| 1 | Work |
| 2 | Cleaning grass and removal of the rubbish up to a distance of 50m outside the periphery of the area cleared.As per DAR No.-2.32 |
| 3 | Earth work in excavation by mechanical means(Hydraulic excavator)/manual means in foundation trenches or drains (not exceeding 1.5m in width or 10sqm on plan),excavated soil and disposal of surlus excavated soil ae directed with in a lead of 50m including dessing of sides and ramming of bottoms,lift up to 1.5m,including getting out the .All kinds of soil.As per DAR No.2.8.1 |
| 4 | Providing and laying in cement concrete 1:5:10 (1 cement : 5 coarse sand :10 graded Stone aggregate 40 mm nominal size) and curing complete,including cost of form- work, in foundation and floors.As per DAR NO.4.1.10 |
| 5 | RCC work Providing and laying in position specified grade of reinforced cement concrete , including the cost of centering, shuttering, finishing and excluding reinforcement - 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) In upto plinth lvl.As per DAR no.5.1.2 |
| 6 | Same as item 3 but R.C.C. work in Column (Using1:1.5:3Mix concrete) M-20.As per DAR No.5.2.2 |
| 7 | As in item 3 abovebut inR.C.C.Top bandwithapproved stone ballast. (Using1:1.5:3Mix concrete) M-20.As per DAR NO.5.3 |
| 8 | Mild steel or iron in plain work such as rein-forced concrete or reinforced brick work (when not included in overall rates) wrought to required shape as necessary.As per DSR No.5.22.6 |
| 9 | Brick work M-150 (1:6 cement coarse sandin foundation upto plinth lvl includingnecessarycutting and moulding of brick work asrequiredand also including honeycombed brick work in thickness of wall more than 12cms.As per DAR No.6.1.2 |
| 10 | Half brick masonary with common burnt clay (non modular) bricks of class -150 in super structure above plinth level up to floors v level.cement mortor 1:3 (1cement : 3 c.sand).As per DAR No.6.13.1 |
| 11 | 12mm cement plaster in single coat on fair side of single or half brick wall for exterior plastering up to floor two level including internal rounded angles chamfers, and/or roundedangles not exceeding 80mm in girth and finished even and smooth no extra for mixing any additive. (1)1 cement : 6 course sand.As per DAR No.13.4.2 |
| 12 | Providing and applying white cement based putty of average thickness 1 mm of approved brand and manufacture over the plastered wall surface to prepare the surface even and smooth complete.As per PWD No.13.80 |
| 13 | Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required shade. New work (Two or more coats applied @ 1.43 ltr/ 10 sqm. over and including priming coat of exterior primer applied @ 2.20 kg/ 10 sqm).As per PWD-13.46.1, 39 Circle Lko |
| 14 | Providing and fixing concertina coil fencing with punched tape concertina coil 600 mm dia 10 metre openable length ( total length 90 m), having 50 nos rounds per 6 metre length, upto 3 m height of wall with existing angle iron \"Y\" shaped placed 2.4m or 3.00 m apart and with 9 horizontal R.B.T. reinforced barbed wire, stud tied with G.I. staples and G.I. clips to retain horizontal, including necessary bolts or G.I. barbed wire tied to angle iron, all complete as per direction of Engineer-in-charge, with reinforced barbed tape(R.B.T.) / Spring core (2.5mm thick) wire of high tensile strength of 165 kg/ sq.mm with tape (0.52 mm thick) and weight 43.478 gm/ metre (cost of M.S. angle, C.C. blocks shall be paid separately).As per DSR No.16.53 |
| 15 | M.S. in iron work of small sizes and sections such as holding down bolts, hold fasts etc as required for proper completion of the work. (Angle Iron- 40x40x5).As per DAR No.10.31onTop of Boundary wall |
| 16 | Mild Steel Iron Gate and Grill of a approved qualitiy and drawing including supply of all materials, fabrication, labour, T&P in all respect as per direction of Engineer-in-charge for proper completion of work at site.As per DAR No.10.25.2 |
| 17 | Painting two coat over priming coat (but including cost of priming coat) on steel and other metal surfaces up to 10 cm. width or girth or small articles not exceeding 0.10sqm in area white superior synthetic enamel such as LUXOL3, Hi-gloss apcolite superlac, DULUX specified brushing to give an even shade and including cleaning the surface of all dirt,dust and other foreign matter sand papering and stoping including cost of all materials, labour tools and plants etc. required for proper completion of the work.As per [PWD- 641 +642] , 39 Circle Lko |
| 18 | Centering & shuttering including strutting, propping etc. and removal of form for Upto foundation.As per DAR No.5.9.1 |
| 19 | Centering & shuttering including strutting, propping etc. and removal of form for plinth band,tie beam & top band.As per DAR No.5.9.5 |
| 20 | Centering & shuttering including strutting, propping etc. and removal of form for Column.As per DAR No.5.9.6 |
| 21 | Providing and fixing 110mm dia PVC pipe for drainage of rain water including cost of material complete in all respects.As per PWD SOR Material page no.4(31)] |