| 1 | ERRECTION OF 22KV H.T LINE |
| 2 | Erection of pole.Digging of pit,(ii) Laying of RCC muff (iii) Drilling of holes in X-bracing set, X-arms (iv) Erection of pole (v) fixing of insulator,X-arm, X-bracing set, (vi) fixing of Barbed wire, Danger plate (vii) filling of pit & Ramming i/c painting of pole D/Pole str. (Complete in all respect). |
| 3 | ERRECTION OF STAY SET |
| 4 | (i) Digging of pit (ii)fixing of stay rod (iii) Filling of pit (iv)Nozzeling & Tighting. |
| 5 | ERRECTION OF EARTHING |
| 6 | (i) Digging of pit (ii) fixing of G.I wire to the earth system, filling of pit. |
| 7 | Sagging ofACSR Conductor 6/1/3.35mm (Single wire). |
| 8 | Laying of conductor (i) stringing & sagging (ii) binding with insulator. |
| 9 | Sagging of G.I Wire for earth wire |
| 10 | Proving Protection wall around the double pole Str. In Cement concrete 1:5:10 size. |
| 11 | Erection of 22kV GO Switch. |
| 12 | MANNUAL CARRIAGE OF H.T LINE MATERIAL CONSIDERING AVERAGE DISTANCE 0.100 K.M. |
| 13 | Erection of 100KVA S/Stn. |
| 14 | Digging of pit for pole and earthing, drilling of holes in x-arm, preparation of plate form, Str. MemberC.I A.I. X-arm, knee bracing set, erection of D-pole, c.c.muff, erection of plate form, erection of x-arm, dropout fuse unit, lightning arrester, MCCB switch, L.T box, energy meter, erection of transformer, G.O switch, stay set, jumper earthing 3 sets, L.T cables, paintingetc. (Complete in all respect). |
| 15 | MANNUAL CARRIAGE OF H.T LINE MATERIAL CONSIDERING AVERAGE DISTANCE 0.100 K.M. |
| 16 | Providing Fencing around the Sub-station. |
| 17 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed within a lead of 50 m. All kinds of soil |
| 18 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering-All work up to plinth level: 1:4:3 (1 Cement: 4 coarse sand): 5 graded stone aggregate 40 num nominal size) |
| 19 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level 11.5.3 (1 cement: 1.5 coarse sand) 3 graded stone aggregate 20 mm nominal size) |
| 20 | Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
| 21 | Providing and fixing G1 chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 2 mm dia wire or nuts, bolts and washers as required complete as per the direction of Engineer-in-charge. Made of GI wire of dia 4 mm |
| 22 | Providing and fixing ISI marked M.S. pressed butt hinges bright finished with necessary screws etc. complete 100x35x1.90 mm |
| 23 | Providing and fixing 151 marked oxidised M5. sliding door bolts with nuts and screws etc. complete 250-16 mm |
| 24 | Erection of HT metering (CT/PT combine unit) |
| 25 | Loading /unloading charges of transformer & other s/stn. Material. |
| 26 | MATERIAL TO BE SUPPLIED BY CONTRACTOR (Subject to the non-availability of material at Divisional Store). |
| 27 | Prov. Cross Arm: [Channel Iron (100x50x5 mm),Length (2800) mm. |
| 28 | Prov. Cross Arm: [Channel Iron (100x50x5 mm),Length (1800) mm. |
| 29 | Prov. MS Channel Iron (75*40*5mm), length 2800mm*2Nos. For supporting CT/PT Unit. |
| 30 | Prov. MS Angle Iron (50*50*5mm), length 2800mm* 2Nos. |
| 31 | Prov. PVC Control Cable 2.5mm2 (1.1KV,12C, Hhr FRLS, Cu, Un-Screen) Cable for Energy Meter connection. |
| 32 | Prov. Sub station fitting (complete in all respect). |
| 33 | Prov. X-Bracing Set. |
| 34 | Prov. Disc Insulator Set (including Dead end clamp,Ballcleaves eye sockets, straight stapple & Bend Stapple etc.) |
| 35 | Prov. 22kV Pin Insulators with GI Pin. |
| 36 | Prov. 22kV GO Switch. |
| 37 | Prov. ACSR Conductor 6/1/3.35mm2 |
| 38 | Prov. HT stay set. |
| 39 | Prov. stay Wire (7/3.15mm) |
| 40 | Prov. Nuts & bolts. (off soze) |
| 41 | Prov. Aluminium paint. |
| 42 | Prov. Stay clamp |
| 43 | Prov. Egg Insulator. |
| 44 | Prov. Barbed wire. |
| 45 | Prov. Earthing Set (HT) with charcoal & Salt. (complete in all respect.) |
| 46 | Prov. Earthing Set (S/Stn.) with charcoal & Salt. (complete in all respect.) |