| 1 | Supplying and fixing Cable jointing kit for 11 KV (Earthed) grade cable for outdoor termination heat shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured aluminium conductor cable of size 240 sqmm to 300 sqmm |
| 2 | Supply, laying, jointing, connecting and testing XLPE insulated, screened, PVC bedded, galvanized steel strip or wire armoured electric power cable (heavy duty) with stranded aluminium conductor, 11000 volts grade earthed system of size 300 Sqmm 3 core conforming to IS-7098 (Part-II) 1985laid in trenches, in floor, in duct, through pipes or along the polecomplete all as specified and directed |
| 3 | Shifting of retrieved serviceable cable in any length recd completeto reqd site within 200 mtr and Relaying of 11 KV HT Cable off size carefully at diff route in trenches including connecting to existing/new system incl testing, commissioning complete all as specified and directed by Engineer-in-Charge.Note: The excavation and related civil wk will be measured and paid separately. |
| 4 | Takingout HT cable off sizes from trench & taking down from pole including disconnecting all electrical connections and keepingserviceable cable in safe custody for re-use to re-route existing HT feeder site within 200mtr incl taking out existing PCC cabe cover and setting aside neatly for re-use.Note: The excavation and related civil wk will be measured and paid separately. Contractor shall have to S&F new HT cable within overall quoted rates, if existing cable gets damaged due to negligence, mishandling at site. |
| 5 | Supply and fixing galvanised pipe light grade of 100 mm dia bore for passing of cable fixed to poles/walls/laid under floor complete with and including fittings as required compete all as specified and directed by Engr-in-charge. |
| 6 | Supply & fix new MS Cross arms, bracing,supports, clamps, anti climbing device and back plates fabricated from structural steel section including nuts, bolts, washers with reqdmech working/ process i.e. cutting, welding, bending, cold or hot, drilling holes, grinding or bolt in any shape or size including 2 coats of aluminium paint over one coat of red oxide including taking out unserviceablecomplete all as specified and directed by Engineer-in-charge. Note : Unexposed surface shall be given one coat of primer only. |
| 7 | Material and labour for fixing cable route indicators made of PCC (1:3:6) of size 150 x 150 x 900 mm duly engraved “HT CABLE / HT JOINT” coloured with two coats of synthetic paint in brownfixed 300mm below ground level with reqd PCC all as specified and directed. |
| 8 | Excavation in trenches in soft/loose soil not exceeding 1.50 mtr wide and depth not exceeding 1.50 mtr in depth for cable trench, poles and gettingout complete all as specifiedand directed by Engineer-in-Charge. |
| 9 | Excavation in trenches in soft/loose soil not exceeding 1.50 mtr wide and depth exceeding 1.50 mtr in depth for fixing of poles and gettingout complete all as specifiedand directed by Engineer-in-Charge. |
| 10 | Returing, filling in, including spreading, leveling watering and well ramming inlayers not exceeding 25 cms thick each layer compete all as specified and directed by Engineer-in-Charge. |
| 11 | Removal of surplus soil to a distance not exceeding 50 mtr and depositing where directed at a level not exceeding 1.5 mtr above the starting point completeall as specified and directed by Engr-in-charge. |
| 12 | Material and labour for sand cushioning with a layer of sand 8cm thick before laying of cable and 15 cm thick after laying of cable and punned down to thicknes of 18cm in trenches complete all as specified.(Note: Punned thickness of 18 cm will be measured) |
| 13 | Supply & laying un-reinforced precast concrete cable cover, class HV, type I, flat, size 300mm x 180mm x 40mm laid flat in trenches over the cable with the length of brickperpendicular to the directionof cable length, adjacent/abutting each other complete all as specified and directed by Engineer-in-charge. |
| 14 | Relaying of existing retrieved bricks/PCC cover during excavation within 200mtr laid in trenches for cable protection perpendicular to the direction of cable length, adjacent abutting each other complete all as specified and directed. |
| 15 | Supply, and errecting in position pre-stressed concrete pole 11 metre long, cross section 152mm x 152mm at top and 152mm x 260mm at bottom class-9 including painting of poles with two coats of synthetic enamel paint in alternate black & white strips upto 1.5mtr height from top of PCC coping over a coat of primer, and numbering of poles with synthetic enamel paint whitein 30mm high letters over yellow base of size 150mm x 230mm complete all as specified and directed.Note :- PCC and earth work shall be measured & paid for separately |
| 16 | Material and labourfor PCC work (1:4:8)type D-2 using 40 mm graded stone aggregatein foundation of electric pole, etc. including necessary form work and fare finish to exposed surfaces without using extra cement etc. complete all as specified. |
| 17 | M & L for PCC work(1:3:6) type C-2 using 40 mm graded mechanically crushed stone aggregate as in foundationof poles including necessary form work and fare finish to exposed surfaces without using extra cement etc. complete all as specified. |
| 18 | Material and labourfor PCC work (1:2:4)type B-2 using 40 mm graded stone aggregatein coping of electric pole, etc. including necessary form work and fare finish to exposed surfaces without using extra cement etc. complete all as specified. |