)ACSR Rabit/Dog /Racoon/weasel/ conductor |
| 8 | (G)ABC( 3x120/95/70/25/16) Sqmm. |
| 9 | (H)11 KV XLPE Cable (3x35/70/120/185/240) |
| 10 | (I) 11kv pilfer resistant metering cubical |
| 11 | (J) 33kv pilfer resistant metering cubical |
| 12 | (K)11 KV Pole mounted CT/PT |
| 13 | (L)DP Box 3 Phase |
| 14 | Fabrication, erection of sub-station type double pole on 8.5 mtr long PCC/11 mtr. Long ST pole along with fixing of necessary hardware of doble polealongwith necessery pin insulators as per RESPO specification and direction of E/I. |
| 15 | Dragging of ST/PCC pole to pit site, digging of pit erection and grouting (As per RESPO norms) of 11KV 9/11/8.5 mtr long ST/PCC pole with fixing of necessary items, such as V-type X-arm, F-bracket, 11KV Pin/Disc insulator, guarding angle(1.8 mm65x65x6) with nut & bolts its ramming as per RESSPO Specification. |
| 16 | Dragging of ST/PCC Pole from dump store to pit site, digging of pit erection & grouting (As per RESPO norms) of LT support suitable for laying of ABC line on 8.5mtr long PCC pole by providing of necessary eye hook/LT shackle insulator with clamps and its accessories etc. as per RESPO specification. Only Pole will be provided by the department. |
| 17 | Fabrication, erection T-Off pole single section pole along with T-Off channel clamp disc fitting & pin accessories, grouting in 1:4:8 cement sand and brick ballast as per RESPO specification. |
| 18 | Providing and fixing of 11 KV DO fuse set along with clamps & nut bolts on existing of double pole. |
| 19 | Fixing of 11 KV TPMO along with clamps & nut bolts on existing of double pole. |
| 20 | Ordinary earthing by MS earth Rod 2500mm long as per RESPO Schedule. Only GI wire& Earth rod shall be supplied by the department. |
| 21 | Grouting and Nuzzling of stay set complete including fixing of necessary clamps. Accessories required including its grouting by civil material (Sand: brick ballast: cement). Only stay rod and Stay wire shall be supplied by the Department. |
| 22 | Laying and sagging of 3 phase 3 wire 11 KV line on ACSR weasel/rabbit/Raccoon/Dog conductor as per RESPO specification and direction of E/I. |
| 23 | Providing and fixing of guarding angle on existing 11 KV support with clamp and nut bolts. |
| 24 | Cradle guarding of HT line by GI wire. GI wire shall be supplied by the department. |
| 25 | Erection & commissioning of (3x120/95/70/25/16 Sq.mm) Aerial Bunched Conductor. |
| 26 | Laying of cable 11 KV XLPE cable (3x35/70/120/185/240) sqmm in pakka road by boring method laying cable as per RESPO specification & direction of E/I. |
| 27 | Laying of cable 11 KV Through piping . |
| 28 | Hoisting of 11 KV XLPE Cable will be passed through MS pipe of required size duly clamped with pole at the bottom, middle and top of the pole. |
| 29 | Supply and fixing of 11 KVCablejoining kit O/D and I/D. |
| 30 | Installation of 11 KV CT/PT on double pole connected with metering unit along with providing and fixing of all accessories such as S/S base, MS flat, clamps, nut and bolts its jumpering and commissioning. |
| 31 | Dragging of 11 KV Pilfer metering cubical inside the metering room, its installation and commissioning. |
| 32 | Dragging of 33 KV Pilfer metering cubical inside the metering room, its installation and commissioning. |
| 33 | Fixing of 3 phase distribution box/kiosk on the LT poles including all clamps and material required for mounting connections and sealing. |
| 34 | Making section of 11 KV line by fixing of All necessaries accessories such asT-Off channel disc insulator with fitting pin insulator with pin along with sagging jumpering and binding etc only insulator shall be provided by the dept. |
| 35 | Cutting and chopping of tree branches for clearance of HT/LT Line. After clearance line throughout pieces of tree branches of site. |
| 36 | Safe installation & energisation of 10/16/25/63/100 KVA T/F on double pole by providing and fixing of L-piece, Lugs making HT/LT connections and its commissioning. Only Transformer shall be supplied by the deppt. |
| 37 | Safe installation & energisation of 250 KVA T/F on double pole by providing and fixing of L-piece, Lugs making HT/LT connections and its commissioning. Only Transformer shall be supplied by the deppt. |
| 38 | Construction new Fencing of100/250 kVA distribution Transformers installed under EDD-ILakhimpur by MS Sqaremesh fabricated on MS angles of size 50X50X6mm and MS striphaving overall dimension complete with one no gate with provision of hinges roller & lacking arrangement properly grouted and painted with one coat of Red Oxide primer and two coasts of Bus Green Super enamel Paint. |
| 39 | Construction new plinth of100/250 kVA Distribution transformer of size 5x5x4 Fit with first class bricks, cement and coarse sand as per RESPO Norms alongwith cost of materials. |
| 40 | Work for earthing of Distribution Transformer with G.I. Pipe type earthing pipe size 3cm dia from ground up-to the water level (Minimum 20 feet deep) as per standard practice (All materials shall be provided by the contractor) in work area of EDD-I Lakhimpur Kheri. |
| 41 | Supply of top Droper T-off clamp |
| 42 | Fabrication T-Off Top Droper S/s Base Grouting Engal |
| 43 | Supply of Net-Bolt i-type |
| 44 | Supply of 10/16 kva T/F Holding Clamp |
| 45 | Supply of LT Clamp for PCC/ST Pole |
| 46 | Supply of Holding Clamp for PCC/ST Pole |
| 47 | Supply of F-Clamp |
| 48 | Supply of Stay Clamp |