| 1 | Description of items and specification ofwork to be excuted. |
| 2 | Clearing jungle including uprooting of rank vegetation, grass, brush wood,trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared. |
| 3 | Demolishing stone rubble masonrymanually/ by mechanical means including stacking of serviceablematerial and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge :In lime mortar |
| 4 | R.R Stone masonry of bastion and wall with lime, Surkhi, Mortar 1:1:1 (1 lime: 1 C-Send, 1 Surkhi) mixed with adhesive material like gud, Belgiri and babool gum including curing 30% old available at site & 70% new stone etc. complete |
| 5 | Recess pointing on R. R.Stone masonry of the structure with lime mortar 1:1:1 (1 lime : 1 C. Sand (with less than 8% clay content) : 1 brick surkhi) mortar to be prepared in garath mixed with adhesive material like gud, belgiri, gond, etc. complete as directed by engineer in-charge. |
| 6 | Dismantling stone slab flooring lime mortar including stacking of serviceable material and disposal of unserviceable material within 50 metres lead. |
| 7 | Demolishing lime concrete manually/ by mechanical means and disposal of material within 50 metres lead as per direction of Engineer- in-charge. |
| 8 | Dismantling 20 mm thick old lime plaster or raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead. |
| 9 | Lime plaster 30 mm thick in lime shurkhi mortar 1:1:1: (1lime:1surkhi:1C.send) in two coat mixed with gud, belgiri, gum,methi etc. complete. |
| 10 | Providing & Fixing 70 to 75 mm thick Bijoliya stone flooring over 20 mm thick base of lime mortar 1:1:1 (1lime:1Surkhi:1C.sand) mortar with an admixture of pigment to match the shade of stone |
| 11 | Providing & laying lime concrete with graded stone aggrigate 20 mm nominal size and 50% lime mortar 1:1:1 (1lime:1C.Sand:1Surkhi) rammed and finished with gur, gum and belgiri treatment etc. complete. |
| 12 | Disposal of building rubbish / malba /similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved. |
| 13 | Providing and fixing double scaffolding system (cup lock type) on the exterior side of building/structure, upto 25 metre height, above ground level, including additional rows of scaffolding in stepped manner as per requirement of site, made with 40 mm dia M.S. tube, placed 1.5 metre centre to centre, horizontal & vertical tubes joint with cup & lock system with M.S.Tubes, M.S. tube challis, M.S.clamps and staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for execution ofwork cleaning and/ or pointing and / or applying chemical and removingin thereafter. The scaffolding system shall be stiffened with bracings, runners, connecting with the building etc, wherever required, if feasible, for inspection or work at required locations with essential saftery features for the workmen etc., complete as per directions and approval of Engineer-in-charge. Note:- (1) The elevational area of the scaffolding shall be measured for payment purpose (2) The payment will be made once only for execution of all items for such works.\" |
| 14 | Supply of water tanker for masonry work etc. complete |