| 1 | Picking the existing surface 3 to 5 cm deep removal of picked up staff to the side berms and using the useful metal to the road hand packing to camber sectioning levelling etc.,complete as per including labour charges for picking and other tools and plants etc., complete as per standard specifications. 404 ofMORTH |
| 2 | Providing and Laying Wet Mix Mecadam using 0.396m3 of 45-22.40mm graded metal, 0.528m3 of 22.40-2.36mm graded metal and 0.396m3 of 2.36 and below size graded metal premixed with water to a densemass on a prepared subgrade / base to template in uniform 15cm Consolidated thickness and consolidation with Vibratory roller of 8 to 10 tonne capacity in stages to proper grade and camber rolling with protecting edges, etc completing with MORTH specification Clause 406. |
| 3 | Providing and layingPriming coat over WBM/WMM surface using 7Kg ofEmulsion Bitumen (SS1) for 10 Sq.m for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinary, fule and all other incidental chrages etc., complte as for clause 502 ofMORTH Rev-5. |
| 4 | Providing and layingTack coat over WBM/WMM surface (Preaped with primer) using 2.50Kg ofBitu Emulsion (RS1)for 10 Sq.m for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinary, fule and all other incidental chrages etc., complte as for clause 503 ofMORTH Rev-5. |
| 5 | Providing and laying 50 mm conslidated thick Dense Bituminuous macadam using 0.24 cum of 26.50-13.20 mm,0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm and below and with 53.20kg of vt 30 bitumen premixing 10 sqm including cost and conveyance of all materials to CMP site,heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 tons capacity,conveying the mix by tipper trucks to work site,spreading the mixuniform thickness of 50mm with paver to the specified grade and cross sections and compaction byvibratory/ pneumapic roller to the required density etc., including labour for accending to pavor at sites etc., including hire charges and fuel chargesfor 20-30 CMP with bitumen tipper trucks, paver finisher/9 m paver finisher,vibratory/ pneumapic rollers and all other tools and plant required including to all other incidental charges etc., complete as per specification using CMP as clause 505MORTH Rev-5. |
| 6 | Providing and layingBituminous concrete to 30mm thick using 0.13 cum of 19.00-9.50 mm, 0.17cum of 9.50-2.36 mm and 0.26cum of 2.36mm and blow with 45.27 kgs of 60/70 Grade Bulk bitumen and 5.03 kg of shredded Plastic waste for premixing for 10 sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20–30 tonnes capacity, conveying the mix by tipper trucks to paver site spreading the mix to uniform thickness of 30 mm with mechanical Paver to the specified grades and cross sections and consolidated by 80 - 10 tonne vibratory/ pneumatic roller to the required density etc., including labor for attending to paver site etc., including hire charges and fuel charges for 20 – 30tCMP with bitumen boiler, tipper trucks, paver finisher,/ 9m paver finisher, vibratory/ pneumatic rollers and all other tools and plant required including fule and all other incidental charges etc., complete as per specification using CMP as for clause 507of MORTH |
| 7 | Providing & laying of hot applied thermoplastic compound of 2.50mm thick reflecting glass beads @ 250 grammes / square metre area thickness 2.50mm exculives surface applied glass beads as per IRC certified 35. |
| 8 | Earthwork excavationfor foundation and depositingon Bank with metal lead of 10m and initial of 2m in Hard stiff clay, stiff black cotton,hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders including all labour chargesetc.completeas per SS 20 BTNDSS No 23, 24 VI(S2),VI, VII.9 & 10 |
| 9 | Cement concrete of mix 1:4:8 (one part of cement, andfour part of sand, andeaight part ofcoarse aggregate) using hard broken granite stone jelly of 40 mm gauge for foundation levelling course, including shuttering, dewatering wherever necessary and laid I layers of not more than 15cm thick complete complying with standard specifications and drawings and as directed by the departmental Engineers including all cost & conveyance of materials laying curing etc., complete as per TNDSS No 28V,VI(S2),VI(S54) and VII |
| 10 | Supplying and erecting centering for sides and soffits including supports and srtutting upto 3.29mm height for plane surfaces in all floors with cross bracings using miled steel sheets of size 30cm x 60cm and 10 gauge stiffened welded with miled steel sheets of size 25mm x 25mm x 3mm for boarding and laid over silver oak (country wood).Joists of size 10cm x 6.5cm dia spaced at about90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced 75cm centre to centre etc., complete complying with standard specification ans as directed for the following items as per TNDSS No 30 & 86 |
| 11 | Plain Cement Concrete 1:2:4 Mix (one part cement, two part sand and four part of aggrigate) using 20mm size ISS HBG metal machine crushed from approved quarry including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete. Complying with std. specifications.. complete as per TNDSS No.24 |
| 12 | Plastering in Cement Mortor 1:5 Mix (one Cement, five sand) 20mm thick including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete. Complying with std. specifications. |